Overview of the Tsurumi Plant

Last Updated July 1, 2024

Location
1-15-1, Suehirocho, Tsurumi-ku, Yokohama-shi

Yokohama 3R Dream Mascot Eo

Site area
61,053.95 square meters (excluding facilities that use residual heat)

Total operating expenses
Approx. ¥51.8 billion

Processing capacity
1,200 tons per day (400 tons per unit x 3 units)

Incinerator type
Continuous combustion incinerator (Mitsubishi Martin type)

Pollution prevention equipment
Exhaust gas treatment equipment: Filter type dust collectors (bag filters), catalyst denitrification equipment, smoke wash towers
Wastewater treatment facilities
Deodorant and soundproofing equipment
Desalination equipment

Power generation capacity
22,000 kilowatts

Building structure scale
Factory building: Steel-framed reinforced concrete structure and steel frame structure 8 floors above ground and 1 floor below ground
Building area 18,271.89 square meters Total floor area 39,512.02 square meters
Administration Building: Reinforced concrete 3F above ground
Building area 944.37 square meters Total floor area 2,236.30 square meters

Chimney structure scale
Outer tube: Reinforced concrete
Inside tube: 3-piece set made of steel sheet
Height: 130 meters

Construction period
Construction started in fiscal 1990 (September 1990)
Full-scale operation in April 1995

You may need a separate PDF reader to open a PDF file.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

Inquiries to this page

Tsurumi Plant, Resources and Waste Recycling Bureau Proper Treatment Planning Department

Telephone: 045-521-2191

Telephone: 045-521-2191

Fax: 045-521-2193

Email address: sj-tsurumikojo@city.yokohama.lg.jp

Return to the previous page

Page ID: 951-691-403

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews