Here's the text.
Situation of District
Last Updated May 27, 2024
Current situation and direction of town development
In the vicinity of East Exit Tsunashima Station, we are promoting the development of new Tsunashima Station, a new station on the Tokyu Shin-Yokohama Line.
Many roads do not have sufficient sidewalks in this area, and there are traffic issues such as chronic traffic congestion on surrounding roads such as the Tsunashima Kaido. In addition, the area around the new station was not fully utilized.
The new station will open in March 2023, and first, the land readjustment project and the urban redevelopment project will be integrated around the new station, and the maintenance of urban infrastructure such as roads and land suitable for the land adjacent to the new station We are promoting use. Next, we plan to implement an urban redevelopment project at Tsunashima Station East Exit Station. We will promote community development in both areas and enhance the functions of the entire East Exit of Tsunashima Station.
Town Development around East Exit Tsunashima Station - Overview -
This is a leaflet that briefly summarizes the current situation and initiatives.
※When specifying printing, double-sided printing (short-sided binding) will make the A3 spread leaflet shape.
※The content is the same as above. A4 Please use this when printing.
History of Town Development in the District
Year and Year | Contents |
---|---|
November, 1983 | Established Tsunashima East Exit Redevelopment Council |
August, 1997 | Tsunashima Station East Exit Station Area Urban Redevelopment Preparatory Association established |
June, 2004 | Dissolution of Tsunashima Station East Exit Station Area Urban Redevelopment Preparatory Association |
January, 2008 | Formed by Tsunashima East Exit Redevelopment Council Land Owners' Association |
May, 2014 | Establishment of a preparatory meeting for town planning around Shin-Tsunashima Station |
December, 2014 | Establishment of Shin-Tsunashima Ekimae Area Urban Redevelopment Preparatory Association (restructured from Shin-Tsunashima Ekimae Area Redevelopment Preparatory Meeting) |
March, 2016 | Tsunashima Station East Exit Station Area Urban Redevelopment Preparatory Association (restructured from Tsunashima East Exit Station Area Redevelopment Preparatory Meeting) |
September, 2016 | Urban planning decision of land readjustment project around Shin-Tsunashima Station |
February, 2017 | Business plan decision of land readjustment project around Shin-Tsunashima Station |
August, 2017 | Established Tsunashima East Exit City Planning Study Group |
November, 2018 | Establishment of Shin-Tsunashima Station Area Urban Redevelopment Association (Business Authorization) |
February, 2020 | Change in city planning of Tsunashima Higashi 1-chome District Planning |
July, 2022 | Tsunashima Station East Exit Station Area First-Class Urban Redevelopment Project |
March, 2023 | Opened "Shin-Tsunashima Station" on the Tokyu Shin-Yokohama Line |
October, 2023 | New Tsunashima Station Area Type 1 Urban Redevelopment Project Facility Construction completed |
December, 2023 | Tsunashimahigashi Line opening, Shin-Tsunashima Station bus stop service start |
January, 2024 | Start of operation of Shin-Tsunashima Station bicycle parking lot |
March, 2024 | Completed Kohoku Kumin Cultural Center (nicknamed "Miskey Hall") |
District planning
As for the details of city planning including policy of land use, please see the following page.
You may need a separate PDF reader to open a PDF file.
If you do not have it, you can download it free of charge from Adobe.
To download Adobe Acrobat Reader DC
Inquiries to this page
Tsunashima Station East Exit Development Office, Urban Development Department, Urban Development Bureau
Telephone: 045-531-9600
Telephone: 045-531-9600
Fax: 045-531-9605
Email address: tb-tsunashima@city.yokohama.lg.jp
Page ID: 256-460-121