Kawai Purification Plant was founded in 1901 and built a major facility in operation in 1963. However, due to aging and earthquake resistance problems, we decided to renew it.
When renewing, it is necessary to operate the existing facilities, so space saving can be reduced compared to the rapid sand filtration method, and effective use of location energy due to the height difference from the water source Doshi River. We decided to adopt a membrane filtration method that can do it.
In addition, since the membrane filtration method is a new technology, PFI that allows private-sector technology and know-how can be used. ※We can expect a reduction in total cost by adopting a method and combining design, construction, and maintenance, so we decided to proceed with redevelopment using PFI.
※1 PFI: This is a business method that uses private funds and management and technical skills (know-how) to construct, maintain, manage, and operate public facilities.
Items | Contents |
---|---|
Business Name | Kawai Purification Plant Redevelopment Project |
The other party to the contract | WaterNext Yokohama Co., Ltd. |
Contract amount | 27,679,173,328 yen (including tax) |
Business period (overall) | From April 1, 2009 to March 31, 2006 |
Facility maintenance period [Phase 1] | From April 1, 2009 to March 31, 2014 |
Facility maintenance period [Second Stage 2] | From April 1, 2014 to March 31, 2015 |
Operating and maintenance period [20 years] | From April 1, 2014 to March 31, 2006 |
Water purification capacity | Water produced: 171,070m3/day or more |
Water purification treatment method | Membrane filtration method (ceramic membrane) |
Distribution reservoir | Effective capacity: 30,000m3 |
Wastewater treatment facilities | Wastewater and dehydration treatment facilities |
Time | Items |
---|---|
December 14, 2007 | Announcement of Implementation Policy |
March 3, 2008 | Selection of Specific Business and Publication of Business Requirement Standards (draft) |
June 3, 2008 | Publication of tender instructions, etc. |
September 24, 2008 | Acceptance of bids and proposals |
December 4, 2008 | Determination of winning bidder |
December 26, 2008 | Conclusion of basic agreement |
February 27, 2009 | Conclusion of business contracts |
April 1, 2009 | Start of business |
Location | 2-8-4, Kitasaiwai, Nishi-ku |
---|---|
Representative Director | Toru Kawakami |
Date of establishment | January 22, 2009 |
Shareholders' equity | 100 million yen |
Shareholders | Metawater Co., Ltd. (person responsible for the manufacture of membrane filtration equipment, part of machinery and electrical work, and part of maintenance) |
Major Subsidiaries: Kashima Construction Co., Ltd. (civil engineering and construction work), Tokyo Design Office Co., Ltd. (design, construction supervision)
Water Works Bureau Customer Service Center
Phone: 045-847-6262 Fax: 045-848-4281
※Please be careful not to make a mistake.
Water Works Bureau Water Purification Department Kawai Purification Plant
Phone: 045-921-1174
Phone: 045-921-1174
Fax: 045-922-4989
Email address: su-kawaijosui@city.yokohama.jp
Page ID: 843-053-337