About public sewer temporary use application

Last Updated January 26, 2024

What is Public Sewerage Temporary Use?

When we perform the following drainage including drainage for construction, and use public sewer temporarily, please submit public sewer temporary use permission application and receive permission of Public Works Office. (Yokohama City Sewerage Ordinance, Article 17, Paragraph 3)

  1. Spring water, rainwater, drainage for construction work, etc.
    (For spring water and rainwater, when a pot is provided with a pot)
  2. Wastewater from temporary toilets and hand-washing areas installed in temporary offices.
  3. Accumulated water from caretaker holes such as telephones, electricity, gas, etc.
  4. Wastewater associated with other construction work.

In addition, when applying, drainage methods etc. must conform to the standards. In addition, industrial waste cannot be drained.

Drainage method

Drainage method (connection method to sewer) is as follows.

  1. When discharging in a combined area, let it flow directly into the connection basin.
  2. When discharging in a diverted area, let it flow directly into the sewage connection basin.
  3. Drainage associated with construction on the road (including underground) can be connected to a human hole by installing a mounting pipe. However, please consult with Public Works Office regarding the connection location, construction method and restoration method.
  4. If there is no connection basin on the premises or near the site, apply for self-financing construction to Public Works Office, install the connection basin and mounting pipe, and submit a temporary application form.

Structure of drainage facilities

When discharging wastewater for construction, install drainage facilities as follows. (excluding temporary office wastewater and temporary toilet drainage)

  1. Public sewerage facilities, road facilities, etc., and traffic.
  2. In the drainage facility, install a sedimentation tank that meets the following standards.
    • A rectifying plate, cough, etc., so that it does not cause disturbance by running water.
    • The sedimentation tank has a structure of two or more tanks
    • In principle, the average flow velocity is 0.3 m/s or less.
    • As a rule, stay time is 30 seconds or more.
    • Mudra is 60cm or more
  3. When alkaline or acidic sewage is discharged, a neutralization tank is set up, adjusted, and then discharged. The neutralization tank must have a function to automatically stop the power pump when the water quality exceeds the standard value in principle.
  4. The sedimentation tank shall have a structure in which the flow rate can be measured in principle.

Water quality standards, etc.

Water quality such as drainage for construction is based on the regulations about conservation of Yokohama-shi living environment and standard such as Yokohama-shi sewer regulations (outside site) other than thing raised in the next table.
Water quality should be inspected from time to time, and appropriate management should be performed to comply with laws and regulations.

Water quality standard method
ItemsProcessing area
(From flowing into the sewage treatment plant)
Untreated area
(It does not flow into the sewage treatment plant)
Hydrogen ion concentrationPH5 and less than 9HP5.8 or higher 8.6 or less
Suspended Substances
Bentonite
Other earth and sand
Less than 600 ppm70 ppm or less

When we violate laws and ordinances or the above-mentioned standards and permission conditions, or when the city deems it necessary, we may rebuild and relocate or remove drainage facilities. The expenses required in this case shall be borne by applicant.
If the pipeline is blocked or damaged due to effluent such as construction drainage, restoration work costs for the facility will be collected. However, if there is an application for self-financing construction from the cause, the cause person to carry out restoration work.

Wastewater volume certification and sewerage usage fee

Certification of drainage and adjustment of sewerage usage fees are handled by the Environmental Planning Bureau Accounting Section, Sewerage Usage Fees Section. Please pay sewerage system usage fee by delivery letter of advice that Motoichi issues.
Environmental Planning Bureau Accounting Section, Sewerage Fees Phone: 045-671-2826

Permit application

For permission application for temporary use, fill in required items in the application form (download: PDF format (PDF: 65KB), Word format (word: 40KB)) at least 7 days before release, attach required documents, and 3 copies to Public Works Office Please submit.
In addition, please refer to calculation method (PDF: 21KB) of estimated drainage amount of public sewer temporary use for calculation method of estimated total drainage amount.

Contact information

Reference list
Contact informationPhone numberDetails of inquiry
Environmental Planning Bureau Accounting and Management Division Sewage Charges045-671-2826Report on drainage volume and inquiries about sewerage usage fees
Environmental Planning Bureau, Sewer Management Division045-671-2832Viewing the sewer ledger map attached to the application
Environmental Planning Bureau Water and Soil Environment Division045-671-2489Water quality standards for public water bodies
Resources and Waste Recycling Bureau Business Waste Reduction Promotion Section045-671-3818Industrial waste

In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

For inquiries to this page

Totsuka Ward Tozuka Public Works Office

Phone: 045-881-1621

Phone: 045-881-1621

Fax: 045-862-3501

Email address: to-doboku@city.yokohama.jp

Return to the previous page

Page ID: 506-990-158

Menu of ward

  • LINE
  • Twitter
  • Instagram
  • YouTube