Kawasaki Machida Line (Okuma Niiba district)
Last update date April 1, 2024
The city planning road Kawasaki Machida Line is a city planning road with a length of about 20 km starting from Yamu 4-chome, Tsurumi-ku and ending in Onta-cho, Aoba-ku.
Of these, the Okuma / Niiba districts have been conducting business in Niiba-cho, Kohoku-ku since 1996.
Improvement work was carried out at the Niiba Crossroads intersection and Otake intersection, and right turn lanes and bus bays were maintained. In other sections, we are proceeding with land acquisition and other activities.
Business Districts | Kawasaki Machida Line (Okuma Niiba district) |
---|---|
Section | Shinba-cho, Kohoku-ku |
Fiscal year | FY2008 to FY12 |
Scale | Extended about 730m, standard width 22m |
Improvement effect | ◆Improvement of transportation convenience and enhancement of transportation functions |
Business Progress Rate※ | 20% (expected at the end of FY2022) |
Land acquisition rate※ | 48% (expected at the end of FY2022) |
Current construction Contract details | No construction is currently under contract. |
Related information | ◆You can look at administrative map information such as city planning from "Yokohama-shi administration map reporting system" (outside site). |
※Business progress rate is shown as the execution rate of total project cost.
※The land acquisition rate indicates the ratio of the acquired area among the areas where the business has been approved.
■Business segments
Location map
■Photographs of current status
Photo 1
Photo 2
For inquiries to this page
Road and Highway Bureau Construction Department, Construction Department
Phone: 045-671-3521
Phone: 045-671-3521
Fax: 045-663-8993
Email address: do-kensetsu@city.yokohama.jp
Page ID: 701-831-803