Specific process

Last Updated July 30, 2024

Intermediate inspection (Specific Process)

  • Intermediate inspections will be conducted when the total area of each building in the part subject to confirmation application is 50 m2 or more.

  • In Yokohama City, an interim inspection system was implemented in July 1999.
    Buildings for which a certificate of confirmation has been issued after that will require an intermediate inspection when the specified process specified in the table below is reached.

  • Please refer to the inspection procedure page for details.

Intermediate inspection specific process schedule
Intermediate inspection Specific process designation (in charge of structure)
Scale and structure of the buildingSpecific processNumber of Interim Inspections
1st time2nd time (*2)
Non-wooden floors 2 or more or more than 200m2
(Mixed structure and the main structure includes non-wooden structures)
RC and SRCWhen foundation reinforcement is completedWhen the second floor slab reinforcement is completed from the bottom floor
S structureWhen foundation reinforcement is completedWhen jointing of the frame is completed
PC constructionWhen foundation reinforcement is completedThe second one from the bottom floor
When installation of floor slab is completed
Super-high-rise buildings
(height over 60m), etc. (*1)
When foundation reinforcement is completed―(※2)1(2(※2))

※1. Buildings that have been certified by the Minister of Land, Infrastructure, Transport and Tourism pursuant to the provisions of Article 68-25 of the Act under the provisions of Article 20, Paragraph 1, Item 1 of the Act.
※2. For buildings to which the provisions of Article 7-3, Paragraph 1, Item 1 of the Building Standards Act apply (all apartments (including apartments) with 3 or more floors in RC and SRC) , The following implementation process is.

Intermediate inspection time: When the first basic reinforcement is completed
When reinforcement of floor and beam on the second floor is completed

Intermediate inspection specific process schedule
Intermediate inspection Specific process designation (in charge of guidance)
Scale and structure of the buildingSpecific processNumber of Interim Inspections
1st time2nd time
Wooden floor with less than 2 floors and less than 500m2AxisWhen all-axis austerity is completed
2×4When the hut is completed
Certified buildings (* 3) or buildings that have been certified for book abbreviation (* 4)When the foundation and frame is completed
Wooden floor 3 or more or over 500m2 (*5)AxisWhen foundation reinforcement is completedWhen all-axis austerity is completed
2×4When foundation reinforcement is completedWhen the hut is completed
Non-wooden floors 1 and 200m2 or less
(Mixed structure and the main structure includes wooden structure)
Major axesWhen the total frame tension of the wooden part is completed
Major 2 × 4When the wooden hut is completed
Major non-wooden structuresWhen foundation reinforcement is completed
Mixed structure with 2 or more floors
Or more than 200m2
(Main structure is wooden) (*5)
The main structure is framedWhen foundation reinforcement is completedWhen all-axis austerity is completed
The main structure is 2 × 4When foundation reinforcement is completedWhen the hut is completed
The main structure is certified buildings (*3) or
Buildings (* 4) that have been certified as abbreviation of books
Completion of bond between foundation and frame

※3. In accordance with the provisions of Article 68-11, Paragraph 1 of the Act, buildings pertaining to the certification manufactured by a person who has been certified by the Minister of Land, Infrastructure, Transport and Tourism as a manufacturer of model members, etc.
※4. Buildings approved by the Minister of Land, Infrastructure, Transport and Tourism pursuant to the provisions of Article 1-3, Paragraph 1, Item 1 (a) of the Enforcement Regulations pursuant to the provisions of Article 68-25 of the Act
※5. In addition to the above, if there is an underground garage, etc., the specific process may change as a building without a basement. For details, please refer to the page on the inspection of underground garages.

Notes
・You cannot proceed to the subsequent process unless you have been issued an intermediate inspection certificate.
In addition, you may be penalized if you do not undergo legal interim or completion inspections.
・When performing construction, be sure to post the confirmed bulletin board in a place where you can easily see it. In addition, please post the name of the construction supervisor and the contact information of the construction supervisor or the construction contractor on the bulletin board.
・At the time of inspection, if the contents of the confirmation application form and the contents of the construction are different, we may not proceed to the next process. If there is a change, please consult in advance.

  • Floor area subject to inspection
    The floor area to be inspected varies depending on the structure and number of floors of the target building.
    Fees vary depending on the floor area to be inspected, so please fill out the application form so that there is no mistake.
    If there is an underground garage, basement, etc.Inspection of underground garages, etc.Please refer to the following page.
    Inspection feesFee for building confirmation applicationPlease refer to the following page.
Floor area to be inspected
When foundation reinforcement is completedFloor area of foundation
When all-axis austerity is completed
When the hut is completed
Floor area of framed parts
(However, this excludes the area to be inspected when the foundation reinforcement is completed.)
Completion of bond between foundation and frame
(Certified buildings (* 1) or buildings that have been certified for book abbreviation (* 2))
Floor area of the first floor

Completion inspection

・Completion inspection will be conducted for all buildings.

  • Floor area subject to inspection
    Regardless of whether there is an intermediate inspection, it is the total floor area targeted at the time of application for confirmation.

Inquiries to this page

Building Guidance Division, Housing and Architecture Bureau Building Guidance Department

Telephone: 045-671-4531

Telephone: 045-671-4531

Fax: 045-681-2437

Email address: kc-shidotanto@city.yokohama.lg.jp

Return to the previous page

Page ID: 711-649-389