Land readjustment project around Shin-Tsunashima Station

Last Updated March 13, 2024

The latest announcement

  • On March 5, 2024, we decided to change the business plan and announced it. The revised business plan (fifth change) is pasted at the bottom of the same page.
  • On October 19, 2023, the 10th Shin-Tsunashima Station Area Land Readjustment Council was held. Please refer to the relevant items for meeting materials.

Overview of Land Readjustment Project

About land readjustment project

In the area around Shin-Tsunashima Station, the Tokyu Shin-Yokohama Line Shin-Tsunashima Station opened in the area in March 2023, and it is hoped that the effective use of land and the formation of a good urban area in front of the station will be in line with the opening of the new station. .
For this reason, the city planning road Tokyo Maruko Yokohama Line (commonly known as Tsunashima Kaido) and Tsunashima Hiyoshi Line, which are important arterial roads around the Area, will be developed, and the Tsunashimahigashi Line, a city planning road that runs north and south through the area, will be newly developed. Will be maintained.
In this way, we plan maintenance, improvement of public facilities and, by arranging land, aim to form a healthy and good urban area suitable as a new station square, and contribute to local development.

Business Overview

Business Overview

Overview
Business nameYokohama International Port Construction Project Land readjustment project around Shin-Tsunashima Station
EnforcerYokohama-shi
Enforcement areaParts of Tsunashima Higashi 1-chome and 2-chome, Kohoku-ku
Enforced areaApproximately 2.7 hectares
Effective period

From FY2016 to FY2026 (including liquidation period)

Public facilities, etc.・Urban planning road Tokyo Maruko Yokohama Line (width: 20m)
・Urban planning road Tsunashima Hiyoshi Line (width: 15m)
・Urban planning road Tsunashimahigashi Line (width 16.75m)
・Blocked roads (width 13m, etc.)
OthersIntegrated implementation with urban redevelopment projects

Blueprint

Land readjustment project plan

History of Business

Progress of Business
Year and Year Contents Remarks
September, 2016 Decision on city planning
February, 2017 Decision of business plan
January, 2018 Changes in Business Plan [1st]

・Setting of construction zone
・Establishment of Urban Redevelopment Project Area

April, 2018 Determination of land evaluation standards and land replacement design standards
June, 2018 1st Temporary replacement lot designation No. 1 Construction Zone
March, 2021 Change of Business Plan [2nd]

・Area transfer between urban planning roads and open spaces
・Changes in funding plans

March, 2021 2nd Temporary Replacement Designated No. 2 Construction Zone
January, 2022 Change of Business Plan [3rd]

・Extension of subsidy period
・Changes in funding plans

September, 2023 Changes in Business Plan [4th]

・Change of shape of open space
・Extension of enforcement period and subsidy period
・Changes in funding plans

March, 2024 Change of Business Plan [Fifth]

・Extension of subsidy period
・Changes in funding plans


Land Readjustment Council

Information on Meetings

Information on Meetings ※It's finished   

Date and time of the event

From 14:00 on Thursday, October 19, 2023

Name of the meeting

The 10th Shin-Tsunashima Station Area Land Readjustment Council

Venue

4th floor (Room 401) Development Office around East Exit Tsunashima Station

Agenda item

・About report of result of council committee election
・New Appointment of Chairman and Deputy Chairman
・About change of temporary substitute lot designation
・Future Business Schedule

Non-disclosurePartially private
Number of observers10 people
How to apply for hearing

・We accept from 13:30 on the 4th floor (room 401) of Tsunashima Station East Exit Development Office.
・It will be on a first-come, first-served basis.

Contact information

Urban Development Bureau Tsunashima Station East Exit Development Office
Telephone 045-531-9600


Purpose of establishment of the council

Established as an advisory body for the enforcer regarding the land readjustment project around Shin-Tsunashima Station.
The council is composed of members elected by the right holders and members elected by academic experts, and the enforcer is interested in the right holders of the land in the enforcement area, such as deciding on a resettlement plan and designating a temporary replacement lot. If you take a disposition, reflect your opinion in that decision.

Laws and regulations

・Article 138-4, Paragraph 3 of the Local Government Act
・Article 56, Paragraph 1 of the Land Readjustment Act
Yokohama International Port Construction Project Around Shin-Tsunashima Station Area Land Readjustment Project Enforcement Ordinance Article 7 (outside site)

Date of installation

November 9, 2017

Council member list

Council Management Rules

Council materials and minutes

About building act in enforcement district

When we perform building acts in area of land readjustment project, permission is necessary.
Specifically, please see this (procedures such as buildings in area of city area development business).

About standards about land readjustment project

You may need a separate PDF reader to open a PDF file.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

Inquiries to this page

Tsunashima Station East Exit Development Office, Urban Development Department, Urban Development Bureau

Telephone: 045-531-9600

Telephone: 045-531-9600

Fax: 045-531-9605