- Q2-2 How long does it take to obtain a development permit?
Here's the text.
Q2-2 How long does it take to obtain a development permit?
Last Updated July 30, 2024
In the case of a development project that does not fall under a specific large-scale development project, it takes about three months from the start of the ordinance procedure to the consent of the mayor, and in the case of a development project that does not correspond to a specific large-scale development project, it takes about three months from the start of the ordinance procedure to the consent of the mayor, and if the application for a development permit to be submitted after that, about 3 weeks, required documents is completed.
Parts to be published in guides on this answer
- Specific large-scale development projects
"Guide to Adjustment Ordinance"Part 2, Chapter 1, Article 2
"Guide to Adjustment Ordinance"Part 2 Chapter 2 Article 11 (About "Resident Explanation" of the Ordinance)
Contact for inquiries regarding this answer
- About the procedure of permission
Housing and Architecture Bureau Residential Land Examination Department
For specific details in a specific location, please contact the person in charge of each area.
Inquiries to this page
Residential Land Examination Division, Housing and Architecture Bureau Residential Land Examination Department
Telephone: 045-671-4515
Telephone: 045-671-4515
Fax: 045-681-2435
Email address: kc-takuchishinsa@city.yokohama.jp
Page ID: 928-156-523