Documents to be submitted after building confirmation and each inspection steel frame construction

Last Updated July 30, 2024

  • Scale of inspection conducted by the person in charge of structure: Buildings over the second floor or more or more than 200m2 have not been certified.
  • For intermediate inspection and completion inspection of wooden structuresIn charge of guidanceIt's the page.

Confirmation application

Issuance of Confirmed CertificateBlank
<Up to 2 weeks before the start of construction>
At least two weeks before the start of the construction, the builder shall submit a “Notification of Appointment of Construction Supervisor and Construction Worker” to a copy of a document certifying that the construction has been supervised and undertaken (eg, construction supervision and construction work) Please attach and submit a contract conclusion certificate).
However, in the case of directly managed construction by the builder, it is not necessary to submit attached documents.
<Up to one week before the start of construction>
When the builder performs the following construction, the construction supervisor or construction builder of the construction concerned must submit the following construction plan (Yokohama City Building Standard Law Enforcement Detailed Regulations Article 17-3 (Hereinafter referred to as "Details").

Start of constructionBlank
<Intermediate inspection process>
The S structure performs an intermediate inspection twice when the foundation reinforcement is completed and when the junction of the shaft is completed. Please refer to the page on the intermediate inspection process for the timing of the intermediate inspection.

<Reservation method for intermediate inspection>
Please make a reservation by phone 10 to 14 days before the intermediate inspection.
Building Guidance Division Structure Manager - TEL: 045-671-4536

Please note that if the inspection is crowded, you may not be able to make a reservation on the desired inspection date.
End of a specific process

Application for intermediate inspectionBlank
<Submission of an interim inspection application>
Please submit an interim inspection application (from 1 to 4) from 4 days before the scheduled inspection date to the day before.
On the four pages, entry can be omitted by submitting a report (construction supervision / construction status) based on Article 12, Paragraph 5 of the Building Standards Law.
A fee is required for the inspection.
For details on how to calculate fees, please refer to the page on how to calculate intermediate inspection fees.

<Attached to the application form>

  • Site guide map
  • Underground map of the part to be inspected (If the construction is divided, specify the inspection range.)

Intermediate inspection
<Documents to be submitted at the time of interim inspection>

<Points of Interim Inspection>

  • When foundation reinforcement is completed
    • Sites and Buildings
      The length of the site in contact with the road
      Placement of buildings
      Retreat distance from the road
    • Securing reinforcing bars
      Lower part of the beam
      Base top and bottom edge
    • Position of Reinforcing bar
      Spacing of main line
      Position of medium suspension reinforcing bar
    • Human hole, penetration sleeve
      Positions in vertical and horizontal directions
      Securing the appearance of star wrap around the sleeves
  • When jointing of the frame is completed
    • Check the construction status of the pillar leg (a check sheet is required depending on the product).
    • Welding conditions
      Check if the welding was performed properly.
    • Deviation of marking of high power bolts
      At the time of high force bolt construction, marking is performed after the primary tightening, and the difference in marking after the secondary tightening is confirmed.
    • Construction status of the composite deck
      Check the pitch of the baking stopper welding and the stud to ensure the fixation level. (Check sheet is required depending on the product.)

<If you pass the intermediate inspection>

If you pass the intermediate inspection, you can proceed to the subsequent process.
However, this cannot be done only after receiving the intermediate inspection pass certificate. (Article 7-3 of the Building Standards Act)
In Yokohama City, a sticker (see the figure below) for which the intermediate inspection has been carried out is attached to the building confirmation display board at the end of the inspection.

Seals that have undergone intermediate inspection

<If the intermediate inspection is not passed>
If you do not pass the intermediate inspection, you will not be able to proceed to the subsequent process.
It is necessary to take necessary measures such as re-inspection and reporting, and pass the intermediate inspection.
Issuance of intermediate inspection pass certificate
<Issuance of intermediate inspection pass certificate>
An intermediate inspection pass certificate will be issued by the person in charge of the structure.
Start of construction after a specific process
<Up to one week before completion inspection>
The completion inspection will be conducted by the instructor.
Please make a reservation by phone 10 to 14 days before the completion inspection.
Building Guidance Division Guidance Section - TEL: 045-671-4531

Please note that if the inspection is crowded, you may not be able to make a reservation on the desired inspection date.
Completed construction
<Submission of completion inspection application>
Please submit the completion inspection application (from 1 to 4) from 7 days before the scheduled inspection date to the day before.
The entry of the structure related on the four pages can be omitted by submitting a construction supervision and construction status report.
A fee is required for the inspection.
For the report attached to the completion inspection application, please see the report form download of the supervisor.

<Documents to be submitted at the time of completion inspection>
Please submit the following report to the person in charge of construction before completion inspection.

<Report of test results of building materials>
The following reports may be submitted after each process is completed. (Article 17-5 of the Detailed Regulations)

  • Concrete strength test report
  • Reinforced Pressure Test Report
  • Welded part ultrasonic inspection test report
  • Reinforcing bar, steel mill sheet
  • Other test results report
  • Photo of construction work

Completion inspection

Certificate of inspection
All the tests have been completed.
The certificate of inspection will be issued by the instructor.

Inquiries to this page

Building Guidance Division, Housing and Architecture Bureau Building Guidance Department

Telephone: 045-671-4531

Telephone: 045-671-4531

Fax: 045-681-2437

Email address: kc-shidotanto@city.yokohama.lg.jp

Return to the previous page

Page ID: 632-505-845

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews