Flow of Inspection Procedures

Last Updated January 24, 2024

After issuing the certificate of confirmation, we will explain the procedure up to the completion of construction and the issuance of the certificate of inspection.
(Interim inspection of S, RC, and SRC works is performed by the structural staff (S, RC, SRC works).)

Contents

  1. Completion of confirmation application procedure (issue of confirmation certificate)
  2. Start of construction and end of specific processes
  3. Application for intermediate inspection
  4. Intermediate inspection
  5. Passing mid-term inspection
  6. Before and after completion of construction
  7. Application for completion inspection
  8. Completion inspection
  9. Certificate of inspection
  10. Notes

At least 14 days before the start of construction, "Notification of Construction Supervisor and Construction Contractor Appointment", "Copy of Construction Supervision and Construction Contract" or "Certificate of Conclusion of Contract for Construction Supervision and Construction Work" Please attach and submit.

(1) Specific process

Intermediate inspections may be performed twice depending on the structure and scale.

(2) Inspection reservation

Please make a reservation for the inspection by telephone from 2 weeks to 10 days before the scheduled intermediate inspection date.

  • Reservation phone number: Building Guidance Division Guidance Section TEL: 045-671-4531

(1) required documents

Please submit the following documents from 4 days before the inspection date to the day before.

※For small wooden buildings, we request an application up to 3 days in advance.

◆Common (submitted one copy)

List of documents
1Intermediate inspection acceptance check sheet
2Interim Inspection Application Form
3Report (Check Sheet) based on Article 12, Paragraph 5 of the Building Standards Act (Construction Supervision and Construction Status) (Note 1)
4Power of Attorney (Note 2)
5Copy of Architect's License (Note 3)
6Photo of construction status (the name of the construction supervisor, seal, date of shooting)

◆Precautions for creating a photograph of construction status

Construction status photos are required when subject to the application of Article 7-5 of the Building Standards Law (exception of inspection). Refer to the table below, at the end of construction of the roof hut (3 or more places), at the end of construction of the main frame or strength wall in terms of structural strength (3 or more places), and at the end of construction of the foundation reinforcement (3 or more places) Please submit a total of about 10 photos (excerpts of distant views, details, etc.).

Photographing position (Reference)
No, noAt the end of construction of the roof hutMajor frames or structures in terms of structural strength
At the end of construction of the strength wall
At the end of construction of foundation reinforcement
WoodenHut beam, girder, rafter, main house,
And the handling of fire materials, etc.
Or other joints
Pillars, horizontal mounts and braces
Or other force-bearing walls
Other joints
Reinforcing bars of main bottoms and beams
S structurePillars, beams,
Or other joints
Pillars, beams, steel braces,
Or other joints
Reinforcing bars of main bottoms and beams
RC constructionA one-story roof, a pillar,
Reinforcing beam reinforcement and reinforcing bars
Placement of columns, beams, walls, floors, reinforcing barsReinforcing bars of main bottoms and beams

In addition, please utilize style published in "7. thing to submit at the time of intermediate inspection" of "form downloading" of Building Guidance Division HP for mount of presentation photograph.
For the construction part performed after the intermediate inspection, please submit a photo at the time of application for completion inspection.

◆Only when there is applicable construction (one copy is submitted without special mention)

List of documents
NumberConstruction detailsDocuments
7Pile constructionResults of construction of pile construction (Note 4)
8Concrete construction of RC, PC, SRC building with 3rd floor or higher or 500m2 or moreConcrete Construction Results Report (Note 4)
9Steel frame construction work for buildings with 3 floors or more or 500m2 or more with S or SRC structuresReport on construction results of steel frame construction (Note 4)
10Small-scale buildings (wooden buildings with less than 2 floors and less than 500m2 or non-wooden buildings with less than 1 floor and less than 200m2)Conventional frame methodReport on the structure of the foundations of buildings
11Books that clearly indicate the position and type of strength walls and hardware, as well as the position of the pillars.
12Please submit the following books when there is no special inspection application.
(1) Wall Amount Statement, 1/4 Balance Calculation
(2) Structural study of fittings and fittings
13Frame wall construction methodReport on the structure of the foundations of buildings
14Books that clearly indicate the position and type of strength walls
15Please submit the following books when there is no special inspection application.
(1) Wall Amount Statement
(2) 40 square meters drawing
16Non-woodenFundamental drawing and detailed structural drawing
17If there is a minor change (provided one copy of each copy) (Note 5)Notification of plan change based on Building Standard Act Article 12 Clause 5
18Changed drawings (Note 6)
19Manuals, certificates, etc. regarding changes

◆Documents required separately for small buildings (submitted one copy)

You may be required to submit a report if any of the following items apply.

List of documents
21Installation and lowering of the foundation, reinforcement diagram of the basement, underground garage, etc., and construction status photo
22Reinforcing diagram of retaining wall and photo of construction status
(Please submit a copy of the certificate of inspection for the part (more than 2m) where you apply for the work.)
23Ground improvement, pile construction status report

(2) Precautions for Interim Inspection

(1) Confirmation of inspection time

Be sure to check the time by telephone with the Building Guidance Division staff in the afternoon of the day before the inspection.

