Shin-Urashima Bridge Rebuilding Project
Last Updated January 16, 2018
We are promoting the replacement business of ShinUrashima Bridge. At noon on Friday, January 12, 2018, we started service of new bridge.
In the future, we will remove temporary humanitarian bridges that have already been closed and restore land borrowed from local residents.
Business Overview
The Shin-Urashima Bridge, which spans the Irie River No. 2 river in Kanagawa Ward, was built from the late Meiji era to the early Taisho (estimated). After that, Nippon Carbon Co., Ltd. used it as a dedicated bridge, replaced the girder in 1955, and reinforced the substructure and widened the sidewalk with the construction of the Metropolitan Expressway Yokohama Haneda Line in 1971, and Yokohama City was transferred in 1987.
Due to the deterioration over time, the strength of piers and floor slabs has been reduced, and earthquake countermeasures are also urgently needed in terms of disaster prevention. We carried out maintenance of sidewalk.
Business Locations
From 363 Urashima-cho, Kanagawa-ku, Yokohama-shi to 1-1-25 Shinurashima-cho
Location map
Fiscal year
FY2014 to FY2019 (Commencement of new bridges on January 12, 2018)
Outline of the plan
[Old Bridge]
Bridge length 54.2m (5-diameter single pure plate girder bridge)
Width 4.3m (roadway 2.8m sidewalk 1.5m)
[New Bridge]
Bridge length 49.0m (2-diameter continuous steel sheet plate girder bridge)
Width 13.0m (roadway 7.0m sidewalk 6.0m (3.0m sidewalk on both sides))
Construction status
1. Construction of temporary humanitarian bridge (construction started in July 2012)
Installation status (August 2012)
Completed installation (August 2013)
2.Removal of the old bridge (construction started in July 2013)
Removal status (November 2013)
Completed removal (March 2014)
3.Construction work (started in August 2014)
Installation status (August 2014)
Completed installation (December 2014)
4.RC pier construction (P1 pier)
Temporary deadline for temporary construction (construction started in January 2015)
Installation status (February 2015)
Completed installation
(March 2015)
Bridgestone framework (June 2015)
Bridge frame construction [Concrete casting] (July 2015)
Completed installation of P1 piers (August 2015)
5.Abutment (A2 abutment)
Place driving piles (December 2015)
Abutment frame construction [Reinforcing bar assembly] (December 2015)
Abutment framework [Concrete casting] (January 2016)
A1 Completed installation of abutment (February 2016)
6.Superstructure construction
Vertical feeder (March 2017)
Cross-planting work (May 2017)
7.Pavement work, other accessories, etc.
Pavement work (August 2017)
Completion of pavement work on the installation road (December 2017)
8.Photo of a new bridge
New Bridge (front)
New bridges (from high altitudes)
New Bridge (side)
Main pillar (image of the brick pier of the old bridge)
Inquiries to this page
Bridge Division, Road and Highway Bureau Construction Department
Telephone: 045-671-2791
Telephone: 045-671-2791
Fax: 045-662-3945
Email address: do-kyoryo@city.yokohama.lg.jp
Page ID: 984-715-665