About correspondence of Motoichi with enforcement of embankment regulation law

Last update date April 12, 2024

 On May 27, 2022, in order to protect the lives and bodies of the people from disasters caused by embankments, etc., the Residential Land Development Regulation Law (hereinafter referred to as the "Old Residential Building Act") was drastically revised to protect the lives and bodies of the people from disasters caused by embankments, etc. (hereinafter referred to as the "Element Regulations") was promulgated.
 The response of Motoichi in response to this is as follows.

  1. About correspondence schedule and transitional measures period of Motoichi
  2. Overview of the Embankment Regulation Law
  3. About candidate area of new regulation area (result of basic investigation) of new regulation area
  4. About common knowledge of construction plan of embankment regulation law (revised outline plan of the regulations about adjustment of Yokohama-shi development business)

 In addition, enforcement of embankment regulation law is May 26, 2023, but until designation of new regulation area, regulation of old house building method continues until designation of new regulation area.

 The enforcement of the Embankment Regulation Law is May 26, 2023, but from the date of enforcement to the designation of a new restricted area based on the Embankment Regulation Law (hereinafter referred to as the transitional measure period), the old Housing Construction Law will continue. Regulations apply.
 The new restricted area is scheduled to be designated on April 1, 2025. From the same day, the provisions of the Embankment Regulation Law will be applied to the entire area of Yokohama City.

※Prior to the announcement of the restricted area under the Embankment Regulation Law, the provisions of the Old Housing Construction Law, including the change permission, will be applied until construction is completed.

※About the details such as permission standards in embankment regulation law, we will tell on Motoichi website or window in future.

(1) Outline of the revision from the Old House Building Law

Regulation without skimming

  • Prefectural governors, etc., designates areas that can cause damage to houses, etc. by embankments, etc., regardless of the use of land such as residential land, agricultural land, forest, etc.
  • Permits, etc. performed in restricted areas, including the creation of farmland and forests and temporary accumulation of debris, are subject to permission.

Ensuring safety of embankments, etc.

  • Permission criteria necessary for disaster prevention are set according to the topography, geology, etc. of the area where embankment is performed.
  • In order to confirm whether safety measures are being taken in accordance with the permission criteria.
    [1]Periodic reports of construction status, [2] Interim inspections during construction and [3] completion inspections when construction is completed.

Clarification of where responsibility lies

  • Clarify that landowners, etc. have a responsibility to maintain a safe state for land where embankments were carried out.
  • When necessary for disaster prevention, not only landowners, but also the causal actor to order corrective measures, etc.

Effective Penalties

  • Reinforce penalties for unauthorized acts and violations of orders, etc. to a higher level than the upper limit of penalties under the regulations so that penalties can function sufficiently as deterrence

※Maximum maximum imprisonment of 3 years or less, fine of 10 million yen or less, corporate heavy department 300 million yen or less

(2) Brochure by the Ministry of Land, Infrastructure, Transport and Tourism, Ministry of Agriculture, Forestry and Fisheries and the Forestry Agency)

General use

For business operators

 In Yokohama City, there are roads where earth and sand may be brought in by vehicles, etc., and from the viewpoint of preventing disasters due to landslides due to embankments or outflow of earth and sand, `` Construction restricted area for residential land development etc. The candidate area of "is the whole area of Yokohama City".

※Because "restricted areas such as specific embankments" and "created residential land disaster prevention areas" are specified except for "construction restricted areas such as residential land development", they will not be designated in Yokohama City.

※If it is designated as a "construction restricted area for residential land development", permission based on the embankment regulation law is required when performing construction work of a certain size or more or more or sediment deposition work.

Table: Current regulated areas and new regulated areas (candidate areas)
 Current regulated areaNew regulated areas (candidate areas)
NameResidential land development construction restricted areaConstruction restricted areas such as residential land development
Basising methodRegulation Law for Residential Land DevelopmentEmbankment Regulation Law
Designated dateJuly 27, 1962As of April 1, 2025 (planned)

In the area
Regulations

Permission from the mayor is required when building residential land

In addition to the left.
In the following cases, permission from the mayor is required.
・ Creation of farmland, pastures, or forest
・ Temporary debris accumulation

Specified
Target area

An urban area in a hilly area or a land that can become an urban area.
Areas where disasters are likely to occur due to development

If embankment is carried out in the city area or its surroundings, houses, etc.
Areas that may cause harm to

Designated pointAbout 62% of Yokohama CityThe entire area of Yokohama (100%)

      (Portable Document Format) (PDF: 652KB)

※This figure is a candidate area for the "Construction Restricted Area for Residential Land Development", and since the area has not been designated, it has not been effective as a regulated area.


 The Embankment Regulation Law requires that a business operator to inform the local residents of the construction plan before applying for permission for construction work or debris accumulation work.
 In Yokohama City, procedures such as the publicity method will be added to the "Ordinance on Coordination of Yokohama City Development Projects" in order to ensure that the local residents based on the Embankment Regulation Law can be carried out smoothly. I will do it.
 This revision stipulates the procedures for dissemination to the local residents when embankments are performed, and affects citizens. Therefore, we carry out citizen opinion offer (public comment) to raise opinions of citizen's all of you about main point plan of revision of the regulations concerned.
 In addition, in conjunction with this ordinance revision, we will review the ordinance based on the actual operation status of the ordinance.
 About main point plan of this regulations revision, please see this (main point plan of revision of the regulations about adjustment of Yokohama-shi development business).

※We carry out public comment (citizen opinion offer) about this main point plan from Wednesday, April 17, Reiwa 6 to Wednesday, May 22, 6.

In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

For inquiries to this page

Housing and Architecture Bureau Residential Land Examination Division Residential Land Planning Division

Phone: 045-671-2945

Phone: 045-671-2945

Fax: 045-681-2435

Email address: kc-takuchishinsa@city.yokohama.jp

Return to the previous page

Page ID: 667-228-370

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews