Flow of inspection procedures

Last Updated January 24, 2024

After the issuance of the confirmed certificate, the construction is completed and the procedure up to the issuance of the inspection certificate will be explained.
(Interim inspection of S, RC construction, and SRC construction is performed by the structural staff (S, RC, SRC construction).)

Contents

  1. Confirmation application procedure completed (issued certificate issued)
  2. Start of construction and end of specific processes
  3. Interim inspection application
  4. Interim inspection
  5. Passed interim inspection
  6. Prior to completion of construction and completion
  7. Completion inspection application
  8. Completion inspection
  9. Issuance of inspection certificate
  10. Notes

At least 14 days before the start of construction, submit a “Notification of Construction Supervisor and Construction Worker”, “Copy of Contract for Construction Supervisory and Construction Work Contract” or “Certificate of Concluding Contract for Construction Supervision and Construction Work” Please attach and submit.

(1) Specific Process

Intermediate inspections may be conducted twice depending on the structure and scale.

(2) Inspection reservation

Please make an appointment for an inspection by telephone two weeks to 10 days before the scheduled intermediate inspection date.

  • Reservation telephone number: Building Guidance Division Guidance Section TEL: 045-671-4531

(1) required documents

Please submit the following documents from 4 days before the inspection date to the day before.

※For small wooden buildings, we ask for application up to three days in advance.

◆Common (submitted one copy)

List of documents
1Intermediate inspection reception check sheet
2Interim inspection application form
3Report (Check sheet) based on Article 12, Paragraph 5 of the Building Standards Act (Construction Supervision and Construction Status) (Note 1)
4Power of Attorney (Note 2)
5A copy of the architect's license (Note 3)
6Photograph of construction status (seal, name of construction supervisor)

◆Precautions for creating construction status photos

Construction status photos are required when receiving the application of Article 7-5 of the Building Standards Law (exceptions for inspection). Refer to the table below, at the end of the construction of the roof hut (3 or more locations), at the end of the construction of the main frame or bearing wall in terms of structural strength (3 or more places), and at the end of the construction of the foundation (3 places) Please submit a total of about 10 photos (distant views, excerpts of details, etc.).

Photography position (reference)
NothingAt the end of construction of the roof hutMajor frames or structures in structural strength
At the end of construction of the load-bearing wall
At the end of construction of foundations
WoodenHut beams, girders, rafters, main house
And firework, etc.
Or other joints
Pillars, sideways and braces;
Or other bearing walls
Other joints
Reinforcing bars of major bottom boards and beams
StructurePillars, beams
Or other joints
Pillars, beams, steel bracelets
Or other joints
Reinforcing bars of major bottom boards and beams
RC constructionOne-story roof plate, pillars,
Reinforcing bars and reinforcing bars
Pillars, beams, walls, floors, and reinforcing barsReinforcing bars of major bottom boards and beams

In addition, please utilize style published in "7. thing to submit at the time of middle inspection" of "format downloading" of Building Guidance Division HP.
For the construction part performed after the interim inspection, please submit a photo when applying for the completion inspection.

◆Only when there is applicable construction (submitted one copy without special notice)

List of documents
NumberConstruction detailsDocumentation
7Pile constructionReport on pile construction results (Note 4)
8Concrete work for buildings that are 3 floors or more or 500m2 or more in RC / PC / SRC constructionConcrete Construction Results Report (Note 4)
9Steel frame construction work for buildings 3 floors or more or 500 m2 or more in SRC constructionReport on the results of steel frame construction (Note 4)
10Small-scale buildings (wooden buildings with less than 2 floors and 500 m2 or less, or non-wooden buildings with less than 1 floors and 200 m2)Conventional framing methodReport on Structure Method of Building Foundation
11Books that clearly indicate the location and type of load-bearing walls and hardware, and the location of the through pillars
12Please submit the following books if there is no special inspection exception.
(1) Wall volume statement, 1/4 balance calculation
(2) Structural review of joints and fittings
13Framed wall construction methodReport on Structure Method of Building Foundation
14Books that clearly indicate the location and type of load-bearing wall
15Please submit the following books if there is no special inspection exception.
(1) Wall volume statement
(2) 40 square meters section line drawing
16Non-woodenFundamental Plan and Structure Detailed Diagram
17If there are minor changes (submitted one copy of each copy) (Note 5)Notification of plan change based on Building Standard Act Article 12, Paragraph 5
18Changed drawing (Note 6)
19Instructions, Certificates, etc. concerning changes

◆Documents required separately for small buildings (submitted one copy)

If the following items apply, you may be required to submit a report.

List of documents
21Raising and standing of foundations, reinforcement drawings of underground garages, etc., and construction status photos
22Reinforcing diagram of retaining walls and photographs of construction status
(Please submit a copy of the inspection certificate for the part (more than 2m) for which the work is applied.)
23Status of ground improvement, pile construction status report

(2) Precautions for Interim Inspection

(1) Confirmation of inspection time

Please be sure to check the time by telephone to the person in charge of the Building Guidance Division in the afternoon of the day before the inspection.

  • Building Guidance Division Guidance Section TEL: 045-671-4531
  • The mid-term inspection pass certificate will be issued by the instructor.
  • Interim inspection pass certificate is required for notification of completion of water supply equipment construction completion.

Please make an appointment for an inspection by telephone two weeks to 10 days before the scheduled completion inspection date.

  • Reservation telephone number: Building Guidance Division Guidance Section TEL: 045-671-4531

(1) required documents

Please submit the following documents from 7 days before the inspection date to the day before.

◆Common (submitted one copy)

List of documents
1Completion inspection reception check sheet
2Completion Inspection Application Form
3Report (Check sheet) based on Article 12, Paragraph 5 of the Building Standards Act (Construction Supervision and Construction Status) (Note 1)
4Power of Attorney (Note 2)
5A copy of the architect's license (Note 3)
6Photograph of construction status (seal, name of construction supervisor)

For “6. Construction Status Photographs (seal of Construction Supervisor, with shooting date)”, please refer to (1) required documents “(Notes on creating construction status photos)” in “3. Application for Intermediate Inspection”. Please refer to.

◆Only when there is applicable construction (submitted one copy without special notice)

List of documents
NumberConstruction detailsDocumentation
7Pile constructionReport on pile construction results (Note 7)
8Concrete work for buildings that are 3 floors or more or 500m2 or more in RC / PC / SRC constructionConcrete Construction Results Report (Note 7)
9Steel frame construction work for buildings 3 floors or more or 500 m2 or more in SRC constructionReport on the results of steel frame construction (Note 7)
10Construction work with a site area of 500 m2 or more in residential use areaGreening facility check sheet
11Small-scale buildings without intermediate inspection (wooden buildings with 2 or less floors and 500 m2 or less or non-wooden buildings with 1 and 200 m2 or less)Conventional framing methodReport on Structure Method of Building Foundation
12Please submit the following books if there is no special inspection exception.
(1) Books that clearly indicate the location and type of load-bearing walls and hardware, and the location of the through pillars
(2) Wall volume statement, 1/4 balance calculation
(3) Structural review of joints and fittings
13Framed wall construction methodReport on Structure Method of Building Foundation
14Please submit the following books if there is no special inspection exception.
(1) Books that clearly indicate the location and type of load-bearing wall
(2) Wall volume statement
(3) 40 square meters section line drawing
15Non-woodenReport on Structure Method of Building Foundation
16If there are minor changes (submitted one copy of each copy) (Note 5)Notification of plan change based on Building Standard Act Article 12, Paragraph 5
17Changed drawing (Note 6)
18Instructions, Certificates, etc. concerning changes

◆Documents required separately for small buildings (submitted one copy)

If the following items apply, you may be required to submit a report.

List of documents
19Raising and standing of foundations, reinforcement drawings of underground garages, etc., and construction status photos
20Reinforcing diagram of retaining walls and photographs of construction status
(Please submit a copy of the inspection certificate for the part (more than 2m) for which the work is applied.)
21Status of ground improvement, pile construction status report

(1) Confirmation of inspection time

Please be sure to check the time by telephone to the person in charge of the Building Guidance Division in the afternoon of the day before the inspection.

  • Building Guidance Division Guidance Section TEL: 045-671-4531

(2) Precautions for Completion Inspection

  • At the time of completion inspection, please submit a copy of the inspection certificate of each inspection certificate (eg, firefighting inspection, inspection related to residential land development and development, inspection of elevators, etc.) at the time of completion inspection application for the building standard-related regulations .
  • Completion inspection in the greening area system
  • Regarding sick house
  • The inspection certificate will be issued by the instructor.

≪When an intermediate inspection is performed once≫

Please submit the applicable one from the "framed construction method (two stories)" "frame construction method (two stories)", "certified building", "reinforced concrete construction" and "steel frame construction".

≪When there are two or more interim inspections≫

The first time is the "basic process", and the second and subsequent times, for the parts constructed after the last intermediate inspection, "framed method (three stories)" "framed construction method (three stories)" "framed construction" Please submit the applicable one from "Steel frame construction".

Please submit only when applying for an inspection by an agent (if you have submitted a power of attorney stating that you will be entrusted to the agent collectively until the inspection application at the time of confirmation application, a copy of it may be used) .

Please submit only if the designer / construction supervisor is an architect and is different from the previous application (not required if it can be confirmed by browsing the architect database, etc.).

Only the part where construction has been completed at the time of the application for interim inspection (Please submit the remaining part by the time of application for completion inspection).

This is not required if you submit it in advance.

Please submit the revised drawing with the contents before the change in red or the drawing before and after the change. When you include change of layout drawing, please submit thing after change of the third side of architectural plan summary book.

Please submit the part that was constructed after the last interim inspection.

For inquiries to this page

Building Guidance Division, Housing and Architecture Bureau Building Guidance Division

Phone: 045-671-4531

Phone: 045-671-4531

Fax: 045-681-2437

Email address: kc-shidotanto@city.yokohama.jp

Return to the previous page