  • Building Guidance Division Guidance Section TEL: 045-671-4531
  • An intermediate inspection pass certificate will be issued by the instructor.
  • An intermediate inspection pass certificate is required for the water supply equipment construction completion notification.

Please make an appointment by telephone from 2 weeks to 10 days before the scheduled completion inspection date.

  • Reservation phone number: Building Guidance Division Guidance Section TEL: 045-671-4531

(1) required documents

Please submit the following documents from 7 days before the inspection date to the day before.

◆Common (submitted one copy)

List of documents
1Completion inspection acceptance check sheet
2Completion inspection application
3Report (Check Sheet) based on Article 12, Paragraph 5 of the Building Standards Act (Construction Supervision and Construction Status) (Note 1)
4Power of Attorney (Note 2)
5Copy of Architect's License (Note 3)
6Photo of construction status (the name of the construction supervisor, seal, date of shooting)

Please refer to (1) required documents (Precautions for the creation of construction status photos) in “3. Application for Interim Inspection” for “6. Photographs of construction status photos (named by the supervisor, seal, with shooting date)”.

◆Only when there is applicable construction (one copy is submitted without special mention)

List of documents
NumberConstruction detailsDocuments
7Pile constructionResults of construction of pile construction (Note 7)
8Concrete construction of RC, PC, SRC building with 3rd floor or higher or 500m2 or moreReport on Construction Results of Concrete Construction (Note 7)
9Steel frame construction work for buildings with 3 floors or more or 500m2 or more with S or SRC structuresReport on construction results of steel frame construction (Note 7)
10Construction work with a site area of 500 m2 or more in residential restricted areasGreening facility check sheet
11Small-scale buildings without intermediate inspections (wooden buildings with a floor of 2 or less and 500m2 or less or non-wooden buildings with a floor of 1 and 200m2 or less)Conventional frame methodReport on the structure of the foundations of buildings
12Please submit the following books when there is no special inspection application.
(1) Books that clearly indicate the position and type of strength walls and hardware, as well as the position of the pillars.
(2) Wall Amount Statement, 1/4 Balance Calculation
(3) Structural study of fittings and fittings
13Frame wall construction methodReport on the structure of the foundations of buildings
14Please submit the following books when there is no special inspection application.
(1) Books that clearly indicate the position and type of strength walls
(2) Wall Amount Statement
(3) 40 square meters drawing
15Non-woodenReport on the structure of the foundations of buildings
16If there is a minor change (provided one copy of each copy) (Note 5)Notification of plan change based on Building Standard Act Article 12 Clause 5
17Changed drawings (Note 6)
18Manuals, certificates, etc. regarding changes

◆Documents required separately for small buildings (submitted one copy)

You may be required to submit a report if any of the following items apply.

List of documents
19Installation and lowering of the foundation, reinforcement diagram of the basement, underground garage, etc., and construction status photo
20Reinforcing diagram of retaining wall and photo of construction status
(Please submit a copy of the certificate of inspection for the part (more than 2m) where you apply for the work.)
21Ground improvement, pile construction status report

(1) Confirmation of inspection time

Be sure to check the time by telephone with the Building Guidance Division staff in the afternoon of the day before the inspection.

  • Building Guidance Division Guidance Section TEL: 045-671-4531

(2) Precautions for Completion Inspection

  • At the time of completion inspection, if a copy of the inspection certificate of each inspection (eg, firefighting inspection, inspection related to residential land development and development, inspection of elevators, etc.) has not been submitted at the time of completion inspection application for building standard related regulations, please submit.
  • Completion inspection in the greening area system
  • About sick house
  • The certificate of inspection will be issued by the instructor.

≪When an intermediate inspection is performed once≫

Please submit the applicable one from "framework method (2 stories)", "framework method (2 stories)", "certified building", "reinforced concrete", "steel frame structure", and "basic process".

≪When there are two or more intermediate tests≫

The first time is the "basic process", and the second and subsequent times, the parts constructed after the previous intermediate inspection are the "basic process", "framework method (three stories)", "framework method (three stories)", "reinforced concrete" Please submit the applicable items from "steel frame construction".

Please submit only when applying for an inspection by an agent. (If you have submitted a power of attorney stating that you will collectively delegate to the agent until the inspection application at the time of confirmation application, a copy of it may be used.) .

Please submit only if the designer / construction supervisor is an architect and is different from the previous application (it is unnecessary if you can check it by browsing the architect database etc.).

Only the part that has been completed at the time of application for intermediate inspection (Please submit the remaining part by the time of application for completion inspection)

This is not required if you submit it in advance.

Please submit the changed drawing with the contents before the change written in red or the drawing before and after the change. When you include change of layout drawing, please submit thing after change of the third side of building plan summary book.

Please submit the part that was constructed later than the previous interim inspection.

Inquiries to this page

Building Guidance Division, Housing and Architecture Bureau Building Guidance Department

Telephone: 045-671-4531

Telephone: 045-671-4531

Fax: 045-681-2437

Email address: kc-shidotanto@city.yokohama.lg.jp

Return to the previous page