Flow of inspection procedures
Last Updated January 24, 2024
After the issuance of the confirmed certificate, the construction is completed and the procedure up to the issuance of the inspection certificate will be explained.
(Interim inspection of S, RC construction, and SRC construction is performed by the structural staff (S, RC, SRC construction).)
Contents
- Confirmation application procedure completed (issued certificate issued)
- Start of construction and end of specific processes
- Interim inspection application
- Interim inspection
- Passed interim inspection
- Prior to completion of construction and completion
- Completion inspection application
- Completion inspection
- Issuance of inspection certificate
- Notes
At least 14 days before the start of construction, submit a “Notification of Construction Supervisor and Construction Worker”, “Copy of Contract for Construction Supervisory and Construction Work Contract” or “Certificate of Concluding Contract for Construction Supervision and Construction Work” Please attach and submit.
(1) Specific Process
Intermediate inspections may be conducted twice depending on the structure and scale.
- Interim inspection (specific process) list
- Specific steps for intermediate inspection of underground garages and houses with basements
- Specific steps of the log assembly method
(2) Inspection reservation
Please make an appointment for an inspection by telephone two weeks to 10 days before the scheduled intermediate inspection date.
- Reservation telephone number: Building Guidance Division Guidance Section TEL: 045-671-4531
(1) required documents
Please submit the following documents from 4 days before the inspection date to the day before.
※For small wooden buildings, we ask for application up to three days in advance.
◆Common (submitted one copy)
1 | Intermediate inspection reception check sheet |
---|---|
2 | Interim inspection application form |
3 | Report (Check sheet) based on Article 12, Paragraph 5 of the Building Standards Act (Construction Supervision and Construction Status) (Note 1) |
4 | Power of Attorney (Note 2) |
5 | A copy of the architect's license (Note 3) |
6 | Photograph of construction status (seal, name of construction supervisor) |
◆Precautions for creating construction status photos
Construction status photos are required when receiving the application of Article 7-5 of the Building Standards Law (exceptions for inspection). Refer to the table below, at the end of the construction of the roof hut (3 or more locations), at the end of the construction of the main frame or bearing wall in terms of structural strength (3 or more places), and at the end of the construction of the foundation (3 places) Please submit a total of about 10 photos (distant views, excerpts of details, etc.).
Nothing | At the end of construction of the roof hut | Major frames or structures in structural strength At the end of construction of the load-bearing wall | At the end of construction of foundations |
---|---|---|---|
Wooden | Hut beams, girders, rafters, main house And firework, etc. Or other joints | Pillars, sideways and braces; Or other bearing walls Other joints | Reinforcing bars of major bottom boards and beams |
Structure | Pillars, beams Or other joints | Pillars, beams, steel bracelets Or other joints | Reinforcing bars of major bottom boards and beams |
RC construction | One-story roof plate, pillars, Reinforcing bars and reinforcing bars | Pillars, beams, walls, floors, and reinforcing bars | Reinforcing bars of major bottom boards and beams |
In addition, please utilize style published in "7. thing to submit at the time of middle inspection" of "format downloading" of Building Guidance Division HP.
For the construction part performed after the interim inspection, please submit a photo when applying for the completion inspection.
◆Only when there is applicable construction (submitted one copy without special notice)
Number | Construction details | Documentation | |
---|---|---|---|
7 | Pile construction | Report on pile construction results (Note 4) | |
8 | Concrete work for buildings that are 3 floors or more or 500m2 or more in RC / PC / SRC construction | Concrete Construction Results Report (Note 4) | |
9 | Steel frame construction work for buildings 3 floors or more or 500 m2 or more in SRC construction | Report on the results of steel frame construction (Note 4) | |
10 | Small-scale buildings (wooden buildings with less than 2 floors and 500 m2 or less, or non-wooden buildings with less than 1 floors and 200 m2) | Conventional framing method | Report on Structure Method of Building Foundation |
11 | Books that clearly indicate the location and type of load-bearing walls and hardware, and the location of the through pillars | ||
12 | Please submit the following books if there is no special inspection exception. (1) Wall volume statement, 1/4 balance calculation (2) Structural review of joints and fittings | ||
13 | Framed wall construction method | Report on Structure Method of Building Foundation | |
14 | Books that clearly indicate the location and type of load-bearing wall | ||
15 | Please submit the following books if there is no special inspection exception. (1) Wall volume statement (2) 40 square meters section line drawing | ||
16 | Non-wooden | Fundamental Plan and Structure Detailed Diagram | |
17 | If there are minor changes (submitted one copy of each copy) (Note 5) | Notification of plan change based on Building Standard Act Article 12, Paragraph 5 | |
18 | Changed drawing (Note 6) | ||
19 | Instructions, Certificates, etc. concerning changes |
◆Documents required separately for small buildings (submitted one copy)
If the following items apply, you may be required to submit a report.
21 | Raising and standing of foundations, reinforcement drawings of underground garages, etc., and construction status photos |
---|---|
22 | Reinforcing diagram of retaining walls and photographs of construction status (Please submit a copy of the inspection certificate for the part (more than 2m) for which the work is applied.) |
23 | Status of ground improvement, pile construction status report |
(2) Precautions for Interim Inspection
- How to attach hardware
- Breathing Pattern Table (Excel: 260KB)
(We have prepared a pattern table for brace arrangement according to the provisions of the notification and a pattern table for brace arrangement based on N value calculation are prepared.)
