Guide to Construction Recycling Law and Related Styles

Last update date May 24, 2024

Contents of this page

Notice

  • We abolished notification of cancellation of report based on "Construction Recycling Law" and "Guidelines pertaining to demolition work of buildings". To cancel the reported construction, select "5. When canceling the notified work" from the above "Contents on this page" and check it.
  • We abolished "notified seal" for notice (public construction) based on the Construction Recycling Law.
  • We revised "guide of Construction Recycling Law" and "guide of instruction summary report pertaining to dismantling construction of Yokohama-shi building" with change of office work mentioned above.

Download the guide

Guide to the Yokohama City Construction Recycling Law

Guide to Yokohama City Construction Recycling Law Guide (May 2024) (PDF: 5,412KB)
Information on the main points of the Construction Recycling Law, the judgment flow for notification, and the flow of procedures.

Guidance of Guidance summary report pertaining to dismantling construction of Yokohama-shi building

Guide (May 2024) (PDF: 2,319KB) of instruction summary report pertaining to dismantling construction of Yokohama-shi building (PDF: 2,319KB)
Yokohama City also requests the submission of a report based on the outline of the demolition of buildings with a total floor area of less than 80 m2.
The main points of the outline and matters to be considered are posted.

About downloading of style about Construction Recycling Law

  1. registration form
  2. Changes registration form
  3. Notice
  4. Other reference forms (such as manuals, recycling reports, etc.)

For details, please refer to the “Documents Required for Notification and Points” in the Construction Recycling Law.

Documents to be submitted [Number of copies: 2 copies (original copy and duplicates)]

Batch download of Excel version (with entry example) related to registration form (Excel: 143KB)
Batch download of registration form-related style PDF version (with entry example) (PDF: 1,418KB)

  1. registration form (Form No. 1)
  2. Appendix “Plans for Separation and Demolition, etc.”
  • Appendix 1 “Dismantling of Buildings”
  • Appendix 2 “New construction, extension, repair, and remodeling of buildings”
  • Appendix 3 “Dismantling and New Construction, etc.” (civil engineering work, etc.)
  1. Power of Attorney (Attachment is required when submitted by an agent.) There is a reference form.
  2. Guide map (map showing the location of the construction site, etc.: scale 1/1500)
  3. Process schedule (there is a reference style for demolition work of buildings.)
  4. Photographs or design drawings
  • In the case of demolition work: Photos (about 1 to 2 photos) that show the entire building to be dismantled or structures other than buildings
  • In the case of new construction and extension work of buildings: Layout plan, floor plan of each floor, elevation (when building multiple buildings as a series of construction by building sales, etc., it is acceptable to attach only one representative building for each floor plan and elevation view. However, please note that the layout drawing is required for each building. )
  • In the case of construction work such as repair and remodeling of buildings: Drawings that show construction details (renovation, repair, building equipment construction, etc.)
  • In the case of construction of structures other than buildings (excluding demolition work): Blueprints or construction outline, etc. that understands construction details
  • If you have any questions, please contact us.

After notification, if any of the following changes occur before the start of construction, a change registration form must be submitted.
However, if the prerequisites such as the ordering party, prime contractor, construction location, or type of construction have changed, it is necessary to notify a new notification.

Documents to be submitted [Number of copies: 2 copies (original copy and duplicates)]

Batch download of Excel version related to registration form (Excel: 103KB)
Batch download of PDF version of registration form-related style PDF version (PDF:570KB)

  1. Changed registration form (Form No. 2)
  2. Attached table for change "Plans for separation and dismantling, etc." (* If there is no change in the separate table, attachment is unnecessary.)
  3. Power of Attorney (Attachment is required when submitted by an agent.) There is a reference form.
  4. Guide map (* Attachment is not required if there is no change in the guide map.)
  5. Process schedule (* If there is no change in the contents of the process schedule, attachment is unnecessary.)
  6. Photo or design drawings (* Attachment is not required if there is no change in the photo or design drawing.)

For public works ordered by national agencies or local governments, please submit a notice instead of registration form.

Documents to be submitted [Number of copies: 2 copies (original copy and duplicates)]

Reference style for explanations based on Article 12, Paragraph 1 of the Construction Recycling Law

Based on Article 12, Paragraph 1 of the Act before contracting for construction, when giving an explanation to the ordering party from the prime contractor, it is necessary to issue a document.

Reference style for notification based on Article 12, Paragraph 3 of the Construction Recycling Law

If there is a subcontractor, the prime contractor must inform the subcontractor of the matters to be notified (including a change notification) based on Article 12, Paragraph 3 of the Act. In order to avoid any trouble, please give us a written notice.

Reference form for documents based on Article 13 of the Construction Recycling Law and Article 7 of the Ministerial Ordinance

In addition to what is stipulated by the Construction Business Law at the time of contract contract, it is necessary to mutually issue a document based on Article 13 of the Law.

Reference style for reporting on recycling, etc. based on Article 18 of the Construction Recycling Law

Based on Article 18 of the Act, when the recycling of specified construction material waste is completed, it is necessary to submit a report on recycling, etc. from the prime contractor to the ordering party in writing.

Download of style about instruction summary (demolition work of building less than 80 m2) pertaining to demolition work of building

  1. Demolition work registration form
  2. Demolition work [Change] registration form
  3. Demolition work registration form [for public works]

For details, please refer to the main points of the guidelines for dismantling construction of buildings and required documents.

Documents to be submitted [Number of copies: 2 copies (original copy and duplicates)]

Disassembly work registration form-related style Excel version (with entry example) (Excel: 82KB)
Collective download of registration form-related form PDF version (with entry example) (PDF: 650KB)

  1. Demolition work registration form (Form No. 1)
  2. Appendix 1 (different from Appendix 1 of the Construction Recycling Law.)
  3. Power of Attorney (Attachment is required when submitted by an agent.) There is a reference form.
  4. Guide map (map showing the location of the construction site, etc.: scale 1/1500)
  5. Process schedule (there is a reference style for demolition work of buildings.)
  6. Photographs (a photo showing the overall appearance)

Please submit dismantling work [change] registration form at least 7 days before the start of construction only if a change occurs before the start of construction after notification.
However, if the prerequisites such as a change in the prime contractor or the location of the construction change, it is necessary to submit a notice of decontinuation and submit a report again.

Documents to be submitted [Number of copies: 2 copies (original copy and duplicates)]

Dismantling work [Change] registration form-related style Excel version (Excel: 68KB)
Demolition work [change] registration form-related style PDF version (PDF: 369KB)

  1. Demolition work [Change] registration form (Form No. 2)
  2. Appendix 2 (Different from Appendix 2 of the Construction Recycling Law.) ※If there is no change in the attached table, it is not necessary to attach.
  3. Power of Attorney (Attachment is required when submitted by an agent.) There is a reference form.
  4. Guide map (* Attachment is not required if there is no change in the guide map.)
  5. Process schedule (* If there is no change in the contents of the process schedule, attachment is unnecessary.)
  6. Photographs(※ If there is no change in the photo.)

In the case of public works ordered by a national institution or local government, please submit the demolition work registration form [for public works] before starting construction.

Documents to be submitted [Number of copies: 2 copies (original copy and duplicates)]

About the case of canceling the reported construction

If you want to cancel the submitted work, please contact the "Inquiry to this page" at the bottom of this page.
We will confirm your receipt number when you contact us, so please check the receipt number on your copy in advance.
In addition, please dispose of the issued "reported seal" as it is not necessary to return it.

In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

For inquiries to this page

Resources and Waste Recycling Bureau Business Waste Management Section Administration Section

Phone: 045-671-3446

Phone: 045-671-3446

Fax: 045-663-0125

Email address: sj-kensetu@city.yokohama.jp

Return to the previous page

Page ID: 167-366-139

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews