Permission to Temporary Buildings (Article 85 of the Act)
Last Updated January 24, 2024
About permission of temporary building
With temporary building, when we admit that there is no problem in safety, fire prevention and hygiene by Article 85 Clause 6 and 7 (permission of temporary building) of Building Standard Act, we set period and temporarily We refer to building to be installed. Temporary permission application is required before applying for confirmation. In addition, in order to judge that there is no problem with safety, fire prevention and hygiene, we may ask for individual correspondence, so please consult in advance using the building consultation Internet reception form.
Building consultation Internet reception form (outside site) before application such as building confirmation
Permission criteria
Permission criteria for temporary exhibition halls, etc. based on the provisions of Article 85, Paragraph 6 of the Building Standards Act (enforced on October 20, 2023) <<pdf format >> (PDF: 218KB)
[Apologies] From July 28, 2023 to October 5, 2023, there was an error in the published permission criteria. <<Opter> pdf format >> (PDF: 180KB)
For more information, please check the permission criteria for enforcement on October 20, 2023.
Application book
<Permission application>
Permit Application Form (Ministry Ordinance No. 44) → (Word format) (Word: 20KB)
<Notification due to plan change>
registration form (Article 15, Paragraph 1 of the Yokohama City Building Standards Law Enforcement Regulations) → 2 copies (Word) (word: 22KB)
<Attached book (Yokohama City Building Standard Law Enforcement Regulations, Article 8, Paragraph 1)>
1 | Reason for | |
---|---|---|
2 | Guide map and location map of temporary buildings | If there is this construction, specify the distance between the location and the temporary building. |
3 | Layout diagram | Specify the surrounding conditions, site height difference, road width, etc. |
4 | Floor plan, elevation, cross-section | |
5 | In the case of leased land, written consent to use the land | Specify the period of use. |
6 | Process schedule | The process from construction to completion to removal of the building and if there is this work, specify the relationship with this construction. |
7 | If there is this construction, a copy of the certificate of completion or a copy of a document certifying the contract (subcontracting) of this work in order to confirm the progress and certainty of implementation | When attachment is difficult due to the process.
|
8 | Power of Attorney | |
9 | Others |
|
Procedure Flow
For the standard processing period, please refer to “Standard Processing Period required for Disposal of Housing and Architecture Bureau Permits, etc.”
Please refer to "Building Confirmation Q & A" for common Q & A.
※Please talk about procedure of Building Standard Act Article 85 Clause 7 individually.
Application fee
In accordance with the revision of the law, the fee regulations have been partially revised.
- Building permission fee for temporary exhibition halls, etc. based on the provisions of Article 85, Paragraph 6 of the Act
- Building permission fee for temporary exhibition halls, etc. based on the provisions of Article 85, Paragraph 7 of the Act 160,000 yen
In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
To download Adobe Acrobat Reader DC
For inquiries to this page
Building Guidance Division, Housing and Architecture Bureau Building Guidance Division
Phone: 045-671-4531
Phone: 045-671-4531
Fax: 045-681-2437
Email address: kc-shidotanto@city.yokohama.jp
Page ID: 719-555-986