(1) Confirmation of inspection time
Please be sure to check the time by telephone to the person in charge of the Building Guidance Division in the afternoon of the day before the inspection.
- Building Guidance Division Guidance Section TEL: 045-671-4531
- The mid-term inspection pass certificate will be issued by the instructor.
- Interim inspection pass certificate is required for notification of completion of water supply equipment construction completion.
- For more information."Please attach a copy of the mid-term inspection pass certificate to the water supply equipment construction completion notification"Please refer to the documentation.
Please make an appointment for an inspection by telephone two weeks to 10 days before the scheduled completion inspection date.
- Reservation telephone number: Building Guidance Division Guidance Section TEL: 045-671-4531
(1) required documents
Please submit the following documents from 7 days before the inspection date to the day before.
◆Common (submitted one copy)
1 | Completion inspection reception check sheet |
---|---|
2 | Completion Inspection Application Form |
3 | Report (Check sheet) based on Article 12, Paragraph 5 of the Building Standards Act (Construction Supervision and Construction Status) (Note 1) |
4 | Power of Attorney (Note 2) |
5 | A copy of the architect's license (Note 3) |
6 | Photograph of construction status (seal, name of construction supervisor) |
For “6. Construction Status Photographs (seal of Construction Supervisor, with shooting date)”, please refer to (1) required documents “(Notes on creating construction status photos)” in “3. Application for Intermediate Inspection”. Please refer to.
◆Only when there is applicable construction (submitted one copy without special notice)
Number | Construction details | Documentation | |
---|---|---|---|
7 | Pile construction | Report on pile construction results (Note 7) | |
8 | Concrete work for buildings that are 3 floors or more or 500m2 or more in RC / PC / SRC construction | Concrete Construction Results Report (Note 7) | |
9 | Steel frame construction work for buildings 3 floors or more or 500 m2 or more in SRC construction | Report on the results of steel frame construction (Note 7) | |
10 | Construction work with a site area of 500 m2 or more in residential use area | Greening facility check sheet | |
11 | Small-scale buildings without intermediate inspection (wooden buildings with 2 or less floors and 500 m2 or less or non-wooden buildings with 1 and 200 m2 or less) | Conventional framing method | Report on Structure Method of Building Foundation |
12 | Please submit the following books if there is no special inspection exception. (1) Books that clearly indicate the location and type of load-bearing walls and hardware, and the location of the through pillars (2) Wall volume statement, 1/4 balance calculation (3) Structural review of joints and fittings | ||
13 | Framed wall construction method | Report on Structure Method of Building Foundation | |
14 | Please submit the following books if there is no special inspection exception. (1) Books that clearly indicate the location and type of load-bearing wall (2) Wall volume statement (3) 40 square meters section line drawing | ||
15 | Non-wooden | Report on Structure Method of Building Foundation | |
16 | If there are minor changes (submitted one copy of each copy) (Note 5) | Notification of plan change based on Building Standard Act Article 12, Paragraph 5 | |
17 | Changed drawing (Note 6) | ||
18 | Instructions, Certificates, etc. concerning changes |
◆Documents required separately for small buildings (submitted one copy)
If the following items apply, you may be required to submit a report.
19 | Raising and standing of foundations, reinforcement drawings of underground garages, etc., and construction status photos |
---|---|
20 | Reinforcing diagram of retaining walls and photographs of construction status (Please submit a copy of the inspection certificate for the part (more than 2m) for which the work is applied.) |
21 | Status of ground improvement, pile construction status report |
(1) Confirmation of inspection time
Please be sure to check the time by telephone to the person in charge of the Building Guidance Division in the afternoon of the day before the inspection.
- Building Guidance Division Guidance Section TEL: 045-671-4531
(2) Precautions for Completion Inspection
- At the time of completion inspection, please submit a copy of the inspection certificate of each inspection certificate (eg, firefighting inspection, inspection related to residential land development and development, inspection of elevators, etc.) at the time of completion inspection application for the building standard-related regulations .
- Completion inspection in the greening area system
- Regarding sick house
- The inspection certificate will be issued by the instructor.
≪When an intermediate inspection is performed once≫
Please submit the applicable one from the "framed construction method (two stories)" "frame construction method (two stories)", "certified building", "reinforced concrete construction" and "steel frame construction".
≪When there are two or more interim inspections≫
The first time is the "basic process", and the second and subsequent times, for the parts constructed after the last intermediate inspection, "framed method (three stories)" "framed construction method (three stories)" "framed construction" Please submit the applicable one from "Steel frame construction".
Please submit only when applying for an inspection by an agent (if you have submitted a power of attorney stating that you will be entrusted to the agent collectively until the inspection application at the time of confirmation application, a copy of it may be used) .
Please submit only if the designer / construction supervisor is an architect and is different from the previous application (not required if it can be confirmed by browsing the architect database, etc.).
Only the part where construction has been completed at the time of the application for interim inspection (Please submit the remaining part by the time of application for completion inspection).
This is not required if you submit it in advance.
Please submit the revised drawing with the contents before the change in red or the drawing before and after the change. When you include change of layout drawing, please submit thing after change of the third side of architectural plan summary book.
Please submit the part that was constructed after the last interim inspection.
For inquiries to this page
Building Guidance Division, Housing and Architecture Bureau Building Guidance Division
Phone: 045-671-4531
Phone: 045-671-4531
Fax: 045-681-2437
Email address: kc-shidotanto@city.yokohama.jp
Page ID: 949-743-418