Text version of Totsuka Station, Yokohama City Road Specific Business Plan

Last Updated November 14, 2024

Around Totsuka Station, Yokohama City Area Road Specific Business Plan June 2008 Formulated

1.Introduction

In December 2006, the "Law Concerning the Promotion of Smooth Movement of Elderly and Disabled Persons" (commonly known as the new barrier-free law) was enforced. In response to this, Yokohama City is developing a basic concept around major stations and in areas where public facilities are concentrated.
In March 2008, we formulated the Basic Concept for Barrier-Free Area around Totsuka Station, which is located in the center of Totsuka Ward and is home to business, commerce, public facilities, welfare and medical facilities.

In order to realize this basic concept, Totsuka Ward and Road and Highway Bureau have formulated a Road-Specific Business Plan that specifies the details of the project and the expected period of implementation. In the future, we will implement the project based on this plan.

2.New Barrier-Free Law

(1) What is the New Barrier-Free Law?

The new barrier-free law is designed not only for the elderly and the physically handicapped, but also for all persons with disabilities, pregnant women, injured persons, etc., including intellectual, mental and developmental disabilities, as well as buildings and public transportation, as well as off-street parking lots and city parks. The purpose is to reduce the burden on the body involved in transportation and to improve the convenience and safety of transportation.
In addition, we will promote barrier-free through the following two major pillars.

  • Promotion of barrier-free public transportation, buildings, and public facilities
    When constructing or introducing public transportation (passenger facilities such as stations and bus terminals, vehicles such as railway vehicles and buses), as well as specific buildings, roads, off-street parking lots and city parks, each company / building We obligate facility installation managers such as owners to comply with the "barrier-free standards (standards for facilitation such as movement)" established for each facility. In addition, efforts are imposed on these existing facilities to comply with the standards.
  • Promotion of barrier-free facilities in priority areas
    Municipalities are responsible for public transportation, buildings, roads, off-street parking in areas centered on passenger facilities such as railway stations, and in areas where facilities used by the elderly and disabled are gathered (important maintenance areas). In order to promote barrier-free parking, city parks, traffic lights, etc. in a focused and integrated manner, we can create a "barrier-free basic concept".

(2) What is the Basic Concept of Barrier-Free?

The barrier-free basic concept focuses on barrier-free passenger facilities such as railway stations, public facilities such as roads and parks, and public buildings used by the elderly, disabled, etc. in priority maintenance areas. In order to promote integrally, the area of the priority maintenance area, the route (life-related route) for barrier-free, and the contents of the business to be implemented for barrier-free.

In the area around Totsuka Station, a council consisting of academics, citizens such as the elderly and disabled, related businesses and administrative organizations to promote "barrier-free priority maintenance areas". After repeated examinations at the preparatory meeting, the basic barrier-free concept was formulated.

In addition, after basic design development, each company makes concrete business plan based on basic design and, for the purpose of 2010, will carry out barrier-free in important maintenance district.

3.Priority maintenance areas and routes for barrier-free

In the "Basic Concept for Barrier-Free around Totsuka Station" formulated in April 2008, "Life-related routes (A)" and "Life-related routes (B)" are defined.

Life-related routes (A)

  • Of the lifestyle-related routes, routes that carry out maintenance in accordance with the standards for facilitating movement based on the law
  • At present, maintenance based on maintenance standard of town development regulations of Yokohama-shi welfare is made, and route which does not particularly hinder smooth movement of elderly person, person with a disability.

Life-related routes (B)

  • Among the life-related routes, taking into account the road function and role of the route, the conditions of urbanization and topography, etc., and actively apply it after fully recognizing the concept of the standard for facilitating movement based on the law. Routes that carry out maintenance for barrier-free by applying

4.What is the Road Specific Business Plan?

With "road specific business plan", road manager establishes the following matters along basic design in important point maintenance district established in basic design.

  • "Road section" that implements road identification projects
  • "Contents and scheduled implementation period" of road-specific projects to be implemented for each section
  • Other "important matters to be considered" when implementing road-specific projects
    *Priority areas: Including the location of life-related facilities (stations, government offices, welfare facilities, other facilities), it is particularly necessary that the movement between each facility is usually performed on foot, and that projects to facilitate movement etc. be implemented. Area recognized.

5.Maintenance Policy

(1) Target year

In principle, maintenance will be carried out by 2010. In addition, there are routes that will be after 2011 due to connection with other businesses.

(2) Setting the maintenance level

In consideration of regional characteristics and surrounding roadside conditions, we will set a level of maintenance such as full or partial renovation. In addition, we plan cooperation and consistency with other companies to carry out effective maintenance and consider continuity of walking space.

(3) Main maintenance standards of the guidelines for smooth maintenance of road movement, etc.

We carry out maintenance based on "facilitation maintenance guidelines such as movement of road" and "town development regulations facility maintenance manual of Yokohama-shi welfare".

6.Maintenance plan

We show plan as follows about route to carry out business to plan barrier-free mainly, integrally.
In addition, in order to make the plan more effective, the plan may be reviewed through coordination with other businesses or budgets.

(1) Business plan for individual routes

(2) Routes subject to road specific business plans

Target routes and business plans are as follows:

Life-related routes (A)

Route name

(1)Station East Exit Pedestrian Deck (3019 Yabe in front of Ofuna Station)

Business Section

JR Totsuka Station-Prefectural Road Ofuna Station Yabe

Business extension

50m

Project implementation period

2008

Maintenance Policy

[Route] : This is the main route from Totsuka Station to East Exit Station Square and the eastern area of the station.
[Issues] : Some parts of the block for guiding visually impaired persons are damaged or uninstalled.
[Measures] : New construction and renovation of blocks for guiding visually impaired persons on the deck.

Maintenance items

Continuous installation of route guidance 30m
Continuous laying and repair of route guidance 70m
Life-related routes (B)

Route name

(2)National highway No. 1 (large railroad crossing-Ohashi) (Prefectural road Yokohama Kanagawa 1235)

Business Section

JR Totsuka Station-Prefectural Road Ofuna Station Yabe

Business extension

80m

Project implementation period

2008

Maintenance Policy

[Route] : This is the main route from Totsuka Station East Exit to Tozuka Kyoritsu No. 2 Hospital.
[Issues] : The width of the sidewalk of the Ohashi Bridge is narrow, and there are places where the longitudinal slope is tight at the edge of the bridge.
[Measures] : Widen the sidewalk, semi-flat, and repair the slope at the end. In addition, renovation of steps and slope at intersections, renovation of pavements, and new construction and renovation of blocks for guiding visually impaired people will be performed.

Maintenance items

Securing pedestrian spaces
Width of sidewalk 100m
Renovation of road structure
Partial renovation of sidewalk 5 renovation steps and slope
Partial renovation of sidewalk pavement renovation 190m2
Partial renovation of sidewalk renovation of drainage facilities 4
Laying and renovation of blocks for guiding visually impaired persons
6 new installations at intersections, etc.
Partial laying and renovation at intersections, etc. 4 locations
Life-related routes (B)

Route name

(3)In front of Tozuka Kyoritsu No. 2 Hospital (Yabe 521)

Business Section

Yoshida Ohashi Intersection-Tozuka Kyoritsu No. 2 Hospital

Business extension

90m

Project implementation period

Fiscal 2008 - Fiscal 2021

Maintenance Policy

[Route] : This route connects Totsuka Station East Exit to Tozuka Kyoritsu No. 2 Hospital via the Yoshida Ohashi intersection on National Route 1.
[Issues] : There are places where the steps and slopes are tight at the intersection.
[Measures] : Renovation of steps and slopes at intersections, and renovation of blocks for guiding visually impaired people.

Maintenance items

Renovation of road structure
Partial renovation of the sidewalk, renovation of steps and slopes
Partial renovation of sidewalk and pavement renovation 10m2
Partial renovation of sidewalks and renovation of drainage facilities
Laying and renovation of blocks for guiding visually impaired persons
Two parts laying and renovations at intersections
Life-related routes (A)

Route name

(4)(Tokyo) Kaminagaya Totsuka Line (3019 Yabe in front of the prefectural road Ofuna Station)

Business Section

Station East Exit Plaza Exit Intersection - Station East Exit Entrance Intersection

Business extension

140m

Project implementation period

From FY2008 to FY2022

Maintenance Policy

[Route] : This is the main route from Totsuka Station East Exit to the northeast area (toward National Route 1).
[Issues] : There are places where blocks for guiding the visually impaired are not installed, and places where the steps and rubbing gradients are tight at intersections.
[Measures] : Renovation of steps and gradients at intersections and new construction and renovation of blocks for guiding visually impaired people. In addition, a new route guidance for the visually impaired will be provided between the East Exit station square and the general car rotary.

Maintenance items

Securing pedestrian spaces
Width of the sidewalk 10m
Renovation of road structure
Partial renovation of sidewalk 12 renovation of steps and slope
Partial renovation of sidewalk pavement renovation 300m2
Partial renovation of sidewalks 9 renovation of drainage facilities
Laying and renovation of blocks for guiding visually impaired persons
Continuous installation of route guidance 80m
Three new installations at intersections, etc.
Partial laying and renovation at intersections, etc. 7 locations
Life-related routes (B)

Route name

(5)Prefectural road Ofuna Station Yabe (3019 Yabe in front of prefectural road Ofuna Station)

Business Section

Station East Exit Plaza Exit Intersection-Tozuka Prefectural Tax Office Entrance

Business extension

290m

Project implementation period

From FY2008 to FY2022

Maintenance Policy

[Route] : This is the main route from Totsuka Station East Exit to Tozuka Prefectural Tax Office.
[Issues] : There are sections where blocks for guiding visually impaired persons are not installed, steps at intersections and steep slopes are tight.
[Measures] : Renovation of steps and gradients at intersections and new construction and renovation of blocks for guiding visually impaired people. In addition, the sidewalk of Yoshikura Bridge will be renovated to a non-slip pavement.

Maintenance items

Renovation of road structure
Partial renovation of sidewalk 20 renovation steps and slopes
Partial renovation of sidewalk pavement renovation 940m2
Partial renovation of sidewalk renovation of drainage facilities 17 locations
Laying and renovation of blocks for guiding visually impaired persons
Continuous installation of route guidance 250m
9 new installations at intersections, etc.
9 parts laying and renovations at intersections, etc.
Life-related routes (A)

Route name

(6)East Exit Station Square (3019 in front of the prefectural road Ofuna Station)

Business Section

JR Totsuka Station-Prefectural Road Ofuna Station Yabe

Business extension

140m

Project implementation period

From FY2009 to FY2010

Maintenance Policy

[Route] : It is a route within Totsuka Station East Exit Station Square and has a wide sidewalk width.
[Issues] : At intersections, there are steep steps and steep slopes. In addition, there are places where blocks for guiding visually impaired people are not installed or difficult to use.
[Measures] : Renovation of steps and gradients at intersections and new construction and renovation of blocks for guiding visually impaired people.

Maintenance items

Laying and renovation of blocks for guiding visually impaired persons
Continuous installation of route guidance 20m
Continuous laying and repair of route guidance 20m
Two parts laying and renovations at intersections, etc.
Life-related routes (A)

Route name

(7)Main local road Yokohama Isehara (Chogo Kaido) (Prefectural Road Yokohama Isehara 1235)

Business Section

West from the intersection in front of the bus center

Business extension

120m

Project implementation period

From FY2009 to FY2010

Maintenance Policy

[Route] : It is a route from Totsuka Station West Exit over National Route 1 to the western region.
[Issues] : There are steep steps and gradients at intersections, and sections where blocks for guiding visually impaired people are not installed.
[Measures] : Renovation of steps and gradients at intersections and new construction and renovation of blocks for guiding visually impaired people.

Maintenance items

Renovation of road structure
Partial renovation of sidewalks Three renovations with steps and slopes
Partial renovation of sidewalk pavement renovation 170m2
Partial renovation of sidewalk Refurbishment of drainage facilities
Laying and renovation of blocks for guiding visually impaired persons
Continuous installation of route guidance 10m
Two parts laying and renovations at intersections, etc.

Matters to be considered

Development in conjunction with Totsuka Station West Exit Type 1 Urban Redevelopment Project
Life-related routes (A)

Route name

(8)National Route 1 (Tokyo) Kashio Totsuka Line (Kashio Totsuka Line)

Business Section

Intersection in front of the bus center-Yokohama Tozuka Employment Assistance Center

Business extension

100m

Project implementation period

From FY2009 to FY2010

Maintenance Policy

[Route] : It is a route from Totsuka Station West Exit via the intersection in front of the bus center to the Yokohama Tozuka Employment Assistance Center.
[Issues] : There are sections where blocks for guiding visually impaired persons have not been installed.
[Measures] : Create new route guidance for blocks for guiding visually impaired persons.

Maintenance items

Laying and renovation of blocks for guiding visually impaired persons
Continuous installation of route guidance 30m

Matters to be considered

Development in conjunction with Totsuka Station West Exit Type 1 Urban Redevelopment Project
Life-related routes (A)

Route name

(9)In front of Tozuka Sports Center (Tozuka 190)

Business Section

Tozuka Prefectural Tax Office Entrance-Tozuka Sports Center

Business extension

110m

Project implementation period

From FY2009 to FY2010

Maintenance Policy

[Route] : It is a route from Totsuka Station East Exit to Tozuka Sports Center via the entrance of the Tozuka Prefectural Tax Office at the prefectural road Ofuna Station Yabe.
[Issues] : There are places where there are steep steps and gradients at intersections, and sections where blocks for guiding visually impaired people are not installed.
[Measures] : Renovation of steps and gradients at intersections and new construction and renovation of blocks for guiding visually impaired people.

Maintenance items

Renovation of road structure
Partial renovation of sidewalk Two renovation steps and slope
Partial renovation of sidewalk pavement 10m2
Partial renovation of sidewalk Refurbishment of drainage facilities
Laying and renovation of blocks for guiding visually impaired persons
Continuous installation of route guidance 40m
Continuous laying and repair of route guidance 40m
Two new installations at intersections, etc.
Life-related routes (B)

Route name

(10)-1 In front of Asahi Bridge to Kami Kurata Care Plaza (Tozuka 191)

Business Section

Near Asahi Bridge

Business extension

80m

Project implementation period

From FY2009 to FY2010

Maintenance Policy

[Route] : The route from Asahi Bridge on the west side of Totsuka Station via the forum to Kami Kurata Care Plaza is the section from the right bank of Asahi Bridge to the intersection in front of the forum.
[Issues] : On the left bank of Asahi Bridge Hashizume, there is a steep tiled pavement with a steep slope, making it slippery in rainy weather. In addition, there are places where blocks for guiding visually impaired people have not been installed at intersections.
[Measures] : The area around Hashizume on the left bank of Asahi Bridge and the surface of Asahi Bridge will be renovated to a non-slip pavement. In addition, new blocks for guiding visually impaired persons will be constructed at intersections, etc.

Maintenance items

Renovation of road structure
Partial renovation of sidewalk pavement renovation 280m2
Laying and renovation of blocks for guiding visually impaired persons
Continuous installation of route guidance 70m
Three new installations at intersections, etc.

Matters to be considered

For the front road of housing complex-mae Park, coordination with landowners is necessary.
Life-related routes (B)

Route name

(10)-2 In front of Asahi Bridge to Kami Kurata Care Plaza (Tozuka 256)

Business Section

Before the Forum

Business extension

200m

Project implementation period

From FY2009 to FY2010

Maintenance Policy

[Route] : The route from Asahi Bridge on the west side of Totsuka Station via the forum to Kami Kurata Care Plaza is a section from the intersection at the forum corner along the railway to Kami Kurata Care Plaza.
[Issues] : There are sections where the sidewalk width is narrow, where the steps and slope are tight at intersections, and sections where there is no block for guiding visually impaired people.
[Measures] : In addition to widening the sidewalk, new and renovated blocks for guiding the visually impaired. In addition, we will consider coloring at the intersection of the forum corner.

Maintenance items

Securing pedestrian spaces
Width of sidewalk 160m
Renovation of road structure
Partial renovation of sidewalk, renovation of steps and slope
Partial renovation of sidewalk and pavement renovation 180m2
Partial renovation of sidewalks and renovation of drainage facilities
Laying and renovation of blocks for guiding visually impaired persons
Continuous laying and repair of route guidance 5m
1 new installation at intersections, etc.
Partial laying and renovation at intersections, etc.
Life-related routes (B)

Route name

(10)-3 Asahi Bridge to Kami-Kurata Care Plaza (Tozuka 349)

Business Section

In front of Kami Kurata Care Plaza

Business extension

170m

Project implementation period

From FY2009 to FY2010

Maintenance Policy

[Route] : This is the section from Asahi Bridge on the west side of Totsuka Station to Kami Kurata Care Plaza via the forum, from the road along the railway to Kami Kurata Care Plaza.
[Issues] : There is a part of the stairs on the left bank of Sakurabashi Hashizume where there is no block for guiding visually impaired people.
[Measures] : A new block for guiding visually impaired persons will be established at the stairs on the left bank of Sakurabashi Hashizume.

Maintenance items

Laying and renovation of blocks for guiding visually impaired persons
1 new installation at intersections, etc.

Matters to be considered

For the front road of housing complex-mae Park, coordination with landowners is necessary.
Life-related routes (B)

Route name

(11)Kashio River Promenade

Business Section

Tozuka District Center-Friends Tozuka

Business extension

340m

Project implementation period

From FY2009 to FY2010

Maintenance Policy

[Route] : It is a promenade on the right bank of the Kashio River, connecting the Tozuka District Center to Friends Tozuka.
[Issues] : There are places where blocks for guiding visually impaired people are not installed at intersections and places with coarse flat pavements.
[Measures] : New construction of blocks for guiding visually impaired persons at intersections and renovation of pavements.

Maintenance items

Renovation of road structure
Partial renovation of sidewalk pavement renovation 250m2
Laying and renovation of blocks for guiding visually impaired persons
10 new installations at intersections, etc.

Matters to be considered

Discussions with river managers are necessary
Life-related routes (A)

Route name

(12)Kashio River Promenade

Business Section

(Left bank) Yoshikurabashi-Sakurabashi

Business extension

410m

Project implementation period

From FY2009 to FY2010

Maintenance Policy

[Route] : It is a promenade on the left bank of the Kashio River, connecting Yoshikura Bridge to Sakurabashi.
[Issues] : There is an uninstalled block for guiding visually impaired persons at intersections.
[Measures] : A new block for guiding visually impaired persons will be established at intersections.

Maintenance Policy

This is a promenade on the left bank of the Kashio River, which connects Yoshikura Bridge to Sakurabashi, but there are no blocks for guiding visually impaired people at intersections.
For this reason, a new part of the block for guiding visually impaired persons will be laid at intersections.

Maintenance items

Laying and renovation of blocks for guiding visually impaired persons
17 new installations at intersections, etc.

Matters to be considered

Discussions with river managers are necessary
Life-related routes (B)

Route name

(13)Kashio River Promenade

Business Section

(right bank) Ohashi-Yoshikura Bridge

Business extension

590m

Project implementation period

From FY2009 to FY2010

Maintenance Policy

[Route] : It is a promenade on the right bank of the Kashio River, which connects Ohashi to Yoshikura Bridge.
[Issues] : There are places where there is no block for guiding visually impaired people at intersections.
[Measures] : A new block for guiding visually impaired persons will be established at intersections.

Maintenance items

Laying and renovation of blocks for guiding visually impaired persons
Partial laying at intersections, etc. 12 new locations

Matters to be considered

Discussions with river managers are necessary
Life-related routes (A)

Route name

(14)National Route 1 (Large Railroad Crossing-Ohashi)

Business Section

Road No. 1 Land Readjustment Project

Business extension

240m

Project implementation period

From FY2008

Maintenance Policy

[Measures] : Full renovation will be carried out in line with the land readjustment project before and after.

Matters to be considered

Developed in line with the central land readjustment project in the Tozuka station square area (H26 project scheduled to be completed)
Life-related routes (A)

Route name

(15)Tozuka West Exit Terminal 2

Business Section

Tozuka West Exit Terminal 2

Business extension

60m

Project implementation period

Continued examination and maintenance since 2011

Maintenance Policy

[Route] : It is a bus terminal located on the north side of West Exit Totsuka Station.
[Issues] : There are sections where there are steep steps and gradients at the crossing of the roadway, and sections where there is no block for guiding visually impaired people.
[Measures] : Renovation of steps and slopes at the crossing of the roadway, and construction of new blocks for guiding visually impaired persons will be performed.

Maintenance items

Renovation of road structure
Partial renovation of the sidewalk, renovation of steps and slopes
Partial renovation of sidewalk and pavement renovation 10m2
Partial renovation of sidewalks and renovation of drainage facilities
Laying and renovation of blocks for guiding visually impaired persons
Continuous laying and new construction of route guidance 50m
Partial laying and new construction at intersections, etc.

Matters to be considered

Developed in line with the central land readjustment project in the Tozuka station square area (H26 project scheduled to be completed)

(3) Other Initiatives

Cooperation of citizens including the roadside is indispensable in order for the target route to be barrier-free to be effectively utilized by the "Road Specific Project".
The contents of the road manager are shown below.

  • Utilizing city public relations magazines and websites, we provide information on the status of business implementation and approaches for barrier-free.
  • Regarding illegal occupied properties and illegal bicycle parking, etc. that narrow the effective width of roads that hinder movement, cooperation of roadside people and manners such as bicycle users are important, and guidance, removal, and promotion of bicycle parking lot use will be promoted in the future. Call for etc.

7.Promotion of Road Specific Business Plan

In order to create a walking space network where everyone can move safely and comfortably, each person should understand each other and cooperate with related parties such as traffic managers, railway operators, road occupants, roadside residents, etc. Is required. Thank you very much for your cooperation.

Inquiries to this page

Road and Highway Bureau Road Department Facilities Division

Telephone: 045-671-2731

Telephone: 045-671-2731

Fax: 045-550-3376

Email address: do-shisetsu@city.yokohama.lg.jp