Daejeon Kanagawa Line (Baba Area)

Last Updated April 1, 2022

The city planning road Ota Kanagawa Line is a city planning road with a length of about 7.0 km from the Kawasaki city boundary in Komaoka-cho, Tsurumi-ku to Koyasudori, Kanagawa-ku, and is an arterial road connecting the coastal and inland areas of the city.
Of these, the Baba area is connected to the Babadashi entrance of the Yokohama Ring Road Yokohama North Line, and by maintaining this section, smooth traffic, alleviate traffic congestion at the Horyu-ji Temple intersection and the inner road intersection, and improve pedestrian safety. I will do it.

Business Overview
Business districtDaejeon Kanagawa Line (Baba Area)
SectionKamimiya 1-chome ground, Tsurumi-ku to Nishi-Terao 1-chome ground, Kanagawa-ku
Fiscal yearFiscal 2003-Reiwa 3
ScaleApproximately 955m in length, standard width 20 to 26m (4 lanes)
Maintenance effect◆Facilitating traffic
By widening the roadway to four lanes, traffic congestion around the intersection will be eased and traffic will be facilitated.
◆Improvement of pedestrian safety and comfort
Pedestrians and bicycles can pass safely and comfortably by maintaining sidewalks on both sides of the road along with road widening.
Business progress rate※99% (estimated as of the end of FY2021)
Land acquisition rate※

100% (estimated as of the end of FY2021)

Current construction
Contract details

There is no construction currently under contract.

Construction briefing

◆July 7, 14 and 15, 2016
Urban planning road Ota Kanagawa Line (Baba district) street maintenance for residents of a part of Nishi Terao 1-chome, Kanagawa-ku, Baba 1-chome, Tsurumi-ku and a part of Higashi-Terao 1-chome adjacent to the construction We held a briefing on the construction plan of construction work (Part 14). He also explained the connection plan with the surrounding living roads along with the Ota Kanagawa Line maintenance from the vicinity of the bus stop to the inner road intersection in Watauchida.
Construction briefing materials (PDF: 4,896KB)
Explanation document of connection plan with peripheral connection plan (PDF: 4,784KB)
※Regarding the connection plan with the peripheral connection plan, please contact us.
Please contact the Road and Highway Bureau Yokohama Ring Road Adjustment Section (045-671-2780).
◆November 8, 2016
About construction plan of city planning road Ota Kanagawa Line (Baba district) street maintenance construction (part 13) targeting at a part of Baba 1-chome, Tsurumi-ku and a part of 1-chome Nishiderao, Kanagawa-ku adjacent to the construction A briefing session was held.
Construction briefing materials (PDF: 11,626KB)

Related information

◆You can look at administrative map information such as city planning from "Yokohama-shi administrative map reporting system (outside site)".

※The business progress rate is shown as the execution rate of total operating expenses.
※The land acquisition rate shows the ratio of the acquired area among the areas that have been approved for business.
■Business Section

Business floor plan
Business Section

■Photographs

1, Baba, Tsurumi-ku
Photo 3 (1-chome, Baba, Tsurumi-ku)

You may need a separate PDF reader to open a PDF file.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

Inquiries to this page

Construction Division, Construction Department, Road and Highway Bureau Construction Department

Telephone: 045-671-3521

Telephone: 045-671-3521

Fax: 045-663-8993

Email address: do-kensetsu@city.yokohama.lg.jp

Return to the previous page

Page ID: 788-502-276

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews