23.Sotetsu Izumino Line, Third Phase Extension Project Environmental Impact Assessment Procedures

Last Updated March 19, 2019

List of procedures
Business name Sotetsu Izumino Line 3rd extension project
Project Implementation Area

Starting point: 3540, Izumicho, Izumi-ku, Yokohama-shi
End point: 217, Shimoiidacho, Izumi-ku, Yokohama-shi

Business type New construction of railways
Business operators Sagami Railway Co., Ltd.
Preparedness

Submission: November 18, 1991
Public notice and inspection: From November 26, 1991 to 25, 2012

Well-known ward Izumi Ward
Briefing Session December 15, 1991 and December 16, 1991 (twice in total) 164 people
Statement of Position Number of written opinion: 26 copies
Evaluation Report

Submission: February 14, 1992
Public notice and inspection: From March 5 to March 19, 1992

Statement of Position Number of written opinion: 0 copies
Examination committee

Request: February 27, 1992
Report: December 11, 1992 (five deliberations)

Examination Report

Create: December 18, 1992
Public notice: February 15, 1993

Report

Submission: March 12, 1993
Public notice: March 23, 1993

Started registration form

Notification: February 21, 1994
Construction start date: February 14, 1994


Inquiries to this page

Environmental Impact Assessment Division, Environmental Conservation Department, Green Environment Bureau

Telephone: 045-671-2495

Telephone: 045-671-2495

Fax: 045-663-7831

Email address: mk-eikyohyoka@city.yokohama.lg.jp

Return to the previous page

Page ID: 355-608-184

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews