About the process of interim inspection

Last Updated June 7, 2024

Intermediate inspection is performed when the total area of one building (design building) to be applied for confirmation is 50 m2 or more. The method of calculating the interim inspection fee is on the page of calculating the interim inspection fee.

Interim inspection process schedule
 RC constructionStructureSRC construction
1st intermediate inspection processWhen foundational reinforcement is completed
Parts to be inspected
When foundational reinforcement is completed
Parts to be inspected
When foundational reinforcement is completed
Parts to be inspected
2nd intermediate inspection processWhen the second floor slabs are completed from the bottom floor
Parts to be inspected
When jointing of the frame is completed
Parts to be inspected
When the second floor slabs are completed from the bottom floor
Parts to be inspected
In the case of divisional division1st intermediate inspection processWhen foundational reinforcement is completed
Parts to be inspected
When foundational reinforcement is completed
Parts to be inspected
When foundational reinforcement is completed
Parts to be inspected
2nd intermediate inspection processWhen the second floor slabs are completed from the bottom floor
Parts to be inspected
When jointing of the frame is completed
Parts to be inspected
When the second floor slabs are completed from the bottom floor
Parts to be inspected

For buildings to which the provisions of Article 7-3, Paragraph 1, Item 1 of the Building Standards Act are applied (for apartments with RC buildings and SRC buildings with 3 or more floors (all those including apartment houses) It will be the implementation process.

Interim inspection period : When the first foundational reinforcement is completed
2nd floor and beam reinforcement on the second floor is completed

Parts to be inspected・・・ Parts to be inspected

Interim inspection process schedule
■1st intermediate inspection process
: When foundational reinforcement is completed
RC constructionStructureSRC construction
□Precautions for basic muscle reinforcement inspection
  • If there are some pits, etc., and you want to launch in advance, please consult with the application for intermediate inspection in advance.
  • If you want to cast a pressure-resistant plate in advance
    • If all beam reinforcements have been completed, an inspection will be performed before casting the pressure-resistant concrete is cast.
    • If the beam reinforcement cannot be completed until after casting the pressure-resistant version of the concrete, consult with the applicant for the intermediate inspection in advance. As a general rule, even if all reinforcements have not been completed, an inspection will be performed before casting (the state where the lower end of the beam is visible).
When foundational reinforcement is completed

Fee calculation sample chart

■2nd intermediate inspection process
: When the second floor slabs are completed from the bottom floor
RC construction 

When the second floor slabs are completed from the bottom floor

Fee calculation sample chart

■2nd intermediate inspection process
: When jointing of the frame is completed
Structure 

When jointing of the frame is completed
※For two floors above ground


Fee calculation sample chart

■2nd intermediate inspection process
: When the second floor slabs are completed from the bottom floor
SRC construction 

When the second floor slabs are completed from the bottom floor

Fee calculation sample chart

Interim inspection process schedule
■The first intermediate inspection process (when building is divided into sections)
: When the foundation reinforcement of the construction zone where the foundational reinforcement was first completed
RC constructionStructureSRC construction


  [A Construction Zone]   [B Construction Zone]

Fee calculation sample chart

■The second intermediate inspection process (when building is divided into sections)
: When the second floor slabs are completed from the bottom floor
(If there is a construction zone completed by the second interim inspection, it will be included in the inspection target.)

RC construction 


  [A Construction Zone]   [B Construction Zone]
          When the foundation work has been completed

Fee calculation sample chart

■The second intermediate inspection process (when building is divided into sections)
: When jointing of the frame is completed
(If there is a construction zone completed by the second interim inspection, it will be included in the inspection target.)

Structure 


※When division is divided by plane
※For two floors above ground
[A Construction Zone]   [B Construction Zone]
        Completed foundation work
        If you do so

When jointing of the frame is completed
※When the jointing of the frame to the third floor floor and proceed to the "process after the specific process" (see the Yokohama City Building Standard Law Enforcement Detailed Regulations Appendix 4 (PDF: 424KB))



Fee calculation sample chart

■The second intermediate inspection process (when building is divided into sections)
: When the second floor slabs are completed from the bottom floor
(If there is a construction zone completed by the second interim inspection, it will be included in the inspection target.)

SRC construction 

 [A Construction Zone]   [B Construction Zone]

         When the foundation work has been completed

Fee calculation sample chart

In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

For inquiries to this page

Building Guidance Division, Housing and Architecture Bureau Building Guidance Division

Phone: 045-671-4531

Phone: 045-671-4531

Fax: 045-681-2437

Email address: kc-shidotanto@city.yokohama.jp

Return to the previous page