Shin-Urashima Bridge Replacement Business
Last Updated January 16, 2018
We are promoting the replacement business of Shin-Urashima Bridge. At noon on Friday, January 12, 2018, we started service of new bridge.
In the future, we will remove the temporary humanitarian bridge that has already been closed and restoration work on land borrowed from local residents.
Business Overview
Shin-Urashima Bridge, which spans the second river of the Irie River in Kanagawa Ward, was built in the late Meiji era to the early Taisho (estimated). After that, Nippon Carbon Co., Ltd. used it as a dedicated bridge, replaced the girder in 1955, and in 1971 reinforcing the substructure and widened the sidewalk with the construction of the Metropolitan Expressway Yokohama Haneda Line, and in 1987 Yokohama City Has been transferred.
Due to deterioration over time, the strength of the piers and floor slabs has been reduced, and earthquake countermeasures are also urgently needed from the aspect of disaster prevention. We carried out maintenance of car sidewalk.
Business Locations
From 363, Urashima-cho, Kanagawa-ku, Yokohama-shi to 1-1-25 Shin-Urashima-cho
Location map
Fiscal year
FY2014 to FY29 (new bridge commenced operation on January 12, 2018)
Outline of plan
[Old Bridge]
Bridge length 54.2m (5 spanned girder bridge)
Width 4.3m (roadway 2.8m sidewalk 1.5m)
[New Bridge]
Bridge length 49.0m (two continuous steel sheet plate plate girder bridge)
Width 13.0m (roadway 7.0m sidewalk 6.0m (3.0m on both sides))
Construction status
1. Construction of temporary humanitarian bridge construction (construction started in July 2012)
Installation status (Aug. 2012)
Installation completed (Aug. 2013)
2.Removal of the old bridge (construction started in July 2013)
Removal status (November 2013)
Removal completed (March 2014)
3.Workplace installation work (construction started in August 2014)
Installation status (Aug. 2014)
Completion of installation (December 2014)
4.RC pier construction (P1 pier)
Temporary construction Temporary Deadline construction work (construction started in January 2015)
Installation status (February 2015)
Completed installation
Place Uchitake (March 2015)
Piper skeleton construction (June 2015)
Piper skeleton construction [Concrete Place] (July 2015)
P1 piers installation completed (August 2015)
5.Abutment work (A2 abutment)
Place Uchitake (December 2015)
Abutment frame construction [Rebar assembly] (December 2015)
Abutment frame construction [Concrete Place] (January 2016)
A1 abutment installation completed (February 2016)
6.Superstructure construction
Vertical feeders (March 2017)
Crossing (May 2017)
7.Paving work, other accessories, etc.
Status of pavement work (August 2017)
Completion of paving roads (December 2017)
8.Photo of the new bridge
New bridge (front)
New bridge (from high altitude)
New bridge (side)
Main pillar (image of brick pier of an old bridge)
For inquiries to this page
Bridge Division, Road and Highway Bureau Construction Department
Phone: 045-671-2791
Phone: 045-671-2791
Fax: 045-662-3945
Email address: do-kyoryo@city.yokohama.jp
Page ID: 984-715-665