About sewer self-financing construction

Last Updated October 30, 2024


Sewerage self-financing construction is construction that a person other than Yokohama City performs construction about sewerage facilities on public roads at his own expense.
You must submit an application for approval of construction of sewerage facilities to the competent Public Works Office before the construction of sewerage facilities, and obtain approval from The Mayor of Yokohama or Director Public Works Office. (Articles 16 and 27 of the Yokohama City Sewerage Ordinance)

Application for sewerage self-financing construction

Please fill out the application form with required items, attach required documents and submit it to Public Works Office.
Application Form Download: To sewer River Bureau (about sewer self-financing construction) homepage
(It is also distributed in Public Works Office. For more information about required documents, please contact Public Works Office.
The following documents (1 to 6) are usually attached for installation pipe self-financing work. Please contact us for more information.

1. Guide map
Copy of house map, etc.

2. Layout Plan
The exterior of the building and the position of the mounting pipe are known.

3. Floor plan
The extension of the mounting pipe is entered from the inside of the basin to the center of the main pipe. No. 1 decimal point (in meters)
Refer to the installation pipe laying diagram of Yokohama City Sewerage Design Standard Map (tube version).

4. Longitudinal diagram
The extension of the mounting pipe is entered from the inside of the basin to the center of the main pipe. No. 1 decimal point (in meters)
Refer to the installation pipe laying diagram of Yokohama City Sewerage Design Standard Map (tube version).

5. Excavation cross section
It is suitable for the pavement type of the part. Please check with Public Works Office.

6. Copy of Drainage Equipment Plan Confirmation Application
A set of duplicates with confirmation marks.

7. Road excavation site road surface restoration work implementation pledge
seal's pledge

Notification of start of sewerage self-financing construction

If you have received a letter of approval from Public Works Office, please submit it to Public Works Office along with the schedule to registration form.
Application Form Download: To sewer River Bureau (about sewer self-financing construction) homepage

Extension of construction period for sewerage self-financing construction

When we are going to extend construction period for unavoidable reason, we must submit construction period extension registration form such as construction of public sewer facility to the mayor with schedule. (Yokohama City Sewerage Ordinance, Article 17, Paragraph 5)
The "unavoidable reason" herein may, in principle, be as follows.

  • In cases where negotiations with local residents are difficult and construction is delayed.
  • When construction is delayed due to relocation, cut, protection, etc. of underground buried objects.
  • When an unexpected accident occurs at the design stage of soft ground, spring water, etc., resulting in a change in the construction method, etc., and construction is delayed due to this.
  • When construction is delayed due to natural disasters, land changes, etc.

Application Form Download: To sewer River Bureau (about sewer self-financing construction) homepage

Change of sewerage self-financing construction
When we change construction periods for unavoidable reason or are going to change facility contents at the time of approval application, we must submit change registration form such as public sewer facility construction to the mayor. (In the case of minor, it will be corrected in the book.) Please contact us for more information.
Application Form Download: To sewer River Bureau (about sewer self-financing construction) homepage

Notification of completion of sewerage self-financing construction, inspection

The applicant must submit the completed registration form to the competent Public Works Office as soon as the completion of the construction of public sewerage facilities.
Application Form Download: To sewer River Bureau (about sewer self-financing construction) homepage
The following documents (1 to 5) are usually attached for installation pipe self-financing work. Please contact us for more information.

  1. Guide map
    Copy of house map, etc.
  2. Ledger offset diagram
    Public sewer ledger figure information "Daichan map" (outside site)
  3. Floor plan
    The extension of the mounting pipe is entered from the inside of the basin to the center of the main pipe. No. 1 decimal point (in meters)
  4. Longitudinal diagram
    The extension of the mounting pipe is entered from the inside of the basin to the center of the main pipe. No. 1 decimal point (in meters)
  5. Photographs of construction

If there is no defect in the contents of the self-financing construction (if it can be taken over as a facility in Yokohama City), after the completion inspection, a certificate of completion inspection (with the mayor's seal or Public Works Office's seal stamped) will be issued to the applicant. Will be

Inquiries to this page

Totsuka Ward Tozuka Public Works Office

Telephone: 045-881-1621

Telephone: 045-881-1621

Fax: 045-862-3501

Email address: to-doboku@city.yokohama.lg.jp

Return to the previous page

Page ID: 485-373-246