Business Overview (Phase 1 District)

Last Updated December 11, 2023

About roadside areas such as Mitsukyo Shimosoyagi Line northern Futatsu Bridge

In roadside areas such as the northern Mitsukyo Shimosoyagi Line in the northern part of Futatsu Bridge, a city planning decision for the land readjustment project (1958) was made, but the land readjustment project has not been started except for some.
The city planning roads Mitsukyo Shimosoyagi Line and the Seya Chichi Line, which are positioned as arterial roads in the northern area of the Sotetsu Line, are being developed around this area. For this reason, we aim to form a local road network and aim to form a healthy and good urban area by promoting roadside town development in line with the maintenance of city planning roads.

About land readjustment project under enforcement
Business Name Yokohama International Port City Construction Project Futatsu Bridge Northern Mitsukyo Shimosoyagi Line 1st Phase Land Readjustment Project
Enforcer Yokohama-shi
Enforcement area Futatsubashi-cho, Seya-ku and Tono
Operating area Approx.4.1ha
Effective period FY2015 through FY13 (including 5 years of clearing period)
Total operating expenses Approx. ¥9 billion
Public facilities planning
  • City planning road Mitsukyo Shimosoyagi Line (width 18m)
  • City planning road Seya ground line (width 15m)
  • Blocked streets, etc. (width 4.5 to 8.5m)
  • Block park (approx. 850m2)
  • Reservoir (approximately 3,600 m2)
Reduction rate Approx. 9.9% (the rate after reduction of walking due to depreciation acquisition)
Business Plan Business Plan (PDF: 961KB)
Business Brochure (PDF: 3,070KB)

Progress

March, 1958 Urban planning decision for land readjustment project in the northern part of Futatsu Bridge
April, 2015 Inspection of the first phase of the roadside district business plan such as the Mitsukyo Shimosoyagi Line in the northern part of Futatsu Bridge
August, 2015 Business plan for the first phase of the roadside area such as Mitsukyo Shimosoyagi Line in the northern part of Futatsubashi Bridge
February, 2019 1st temporary replacement lot designation
August, 2019 Business plan change (2nd session) (area expansion, new construction of division roads, etc.)
January, 2020 2nd temporary replacement lot designation
July, 2020 3rd temporary replacement lot designation
June, 2021 4th temporary replacement lot designation
January, 2022 Business plan change (3rd) (Change in funding plan)
April, 2022

5th Temporary Replacement Designated

January, 2023 Business plan change (4th) (extension of business implementation period and change of financial plan)
6th Temporary Replacement Designated
October, 2023 Business plan change (fifth) (change of fund plan and change of division road)
Business schedule
(planned)
2026 Landfill disposal
2031 Completion of business (including clearing period of 5 years)

For the latest construction information, please see the page of Futatsu Bridge Northern Land Readjustment Office.

In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

For inquiries to this page

Land Readjustment Office Northern Futatsu Bridge, Urban Development Department, Urban Development Bureau

Phone: 045-363-3110

Phone: 045-363-3110

Fax: 045-363-3116

Email address: tb-futatsubashi@city.yokohama.jp

Return to the previous page