31.Electric Power Development Isogo thermal power station update (new 1.2 machine) plan environmental assessment procedure

Last update date March 20, 2019

List of procedure situation
Business name Electric Power Development Isogo thermal power station update (new 1.2 machine) plan
Business operation area 37-2, Shinisogocho, Isogo-ku, Yokohama-shi
Business type Enlargement (update of power station) of factory
Company Electric Power Development Co.,Ltd Isogo thermal power station
Brief

Submission: October 6, 1995
Notification, general inspection: It is November 13, 1995 from October 13, 1995

Common knowledge ward Naka Ward, Isogo Ward, Konan Ward, Kanazawa Ward
Briefing session

October 24, 1995, October 26, October 31, November 1, November 5 (five times in total) a total of 1,178

Statement of position tsusuu: Four of them
Evaluation book

Submission: December 12, 1995
Notification, general inspection: It is January 4, 1996 from December 15, 1995

Statement of position tsusuu: One of them
Examination committee

Request: December 26, 1995
Report: April 25, 1996

Examination book

Making: May 24, 1996
Notification: May 24, 1996

Report

Submission: June 25, 1996
Notification: July 5, 1996

Subsequent investigation plan Submission: August 30, 1996
Start registration form

Report: August 30, 1996
Construction start day: June, 1998

Completion registration form

Report: November 1, 2010
Completion day: October 31, 2010


Inquiry to this page

Environmental Planning Bureau policy coordination department environmental assessment section

Telephone: 045-671-2495

Telephone: 045-671-2495

Fax: 045-663-7831

E-Mail address [email protected]

Return to the previous page

Page ID: 110-757-266

We come back to the top