27.Environment Project Bureau Kanazawa Plant (tentative name) Construction Project Environmental Impact Assessment Procedure

Final update date March 22, 2019

A list of procedures
Business name Construction of Kanazawa Plant (tentative name)
Project Implementation Area 2-7-1, Sachiura, Kanazawa-ku, Yokohama-shi
Business type New waste treatment facilities
company Yokohama-shi
Preparatory Statement

Submission: May 18, 1993
Public notice and inspection: May 25-June 23, 1993

Public information ward Kanazawa Ward, Isogo Ward
Briefing session June 12, June 13, June 14, June 15, 1993 (four times in total) 159 people in total
Statement of Position Number of copies: 9 mails
Evaluation Report

Send: August 18, 1993
Public notice and inspection: August 25-September 8, 1993

Statement of Position Number of copies: 3 units
Examination Committee

Request: August 31, 1993
Report: December 21, 1993 (four deliberations)

Examination Statement

Creation: January 21, 1994
Notice: April 15, 1994

Report

Submission: April 22, 1994
Notice: May 13, 1994

Start registration form

Notification: September 28, 1995
Construction start date: September 28, 1995


Inquiries to this page

Environmental Impact Assessment Division, Environmental Planning Bureau

Telephone: 045-671-2495

Telephone: 045-671-2495

Fax: 045-663-7831

Email address: [email protected]

Return to the previous page

Page ID: 777-731-720

return to the top