Tsuruyabashi Bridge Replacement Business
Last Updated December 11, 2017
Shimbashi was opened on September 29, 2017. Thank you very much for your cooperation.
Business Overview
Tsuruyabashi Bridge a bridge that connects 2-chome Tsuruya-cho, Kanagawa-ku and Minamiko 1-chome, Nishi-ku, and spans the Katabira River Branch Canal Aratama River
Over fifty years have passed since the completion of the old bridge, Tsuruyabashi Bridge was aging. In addition, the number of pedestrians a day was very large, about 50,000, but the sidewalk was narrow and hindered traffic, so replacement work was carried out.
After the replacement, the sidewalk was widened, the earthquake resistance and flood control safety were increased, and the bridge was reborn as a safe and secure bridge.
Business Locations
From 2-17, Tsuruya-cho, Kanagawa-ku, Yokohama-shi to 1-2 Minamiko, Nishi-ku
Fiscal year
From FY2010 to FY2017
Outline of plan
・Old bridge
Bridge length: 25.364ⅿ
Total width: 10.625m (roadway 4.97m, sidewalk 2.64m, 3.015m)
・Shimbashi
Bridge length: 25.4ⅿ
Total width: 15.75m (roadway 4.75m, sidewalk 5.5m x 2)
Introduction of construction status
1.Construction of temporary work yards and temporary sidewalk
In order to remove the old bridge, a temporary work road and a temporary sidewalk that will be a detour for pedestrians will be constructed.
Construction of temporary work yard
Temporary sidewalk
2.Removal of old bridge
Remove the superstructure (bridge girder / floor slabs) and substructures (piers / abutment) of the old bridge.
Removal of bridge girder and floor slabs
Removal of piers and abutment
3.Construction of substructure
The substructure (abutment) of the new bridge will be constructed.
Abutment installation
Gyro pressing method
4.Manufacture and installation of superstructures
A new bridge superstructure (bridge girder / floor slabs) will be manufactured and installed at the site.
Superstructure Temporary Status
Manufacture of girder
5.Removal of temporary yards and temporary sidewalk
After installing the superstructure of the new bridge, the temporary work yard and the temporary sidewalk that will be a detour for pedestrians.
Removal of temporary workbench
Removal of temporary sidewalk
6.Completed
The new Tsuruyabashi Bridge is completed by paved on and around the bridge with asphalt.
Installation of guidance block
Asphalt pavement
(Reference) Opening ceremony
Thank you very much for your cooperation.
Opening ceremony
For inquiries to this page
Bridge Division, Road and Highway Bureau Construction Department
Phone: 045-671-2791
Phone: 045-671-2791
Fax: 045-662-3945
Email address: do-kyoryo@city.yokohama.jp
Page ID: 303-201-562