Temporary use authorization (6 of Building Standard Act Article 7)

Last update date December 18, 2020

Temporary use authorization

Temporary use recognition system of building under construction decides to be able to use under the constant situation (when authorized administrative agency, chief architect or designated confirmation inspection organization admitted that they did not have problem in evacuation in fire prevention in security) after having limited use of building before receiving grant of certificate of inspection with principle prohibition.
In addition, object of temporary use authorization is buildings from law Article 6 Paragraph 1 1 to 3.

※About temporary use recognition system, it is 2014 law No. 54. By "revised Building Standard Act", we may authorize in the designated confirmation inspection engine from the enforcement on June 1, 2015. As for the details, please see HP (the outside site) of the Ministry of Land, Infrastructure, Transport and Tourism.

Application

When we include by construction such as the enlargement and construction about refuge facilities, except cases of construction that the Minister of Land, Infrastructure and Transport sets, application of temporary use authorization is necessary for identification administrative agency (16 third q.v. of Building Standard Act enforcement regulations Article 4).

As construction such as the enlargement that we use even designated confirmation inspection engines provisionally and can authorize, the following construction is set.

  • We correspond to requirements to advocate by construction of the enlargement next
  • Completing construction (thing concerned with part of temporary use is best.) about refuge facilities before application of temporary use authorization.
  • Do not include construction about refuge facilities modifying part except part affecting the enlargement.
  • Construction of all reconstruction
  • Construction of all reconstruction of the sectioned part when building is sectioned in wall of structure that became independent without opening concerned

Grounds laws and ordinances

Grounds laws and ordinances
6 of law Article 7We set a limit to use of building before receiving grant of certificate of inspection
Article 13 to orderRanges such as refuge facilities
2 of Article 13 to orderConstruction that is simplicity not to be included in construction about refuge facilities
16 of kidai Article 4Application of temporary use authorization
3 of law Article 90Report of plan about measures in security during construction
2 of Article 147 to orderBuilding which needs report of plan about measures in security during construction
2 of kidai Article 11Style of report of plan about measures in security

Application

Application
Application submission pointAddressTemporary use authorization applicationFee
Building Guidance DivisionIt is addressed to specific administrative agency (The Mayor of Yokohama)Confirmation application → No. 33 style, notice of plan → 20 styles of No. 42120, 000 yen
Building Guidance DivisionIt is addressed to chief architectConfirmation application → No. 34 style, notice of plan → 21 styles of No. 42120, 000 yen
Designated confirmation inspection engineIt is addressed to designated confirmation inspection organizationNo. 34 stylePlease ask each organization

<report accompanied with plan change>
Plan change approval registration form (Yokohama-shi Building Standard Act detailed enforcement regulations Article 15 Paragraph 1) → Two copies of principals and vice << Word format >> (word: 71KB)

Necessary book

Necessary book
1Temporary use authorization applicationNo. 33 style (word: 30KB) No. 34 style (word: 31KB) mention example (PDF: 145KB)
2Proxy
3Safe planWhen it is before examination of completion application submission, we attach >>Safe plan (word: 54KB) mention example (PDF: 375KB)
4Progress scheduleWhen it is before examination of completion application submission, we attach (we state temporary period of service clearly for the whole process)
5Neighborhood sketchWe state ranges to use provisionally clearly
6PlanWe state ranges to use provisionally clearly
7Each floor ground planWe state ranges to use provisionally clearly
8Temporary design illustrated mapWhen it is before examination of completion application submission, we attach

※About article performing building certification with designated confirmation inspection engine, please submit the following documents separately.

Documents to submit separately when we perform building certification with designated confirmation inspection engine
1Copy of confirmation application
2Copying of comfirmed proof
3Copying of proof that intermediate inspection passes
4Copy of confirmation application attachment figure (depending on guide map, plan, ground plan, elevation, cross section, use, scale figure of facilities)

Flow of procedure

Flow of temporary use

Adobe Acrobat Reader DC (old Adobe Reader) is necessary to open file of Portable Document Format.
Person who does not have can download free of charge from Adobe company.
Get Adobe Acrobat Reader DCTo downloading of Adobe Acrobat Reader DC

Inquiry to this page

Housing and Architecture Bureau architecture leadership city area Building Control Section

Telephone: 045-671-4510

Telephone: 045-671-4510

Fax: 045-681-2438

E-Mail address [email protected]

Return to the previous page

Page ID: 628-972-539

We come back to the top