[Press Release] About derailment of municipal subway blue line [Continuous Report 3]
Last Updated June 7, 2019
Press release materials
June 7, 2019
Transportation Bureau Electricity Division
Kazuhiro Fukushima
Phone number: 045-326-3874
Fax: 045-322-3913
As of 16:00 on June 7, 2019
1 Current recovery status and future processes
Of the five derailed cars, three cars (vehicles 2, 3, and 6) were raised on the rail.
The sleepers are severely damaged, and it takes time to jack up the trolley. In addition, we are replacing sleepers at places where the vehicle has been moved.
We are continuing to work with the aim of restarting all lines from the first train on Sunday, June 9.
In addition, in addition to JR East, we cooperate with Tokyu for recovery work.
Future Processes
(1) Raise the remaining two derailed vehicles on the rails
(2) Transport of vehicles to depots
(3) Restoration of damaged orbits (replacement of sleepers)
(4) Restoration of the third rail
(5) Safety confirmation by commissioning train
2 Scheduled to operate on Saturday, June 8
The Blue Line will run back all day between Azamino and the landing.
Substitution transportation by bus will be carried out from 5:30 am to 24:30 am by Sotetsu Bus, Kawasaki Tsurumi Rinko Bus, and Authorized Bus between Odoriba Station-Nakada Station-Tateba Station-Izumi-Chuo Station (Sotetsu Izumino Line). I will do it.
In addition, due to lack of transportation capacity, we are calling for the use of transfer transportation to other company lines when going out.
3 injured
We have contacted the customer who offered shoulder pain yesterday and have heard that they will be consulted in the future.
In addition, the crew of the train was diagnosed with bruise in the left knee joint as a result of a re-examination today.
Press release materials
[Press Release] About derailment of municipal subway blue line [Continue report 3] (PDF: 214KB)
In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
To download Adobe Acrobat Reader DC
Page ID: 168-655-622