Sakuragi Higashitotsuka Line (Hirato district)

Last update date November 1, 2023

The city planning road Sakuragi Higashitotsuka Line is an arterial road from 1-chome, Sakuragicho, Naka-ku to Naze-cho, Totsuka-ku.
Of these, the Hirato district is a section of about 670m in length from Hirado 5-chome, Totsuka-ku to Hirado-cho, Totsuka-ku, and has been operating since 1989.

Overview of Sakuragi Higashitotsuka Line (Hirato district)
Business DistrictsSakuragi Higashitotsuka Line (Hirato district)
SectionHirado 5-chome, Totsuka-ku, Hirado-cho, Totsuka-ku
Fiscal yearFiscal 2001 to 9
ScaleExtended about 670m Standard width 24m
Improvement effect
  • Improvement of transportation convenience and enhancement of transportation functions

It is expected that the city area will be integrated by connecting the Higashi Totsuka Station area and the suburbs from the Minato Mirai 21 district of the seaside area.

  • Traffic safety measures for pre-school children

It is expected that passing traffic flowing into residential roads will be suppressed and that the maintenance effect can be demonstrated as a traffic safety measure.

Business Progress Rate※45% (expected at the end of FY2022)
Land acquisition rate※77% (expected at the end of FY2022)
Current construction
Contract details

◆City planning road Sakuragi Higashitotsuka Line (Hirato district) Street maintenance work (city road retaining wall, etc.)
 Construction site: 5-960, Hirado, Totsuka-ku and others
 Contract date: January 24, 2023
 Contract partner: KEITH Co., Ltd.
◆City planning road Sakuragi Higashitotsuka Line (Hirato district) Street maintenance work (Part 3)
 Construction site: From 5-960 Hirado, Totsuka-ku to 2259 Hiradocho
 Contract date: August 23, 2023
 Contract partner: Okino Construction Co., Ltd.

About publication of winning bidder decision report

August 10, 2023
About city planning road Sakuragi Higashitotsuka Line (Hirato district) street maintenance construction, we announce successful bid person decision report as follows.
Successful bidder decision report (PDF: 798KB)
In addition, about procurement notice, it is published in Yokohama-shi homepage "bid of bid".
You can look at page of evaluation committee such as Yokohama-shi road tunnel construction technical proposals from the next link.
Yokohama City Road Tunnel Construction Technical Proposal Evaluation Committee

Related information

You can look at administrative map information such as city planning from Yokohama-shi administration map reporting system (outside site).

※Business progress rate is shown as the execution rate of total project cost.
※The land acquisition rate indicates the ratio of the acquired area among the areas where the business has been approved.

Image of the business section being filled out

Business segments

Photographs of current status
Pit entrance (Yamaya side)Intermediate portion

Photo of the pit entrance (Yamaya side)


Photo of the middle part



In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

For inquiries to this page

Road and Highway Bureau Construction Department, Construction Department

Phone: 045-671-3521

Phone: 045-671-3521

Fax: 045-663-8993

Email address: do-kensetsu@city.yokohama.jp

Return to the previous page

Page ID: 817-622-469