Yokohama City Cliffs [reduce disaster damage] Measures Construction Subsidy Program
Last Updated May 16, 2024
About grant application of 2024
Grant application acceptance period
About grant application of 2024, we start acceptance from April 8, 2024.
The deadline for grant application is scheduled until December 27, 2024.
※We also accept submissions by mail.
For more information, please refer to the following link.
Overview of the reduce disaster damage Construction Subsidy Program
Brochure
It can be downloaded from the cliff reduce disaster damage countermeasure construction subsidy program brochure (PDF: 1,141KB).
Target cliffs
Cliffs that fall under the following items are eligible.
- Artificial cliffs such as natural cliffs and retaining walls
- Cliffs where the height from the ground surface exceeds 2 meters or cliffs where roads may be damaged, cliffs exceeding 1 meter above or 2 meters below the road surface
- Cliffs with an inclination angle of 30° or more
- Cliffs that may damage buildings or roads to be used for living due to landslides
Applicable works
Works that fall under the following items are eligible.
- In principle, construction that does not require procedures under the Building Standards Law and the Regulation Law for Residential Land Development
- Construction where the height and position of cliffs do not change
Applicable construction methods
Type | Construction method | Maximum amount |
---|---|---|
Construction of retaining walls | Intertect retaining wall, RC retaining wall | 1 million yen |
Cut and embankment work | Cutting and embankment work | 1 million yen |
Slope protection work | Framework, mortar and concrete spraying | 1 million yen |
Measures against falling rocks | Rock fall protection fence construction, rock fall protection net construction | 500,000 yen |
Waiting wall construction | Waiting wall construction | 1 million yen |
H-type steel concrete protective fence | 500,000 yen | |
Landslide prevention work | Deterrence pile work, rebar insertion work | 1 million yen |
Groundwater removal work | 500,000 yen | |
Reinforcement of retaining walls | Law frame work, earth anchor work, reinforcing bar insertion work | 1 million yen |
Rock fall protection net construction, wire mesh reinforcement work, flat steel reinforcement work, groundwater removal work | 500,000 yen | |
Removal of additional piles | Removal of additional stacking parts | 1 million yen |
Wire mesh reinforcement work for existing retaining walls, flat steel reinforcement work | 500,000 yen |
※Subsidies may also be issued for other than the above construction methods.
Amount of grant
The amount of the subsidy is 1/2 of the target construction cost or the unit price determined by the city ※The lesser of the amount calculated by (only some construction methods) or the limit (1,000,000 yen or 500,000 yen)
※The unit price per 1 m2 per vertical projection area in FY2024 is as follows.
・Retaining wall construction and waiting retaining wall construction 99,000 yen /㎡
・Cut or embankment work and removal work for additional piles 26,000 yen /㎡
・Law frame construction 78,000 yen /㎡
・Mortar and concrete spraying work 23,000 yen/㎡
For the vertical projection area, please refer to the subsidy calculation method (PDF: 569KB).
Precautions for Use of the System
- When we apply for grant of grant, coordination with Building Disaster Prevention Section cliff is necessary. Please contact us in advance.
- If you have started construction contracts or construction before the grant is decided, you cannot use the subsidy system.
- When we receive grant of grant, it is necessary to have you conclude construction contract with company with headquarters in the city.
- Please submit a completion report by the end of February of the year in which you received the grant decision.
Outline
The grant system is operated based on the following outlines. (Enforced in April 2024)
Please check the outline for details on the target cliffs and construction.
Yokohama-shi cliff ground reduce disaster damage measures construction subsidy grant summary (PDF: 140KB)
Collection of grant summary styles (word: 39KB)
Flow and Form of Procedure
Submission of Proposals | ・reduce disaster damage Cliff construction subsidy proposal (No. 17 style) |
---|---|
Grant application | ・Cliff reduce disaster damage Construction Subsidy Grant Application Form (No. 1 style) |
<If necessary> | |
<When withdrawing the application before receiving the grant decision> | |
After receiving the grant decision | <Slowly after the construction contract> |
<When it turns out that the contents of the grant application will be changed> | |
Construction completion report | ・Completion report (No. 12 style) |
Grant request | ・reduce disaster damage Cliff construction subsidy grant bill (No. 14 style) |
<When applying under joint name> |
You may need a separate PDF reader to open a PDF file.
If you do not have it, you can download it free of charge from Adobe.
To download Adobe Acrobat Reader DC
Inquiries to this page
Building Disaster Prevention Section, Housing and Architecture Bureau Planning Department
Telephone: 045-671-2948
Telephone: 045-671-2948
Fax: 045-663-3255
Email address: kc-gakebousai@city.yokohama.jp
Page ID: 297-514-435