About derailment of municipal subway blue line [Continuous Report 5]
Last Updated June 9, 2019
Press release materials
June 9, 2019
Transportation Bureau Electricity Division
Kazuhiro Fukushima
Phone number: 045-664-2525 (Call Center)
Fax: 045-322-3913
As of 12:30 on June 9, 2019
1 Status of restoration work and future processes
Of the two cars that had been derailed (cars 4 and 5), Cars 5 were raised on the rail at 20:29 yesterday.
As a result, we were able to secure a work space for jacking up Car 4.
In addition to raising the remaining No. 4 car to the rail, we are proceeding with track work such as replacing makuragi in places where possible.
We are also preparing for the transfer of vehicles.
2 Expected restoration
At this time, there is no prospect of resumption of operation in the disconnected section (between Shonandai and Odoriba).
In the future, we will continue to provide information on the status of restoration and the prospect of resumption of operation in disconnected sections.
3 Regarding today's operation status
The Blue Line operates back (every 5 to 7 minutes) between Azamino and the landing all day from the first train.
From 5:30 am to 24:30 am, substitute transportation by bus in the disconnected section will be carried out between Odoriba Station-Nakada Station-Tateba Station-Izumi-Chuo Station (Sotetsu Izumino Line) by two Kawasaki Tsurumi Rinko Bus and 12 official buses. I am.
In addition, due to lack of transportation capacity, we are calling for the use of transfer transportation to other company lines when going out.
4 About tomorrow's service
We are making every effort to ensure that we can resume operation as soon as possible for closed sections.
If it is not possible to resume operation in the disconnected section, the Company will continue to operate.
・The Blue Line runs back between Azamino and the landing (every 5 to 7 minutes) from the first train.
・Closed sections will be transported by bus from 5:30 a.m.
I'm preparing for it.
Press release materials
[Press Release] About derailment of municipal subway blue line [Continue report 5] (PDF: 293KB)
In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
To download Adobe Acrobat Reader DC
Page ID: 783-023-054