Outline of the Tsuzuki Plant

Last Updated March 9, 2019

Aerial photo of the Tsuzuki Plant

Factory overview (aerial photographs are taken at the time of the factory was opened.)

Factory NameCity of Yokohama, Resources and Waste Recycling Bureau Tsuzuki Plant

Location

〒224-0064
27-1, Hiradai, Tsuzuki-ku, Yokohama-shi

Site areaApprox. 64,218 m2

Total floor area of the buildingApprox. 28,692 m2

Date of commencement of constructionDecember 24, 1979

Date of completionMarch 31, 1984

Date of operationApril 1, 1984

Number of furnaces400t/24h x 3 units

Incineration capacityStandard 800t/24h, equipment 1200t/24h

10

Chimney130m above ground, average blowing speed of 30m/s

11

IncineratorsContinuous combustion type Mitsubishi Martin type

12

Waste pit capacity15,000m3

13

Ash pit capacity1,140m3

14

Crusher

1 hydraulic shear type

15

Generator output13,000kW、6,600V

16

Total construction costs

Approx. 28.7 billion yen
(Land cost 8.4 billion yen, construction cost of 9.4 billion yen, furnace construction cost 10.9 billion yen

Dioxin Survey Results (In charge of Policy Coordination Division)

Access to the Tsuzuki Plant

For inquiries to this page

Resources and Waste Recycling Bureau Proper Treatment Planning Dept. Tsuzuki Plant

Phone: 045-941-7911

Phone: 045-941-7911

Fax: 045-941-7912

Email address: sj-tsuzukikojo@city.yokohama.jp

Return to the previous page

Page ID: 792-830-960

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews