About sewer self-financing construction

Last Updated October 30, 2024

1 What is sewerage self-financing construction?

Sewerage self-financing construction refers to sewerage works that are performed mainly on public roads at their own expense, assuming that a person other than the public sewerage manager will take over to Motoichi as a public sewerage facility after receiving approval from the public sewerage manager. I mean
。 For example, if you build three new houses on the site of one existing house, you will need three mounting pipes. In this case, if one mounting pipe uses an existing mounting pipe, the remaining two will be newly installed by self-financing work.
In addition, when changing the position of the existing mounting pipe due to the layout of the building (removal of the existing mounting pipe and installation of a new mounting pipe), it will also be at your own expense.

Laws and regulations: Article 16 of the Sewerage Law

2 About constructor

In the case of performing sewerage self-financing construction on roads managed by the country or for construction to install sewerage mains on city roads, in order to judge the economic and technical capabilities of the constructor, general competitive bidding qualified persons in Yokohama City ( Please select a contractor from the contractors listed in the list of construction qualifications, construction type: civil engineering). (Only until September 30, 2017, it can also be selected from companies that have been licensed by the Construction Business Law.)
But, about installation pipe construction (except construction on national highway), we can select constructor from drainage designation construction shop which the mayor of the sewer regulations Article 38 appointed.

※About registration procedure to general competitive bidding qualified person list of Yokohama-shi, please see "qualification examination application" of door (outside site) of Yokohama bid.

3 Design standards for application documents, etc.

About design standard such as application books of sewer self-financing construction, please confirm the next.

Yokohama City Sewerage Design Guidelines (separate page)
Yokohama City Sewerage Design Standard Map (separate page)
Common Specifications for Civil Engineering Works in Yokohama (separate page)
Yokohama City Sewerage Pipe Construction Specifications (separate page)
・Handling summary PDF (PDF: 507KB) such as public sewer facility construction work

4. Application for Approval

When we carry out sewer self-financing construction, we must submit an application for approval of construction of public sewer facilities to Public Works Office of applicable ward before construction and receive approval of public sewer manager (The Mayor of Yokohama).
Please download the application form from the website. Please contact Public Works Office for details of the attached documents.

・Public sewer facility construction approval application PDF (PDF: 109KB), Excel (Excel: 19KB)
・Road excavation site road surface restoration work implementation pledge PDF (PDF: 114KB), Word (word: 20KB) with public sewer facility construction work
・How to fill out the application form and list of attached books PDF (PDF: 270KB)

When newly connecting the mounting pipe to the sewer main maintained on the private road, please attach the landowner's construction consent form [attached book: registered copy (copy), official map (copy)] to the approval application. .

・Construction Consent Form PDF (PDF: 91KB), Word (word: 19KB)

5 About notification of start

Those who have received the letter of approval must submit to Public Works Office along with the schedule to registration form when they start construction of public sewerage facilities.

・Construction of public sewerage facilities, etc. registration form PDF (PDF: 155KB), Excel (Excel: 17KB)
・How to fill out registration form PDF (PDF: 111KB)

6 Extension of construction period

If you wish to extend the construction period for unavoidable reasons, you must submit it to Public Works Office along with the schedule to registration form.
The "unavoidable reason" here is the following cases.
・When negotiations with local residents, etc. are difficult and construction is delayed
・When construction is delayed due to relocation, cutting, protection, etc. of underground buried objects
・When an unexpected accident occurs at the design stage, such as soft ground, spring water, etc., resulting in a change in construction method, etc., resulting in delay in construction work.
・When construction is delayed due to natural disasters, land changes, etc.

・Public sewerage facility construction extension registration form PDF (PDF: 94KB), Excel (Excel: 17KB)
・How to fill in the extension of construction period registration form PDF (PDF: 110KB)

7. Changes

registration form must be submitted to Public Works Office if the construction period is changed for unavoidable reasons or the contents of the facilities at the time of application for approval is to be changed. Please consult with Public Works Office about attached documents.
In principle, the handling when changing the facility contents at the time of application for approval shall be as shown in the following table. However, please consult with Public Works Office in advance.

Details of procedures and changes

Procedures

Details of changes

Those that require submission of change registration form

What should be corrected in the book
(Minor changes)

Area of water collection area

Change of area of 10% or more

Change of area less than 10%

Pipe type, diameter of main pipe

Required

Not required

Extension of the main pipe

Increase or decrease of 10m or more

Change less than 10m

Construction of main pipe

Required

Not required

Gradient of the main pipe

When the difference from the planned gradient is 20% or more

When the difference from the planned slope is less than 20%

Planned bottom height of main pipe

When the difference from the pipe bottom height of the original plan is 20 cm or more, or when the soil is shallow

When the difference from the pipe bottom height of the original plan is less than 20 cm and the soil cover becomes deeper.

Change of main pipe to connect the mounting pipe

Required

Not required

Private position of pipes
Human hole, rainwater

Not required

Required

Water collection, location and quantity of connection, pipe type of mounting pipe, extension

Not required

Required

※For changes other than the changes in the table above, procedures will be decided in consultation with Public Works Office.

・Changes such as construction of public sewer facilities registration form PDF (PDF: 97KB), Excel (Excel: 17KB)
・How to fill in the change registration form PDF (PDF: 187KB)

8 Withdrawal

If construction is canceled due to the circumstances of the applicant, please submit a notice of withdrawal to the competent Public Works Office after attaching the original form of approval.

9 Notification of completion and inspection


The applicant must submit a completed registration form to the competent Public Works Office within five days of the completion of the construction of public sewerage facilities and undergo a completion inspection.

After passing the completion inspection, a certificate of completion inspection is issued to the applicant, and Motoichi takes over free of charge. With the grant, we take over to Motoichi as public sewer facility and are listed in public sewer ledger figure.

10 Basis Rules, etc.

You may need a separate PDF reader to open a PDF file.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

Inquiries to this page

Sewer River Bureau Sewerage Pipeline Department Sewer Management Division

Telephone: 045-671-2832

Telephone: 045-671-2832

Fax: 045-641-5330

Email address: gk-kanrohozen@city.yokohama.lg.jp

Return to the previous page