Kamoi Kamiiida Line (Motoshuku, Futamatagawa) (Sachigaoka)

Last Updated November 1, 2024

The Kamoi Kamiiida Line is a 13,120m urban planning road that starts in Ikebe-cho, Tsuzuki-ku and ends in Kamiiida-cho, Izumi-ku.
Of these, the Motoshuku, Futamatagawa and Sachigaoka districts are districts from Honjuku-cho, Asahi-ku to Sachigaoka via Futamatagawa Station, and have been operating since 1988.
On March 28, 2023, a section of about 1 km from Sachigaoka to near Futamatagawa Station was opened.
We will continue to proceed with construction work while proceeding with land acquisition.

Business Overview
Business districtKamoi Kamiiida Line (Motoshuku, Futamatagawa) (Sachigaoka)
SectionFrom Honjuku-cho, Asahi-ku to Sachigaoka
Fiscal yearShowa 63-Reiwa 7
Scale

Approximately 1,630m in length
Standard width: 18m (2 lanes)

Maintenance effect

Improvement of traffic convenience and enhancement of transportation functions

  • Communication with the Nakata Sachigaoka Line, Hodogaya Futamatagawa Line and Hodogaya Bypass (Minamihonjyuku Interchange) will be strengthened, and access to stations will be improved to improve transportation convenience.

Optimizing traffic flow

  • By converting traffic flowing into residential roads in the area to the Kamoi Kamiiida Line, traffic flow can be optimized by ensuring pedestrian safety and facilitating traffic.
Business progress rate※93% (end of FY2023)
Land acquisition rate※

99% (end of FY2023)

Current construction
Contract details

◆Urban planning road Kamoi Kamiiida Line (Motoshuku, Futamatagawa district) Street maintenance work (Part 37)
 Construction site: From 51-18 Sachigaoka, Asahi-ku to 78-31, Honjuku-cho
 Contract date: May 25, 2023
 Construction period: Scheduled for December 2024
 The other party to the contract: Chiyoda Construction Co., Ltd.
◆Urban planning road Kamoi Kamiiida Line (Motoshuku, Futamatagawa district) Street maintenance work (Part 39)
 Construction site: From 2-5-7 Futamatagawa, Asahi-ku to 118-11 Honjuku-cho
 Contract date: June 3, 2024
 Construction period: Scheduled for December 2024
 The other party to the contract: Techno Japan Co., Ltd.
◆Urban planning road Kamoi Kamiiida Line (Motoshuku, Futamatagawa district) Street maintenance work (Part 40)
 Construction site: From 2-47-3 Futamatagawa, Asahi-ku to 78-31 Honjuku-cho
 Contract date: June 10, 2024
 Construction period: Scheduled for March 2025
 The other party to the contract: Doshida Construction Co., Ltd.

Related information

※The land acquisition rate shows the ratio of the acquired area among the areas that have been approved for business.
※The business progress rate is shown as the execution rate of total operating expenses.


Location map

You may need a separate PDF reader to open a PDF file.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

Inquiries to this page

Construction Division, Construction Department, Road and Highway Bureau Construction Department

Telephone: 045-671-3521

Telephone: 045-671-3521

Fax: 045-663-8993

Email address: do-kensetsu@city.yokohama.lg.jp

Return to the previous page

Page ID: 428-335-803

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews