Tsuruyabashi Bridge Replacement Business
Last Updated December 11, 2017
Shimbashi was opened on September 29, 2017. Thank you very much for your cooperation.
Business Overview
Tsuruyabashi Bridge is a bridge that connects 2-chome Tsuruyacho, Kanagawa-ku and 1-chome Minamiko, Nishi-ku, and spans Katabira River branch channel (formerlyAratama River).
More than 50 years have passed since the completion of the old bridge, Tsuruyabashi Bridge, was aging. In addition, the number of pedestrians per day was very large, about 50,000, but the sidewalk was narrow and hindered traffic, so replacement work was carried out.
After the replacement, the sidewalk was widened, earthquake resistance and flood control safety increased, and it was reborn as a safe and secure bridge.
Business Locations
From 2-17 Tsuruyacho, Kanagawa-ku, Yokohama-shi to 1-2 Minamiko, Nishi-ku
Fiscal year
From FY2010 to FY2017
Outline of the plan
・Old Bridge
Bridge length: 25.364ⅿ
Full width: 10.625m (roadway 4.97m, sidewalk 2.64m, 3.015m)
・Shimbashi
Bridge length: 25.4ⅿ
Full width: 15.75m (roadway 4.75m, sidewalk 5.5m x 2)
Introduction of construction status
1.Construction of temporary work structures and temporary sidewalks
In order to remove the old bridge, a temporary work road and a temporary sidewalk will be constructed as a detour for pedestrians.
Construction of temporary work platform
Temporary sidewalk
2.Removal of old bridges
Remove the superstructure (bridge girder / floor slab) and the substructure (bridge / abutment) of the old bridge.
Removal of bridge girder and floor slabs
Removal of piers and abutments
3.Construction of substructures
The substructure of the new bridge (abutment) will be constructed.
Installation of abutment
Gyro press method
4.Production and construction of superstructures
A new bridge superstructure (bridge girder / floor slab) will be produced and installed at the site.
Temporary construction status
Production of girder
5.Removal of temporary construction and temporary sidewalks
After the superstructure of the new bridge is installed, the temporary work platform and the temporary sidewalk, which will be a pedestrian detour, will be removed.
Removal of temporary work benches
Removal of temporary sidewalks
6.Completed
The bridge and surrounding areas are paved with asphalt to complete the new Tsuruyabashi Bridge.
Installation of guidance blocks
Asphalt pavement
(Reference) Opening ceremony
Thank you very much for your cooperation.
Opening ceremony
Inquiries to this page
Bridge Division, Road and Highway Bureau Construction Department
Telephone: 045-671-2791
Telephone: 045-671-2791
Fax: 045-662-3945
Email address: do-kyoryo@city.yokohama.lg.jp
Page ID: 303-201-562