Here's the text.

About attachment of bicycle parking lot

Last Updated September 5, 2024

Notice

To all those who submit a notification of completion of construction

 There are cases where corrections are required when submitting the construction completion notification. Therefore, please check the following items carefully before submitting so that the procedure can be proceeded smoothly.

・Details of the construction completion notification  ※Refer to “Examples (PDF: 218KB)”.
・attached documents (1) Copy of Conformity Confirmation Notice
      ⑵A copy of the building's inspection certificate
      ⑶Completed photo (dimensions, number, passage width, etc.)  ※See "How to Take Completed Photos (PDF: 140KB)"

 In addition, if the submitter / manager, location, structure / type, aisle shape / width, etc. are changed, submit the “Bicycle Parking Lot Placement (Change) registration form” before submitting the construction completion notification, and confirm the change conformity Please note that it is necessary to receive a notice. The construction completion notification will be the notification after the issuance of the above change conformity confirmation letter.

 Congestion is expected at the end of the fiscal year, so please check the above items and adjust the schedule before coming to the agency.

Revision of the Form and Guideline

・Various forms were revised on April 1, 2021.
 In the future, please use the new style posted at the bottom of this page (report style, etc.) for those that will report.
・In September 2021, the contents of the "Calculation Statement for the Size of Bicycle Parking Lot (Excel Data)" were partially incorrect, so it was revised. Please use the latest version posted at the bottom of this page when calculating the number of facilities attached to attracting customers.
・In October 2022, the "Guide to Installation of Bicycle Parking Lots" was revised.
・In April 2024, we revised the "Guide to Attachment of Bicycle Parking Lots".
・In September 2024, we revised the "Guide to Attachment of Bicycle Parking Lots". The latest version is uploaded below, so please take a look.

About window system to prevent the spread of COVID-19 infection

At present, Yokohama City Hall is taking steps such as staggered work to prevent the spread of COVID-19. The waiting time may be longer, such as procedures at the counter or inquiries over the phone, but we ask for your understanding.
In addition, please contact us by the day before, as we may not be able to respond unless you make a reservation in advance at the next agency.
※When you come to the agency, please make sure that you have no symptoms such as coughing or fever, and cooperate with wearing a mask.

In addition, for the time being, about prior consultation of the regulations about attachment of Yokohama-shi bicycle parking lot and procedure of report, we cope with reception by mail in addition to correspondence at conventional window.
Specifically, please confirm "about window system for prevention of new coronavirus infectious disease spread (the regulations about attachment of Yokohama-shi bicycle parking lot)" (PDF: 226KB).

About abolition of seal such as registration form

From March 1, 2021, seal will no longer be required for registration form, etc. to be submitted in order to reduce the burden on citizens and businesses and to improve convenience at the counter or by mail. [Reference] Notice Concerning Revision of seal Signatures to Application Forms
Filling in registration form, etc. is only registered.
※Signatures include prints, rubber stamps and stamps, as well as self-writing.

1 Overview

In Motoichi, we performed maintenance of municipal bicycle parking lot or movement work of abandoned bicycle based on "the regulations about prevention of abandonment such as Yokohama-shi bicycles" established in 1985 as illegally parked bicycle measures.
As a result, the situation of abandoned bicycles around the station has been greatly improved, but in some areas, abandoned bicycles for those who use stores etc. for shopping etc. were still an issue. Bicycle parking lots used by visitors to stores, etc. (hereinafter referred to as "bicycle parking lots") should be developed by the customer facilities. In addition, in apartment houses, there were situations where bicycles were left around apartments.
Therefore, in order to ensure a safe and comfortable walking environment, facilitate traffic, and maintain good urban landscapes, we have established an ordinance that requires the installation of bicycle parking lots when building or expanding customer-acquisition facilities and apartment houses that generate demand for bicycle parking.

What is the obligation to install a bicycle parking lot?

In designated areas stipulated in the "Ordinance on Attachment of Yokohama City Bicycle Parking Lots (hereinafter referred to as the" Ordinance ")", attracting facilities (playgrounds, retail stores, restaurants, sports facilities, banks, hospitals, etc.) and apartment houses, etc., the installer of the facility must calculate the walking distance from the facility premises in accordance with the ordinance of the facility. The number of bicycle parking lots must be within 50 meters.)

Subject of mandatory attachment
Areas subject to mandatory attachment
(designated area)
Urbanization area under the City Planning Act
Persons subject to mandatory attachment
(Notification of installation)

Installer (owner) of the target facility
The installer refers to the owner of the building, and does not include those who have lease or use lease. (In the case of a corporation, a person who has the authority of representation)
When proceeding with the procedure under the outsourcing of a consultant, etc., be sure to obtain the consent of the building installer before starting the procedure.

Acts subject to mandatory attachmentAfter April 1, 2019 (applicable date)
  • New construction
  • Expansion

Installation of a bicycle parking lot is required in the building that applies for building confirmation (or notification of the plan).
Even if you apply for a new construction or extension building or submit a notification of a plan before the application date, if you do not start construction before April 1, 2021, installation of a bicycle parking lot is required .

Facilities that started construction before the application date are also required to set up a bicycle parking lot for users or residents.

2 Prior consultation

I would like prior consultation to confirm whether the newly built or expanded facility is subject to the obligation to attach a bicycle parking lot, or to conform to the number of mandatory obligations and technical standards.
If any of the following cases apply, please check the contents of the guide before consulting.
●Facility area of customer-acquisition facilities ※When building or expanding a new building of 300 m2 or more
 ※ Please refer to the guide “2-1 Facilities subject to mandatory installation of attracting facilities” for the purpose and scale of the target facilities.
 Example: [Single-use facilities] Retail stores, restaurants, clinics, etc. with a facility area of 400 m2 or more, amusement arcades, learning facilities, etc. with a facility area of 300 m2 or more, sports facilities with a facility area of 500 m2 or more
●When newly constructing or expanding a condominium with a total number of dwelling units of 10 or more

If you plan to submit registration form, please be sure to consult us in advance.

Please submit a set of registration form attached to the following prior consultation.
Prior consultation (PDF: 170KB) (PDF version)
Prior consultation (word: 32KB) (WORD version)

Guides on the installation of bicycle parking lots, etc.

Please refer to the "Guidelines" for the flow of procedures.

※Reference
When establishing a large-scale retail store (store area of more than 1,000 square meters), a separate procedure based on the “Large-scale Retail Store Location Law” and the “Yokohama City Large-Scale Retail Store Location Law Operation Guidelines” is required. Installation according to the “Large-scale Retail Store Location Law Operation Standards” is required.
Please refer to the website of the Economic Affairs Bureau Commercial Promotion Division for detailed procedures related to the Large-Scale Retail Store Location Act.

3. Notifications, etc.

About notification window

Road and Highway Bureau Road Policy Promotion Section
(Location) 22nd floor of 10 City Hall, 6-50 Honcho, Naka-ku, Yokohama 231-0005, Japan
(Phone number) 045-671-3644

When you come to the agency, you may not be able to respond unless you make a reservation in advance, so please contact us the day before.

Notification style

Special provisions for the number of mandatory assignments

In the area specified in Article 3-2 of the Ordinance Enforcement Regulations, the number obtained by multiplying the number of mandatory units calculated based on the Ordinance Schedule 1 and Schedule 2 by one-half will be the number of mandatory units in the area . In addition, this special case applies only to attracting customers.
Area to which exception applies (PDF: 315KB)

FAQs

You may need a separate PDF reader to open a PDF file.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

Inquiries to this page

Road Policy Promotion Section, Road and Highway Bureau Road Policy Promotion Department

Telephone: 045-671-3644

Telephone: 045-671-3644

Fax: 045-550-4892