How to use hardware ○ and x
Last Updated July 30, 2024
At the time of the mid-term inspection, you can see sites where the hardware is incorrectly paid and sites where it is quite difficult to pay. Therefore, we decided to introduce good and bad examples of how to put hardware on this page. Please refer to the following URL.
Installation of hole-down hardware and bracelet plate
○Good example ○ Using a bracelet plate to avoid interference with HD.
× Bad Example × The brace plate attached to the pillar cannot be mounted because it interferes with HD.
Bracelet plate to be attached to the spine
○Good example ○ Using a bracelet plate used inside to avoid interference with the spine.
× Bad examples × Strength is not secured because the screws on the bracelet are in the spine.
Installation of foundation seal
○Good example ○ Foundation packing should be placed under the pillar.
× Bad example × If there is no foundation seal under the pillar, the base will be greatly applied.
Inquiries to this page
Building Guidance Division, Housing and Architecture Bureau Building Guidance Department
Telephone: 045-671-4531
Telephone: 045-671-4531
Fax: 045-681-2437
Email address: kc-shidotanto@city.yokohama.lg.jp
Page ID: 519-338-349