Kamoi Kamiiida Line (Motoshuku and Futamatagawa) (Sachigaoka district)

Last update date April 1, 2024

The Kamoi Kamiiida Line is a city planning road with a length of about 13,120m, starting from Ikebe-cho, Tsuzuki-ku and ending in Kamiiida-cho, Izumi-ku.
Of these, the Motoshuku / Futamatagawa districts and Sachigaoka districts have been operating since 1988 in the districts from Honjuku-cho, Asahi-ku to Sachigaoka via front of Futamatagawa Station.
On March 28, 2023, a section of about 1 km from Sachigaoka to the vicinity of Futamatagawa Station was opened.
We will continue to work on land acquisition while proceeding with land acquisition.

Business Overview
Business DistrictsKamoi Kamiiida Line (Motoshuku and Futamatagawa districts) (Sachigaoka district)
SectionHonjuku-cho, Asahi-ku-Sachigaoka
Fiscal yearFY2006 to FY2007
Scale

Length: 1,630m
Standard width: 18m (2 lanes)

Improvement effect

Improvement of transportation convenience and enhancement of transportation functions

  • Communication with the Nakata Sachigaoka Line, Hodogaya Futamatagawa Line and Hodogaya Bypass (Minamihonjyuku Interchange) will be strengthened, and traffic convenience will be improved by improving access to the station.

Optimization of traffic flow

  • By switching traffic flowing into the living roads in the area to the Kamoi Kamiiida Line, traffic flows can be optimized, such as ensuring pedestrian safety and smooth traffic flow.
Business Progress Rate※93% (expected at the end of FY2023)
Land acquisition rate※

99% (expected at the end of FY2023)

Current construction
Contract details

◆Urban planning road Kamoi Kamiiida Line (Motoshuku and Futamatagawa districts) Street maintenance (part 34)
 Construction site: 2-52, Futamatagawa, Asahi-ku to 117-10, Honjuku-cho
 Contract date: March 30, 2023
 Construction period: Scheduled for April 30, 2024
 Contract partner: Nara Construction Co., Ltd.
◆Kamoi Kamiiida Line (Motoshuku and Futamatagawa districts) Street maintenance work (part 35) (Building work)
 Construction site: 2-52, Futamatagawa, Asahi-ku-ku From 42 to 47-25
 Contract date: June 5, 2023
 Construction period: Scheduled for April 30, 2024
 Contract partner: Wado Construction Co., Ltd.
◆Kamoi Kamiiida Line (Motoshuku and Futamatagawa districts) Street maintenance work (Part 36) (Elevation equipment construction)
 Construction site: 2-52, Futamatagawa, Asahi-ku-ku From 42 to 47-25
 Contract date: August 23, 2023
 Construction period: Scheduled for April 30, 2024
 Contract partner: Kanagawa Sales Office, Chuo Elevator Industry Co., Ltd.
◆Urban planning road Kamoi Kamiiida Line (Motoshuku and Futamatagawa districts) Street maintenance work (part 37)
 Construction site: From 51-18 Sachigaoka, Asahi-ku to 78-31, Honjuku-cho
 Contract date: May 25, 2023
 Construction period: Scheduled for August 30, 2024
 Contract partner: Chiyoda Construction Co., Ltd.

Related information

※The land acquisition rate indicates the ratio of the acquired area among the areas where the business has been approved.
※Business progress rate is shown as the execution rate of total project cost.


Location map

In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

For inquiries to this page

Road and Highway Bureau Construction Department, Construction Department

Phone: 045-671-3521

Phone: 045-671-3521

Fax: 045-663-8993

Email address: do-kensetsu@city.yokohama.jp

Return to the previous page