Prefectural Road Seya Kashiwao (Okazu district)
Last update date April 1, 2024
In the prefectural road Seya Kashiwao (Okazu district) road improvement project, a right turn lane, bus bay and sidewalk along with the maintenance of the city planning road Nakata Sachigaoka Line (Okazu area) to eliminate traffic congestion at intersections in this project area. We plan pedestrian environment maintenance.
Business Districts | Prefectural Road Seya Kashiwao (Okazu district) |
---|---|
Section | Okazu-cho, Izumi-ku to Kamiyabe-cho, Totsuka-ku |
Fiscal year | Fiscal 2001 to 9 |
Scale | Extended about 212m, standard width 13.25m |
Land acquisition rate※ | 80% (Estimated at the end of FY2023) |
Business Progress Rate※ | 82% (expected at the end of FY2023) |
Current construction Contract details | No construction is currently under contract. |
Related information | ◆You can look at administrative map information such as city planning from Yokohama-shi administration map information system (outside site) (outside site). |
※The land acquisition rate indicates the ratio of the acquired area among the areas where the business has been approved.
※Business progress rate is shown as the execution rate of total project cost.
Business segments
For Yayoidai
For Tozuka
For inquiries to this page
Road and Highway Bureau Construction Department, Construction Department
Phone: 045-671-3521
Phone: 045-671-3521
Fax: 045-663-8993
Email address: do-kensetsu@city.yokohama.jp
Page ID: 635-126-409