Loop Route 3 (Tozuka District)
Last update date November 1, 2023
Ring Route 3 (Tozuka area) is conducting business from the Naganuma area on the east side to the west. In March 2004, a section exceeding the JR Tokaido Line and the Kashio River from the Kan 3 Naganuma Intersection in Sakae-chonuma-cho, Sakae-cho, was completed. After the opening of 850m to the Hinode Bridge Intersection in July 2004, approximately 1,300m of the main line, including the remaining 450m, was opened in March 2022.
In 2023, a part of the installation road will be opened (PDF: 1,396KB), and we will continue to maintain the connecting stairs and incidental work.
Business Districts | Loop Route 3 (Tozuka District) |
---|---|
Section | Sakae-cho, Totsuka-cho, Totsuka-ku |
Fiscal year | FY 2002 to FY2006 |
Scale | Approx. 1,300m Standard width 22m (4 lanes) |
Improvement effect |
|
Business Progress Rate※ | 97% (expected at the end of FY2022) |
Land acquisition rate※ | 100% |
Current Construction Contracts |
Outline of construction Box culvert, asphalt pavement
Outline of construction roadway pavement, cutting overlay work, sidewalk pavement
Outline of construction Slope shaping work, mortar spraying work, pier foundation work
Outline of construction Factories, Factory Painting Work |
※Business progress rate is shown as the execution rate of total project cost.
※The land acquisition rate indicates the ratio of the acquired area among the areas where the business has been approved.
- Business segments
- Completion of bridge section
- Completed near Hinode Bridge Intersection
In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
To download Adobe Acrobat Reader DC
For inquiries to this page
Road and Highway Bureau Construction Department, Construction Department
Phone: 045-671-3521
Phone: 045-671-3521
Fax: 045-663-8993
Email address: do-kensetsu@city.yokohama.jp
Page ID: 883-137-495