Menu

Close

Here's the text.

Business Overview (Phase 1)

Last Updated November 14, 2024

About roadside districts such as Mitsukyo Shimokusayanagi Line northern Futatsu Bridge

In the roadside districts such as the northern part of Futatsu Bridge Mitsukyo Shimokusayanagi Line, a city planning decision (1958) of the land readjustment project was made, but the land readjustment project has not been started except for some parts.
The city planning roads Mitsukyo Shimokusayanagi Line and Seya Chinai Line, which are positioned as arterial roads in the northern area of the Sotetsu Line, are being developed around this area. For this reason, we aim to form a local road network and form a healthy and good urban area by promoting roadside town development along with the maintenance of city planning roads.

About land readjustment project under enforcement
Business name Yokohama International Port Construction Project Northern Mitsukyo Shimokusayanagi Line, etc. Roadside District Phase 1 Land Readjustment Project
Enforcer Yokohama-shi
Enforcement area Part of Futatsubashi-cho, Seya-ku and Tono
Enforced area About 4.1ha
Effective period FY2013-2013 (including 5 years of settlement)
Total operating expenses Approx. ¥10.3 billion
Public facilities plan
  • Urban planning road Mitsukyo Shimokusayanagi Line (width: 18m)
  • Urban planning road Seya ground line (width 15m)
  • Block streets, etc. (width: 4.5-8.5m)
  • Block park (approximately 850m2)
  • Reservoir (approximately 3,600 m2)
Reduction rate Approx. 9.9% (rate after the reduction of walks due to the acquisition of depreciation)
Business Plan Business plan diagram (PDF: 961KB)
Business brochure (PDF: 3,070KB)

Progress

March, 1958 Urban planning decision of land readjustment project in the northern part of Futatsu Bridge
April, 2015 Inspection of the first district business plan of the roadside district such as the Futatsu Bridge Northern Mitsukyo Shimokusayanagi Line
August, 2015 Kitabu Futatsu Bridge Mitsukyo Shimokusayanagi Line, etc. Roadside District Phase 1 Business Plan Decision
February, 2019 1st Temporary replacement lot designation
August, 2019 Business plan change (2nd) (expansion of area, new construction of division roads, etc.)
January, 2020 2nd Temporary Replacement Designated
July, 2020 3rd Temporary Replacement Designated
June, 2021 4th Temporary Replacement Designated
January, 2022 Change of Business Plan (3rd) (Change of Fund Plan)
April, 2022

5th Temporary replacement lot designation

January, 2023 Business plan change (4th) (extension of business enforcement period and change of funding plan)
6th Temporary replacement lot designation
October, 2023 Business plan change (fifth) (change of fund plan and change of division road, etc.)
October, 2024 Business plan change (6th) (change of funding plan and change of division road, etc.)
Business schedule
(planned)
2026 Landfill disposal
2031 Completion of business (including liquidation period of 5 years)

For the latest construction information, please see the page of Futatsu Bridge Northern Land Readjustment Office.

You may need a separate PDF reader to open a PDF file.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

Inquiries to this page

Land readjustment office in the northern part of Futatsu Bridge, Urban Development Department, Urban Development Bureau

Telephone: 045-363-3110

Telephone: 045-363-3110

Fax: 045-363-3116

Email address: tb-futatsubashi@city.yokohama.lg.jp

Return to the previous page

Page ID: 528-399-498

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews