Procedure of Development Project Coordination Ordinance

Last Updated March 7, 2022

July 9, 2013

 Procedure Flow

The general procedure for obtaining a development permit is as follows. Documents, drawings, detailed procedures, etc. required at each stage differ depending on each development project.
For details, please confirm in "guide of the regulations about adjustment of Yokohama-shi development business", and please talk with charge window.

Procedures for the Development Project Coordination Ordinance (1) and (2)
(1) Installation of signs, (2) Submission of sign installation notification
Development company installs sign in easy-to-see place of development business area and submits sign setting notice to city to publicize summary of development business to inhabitants.

Arrow

Procedure of the Development Project Coordination Ordinance (3)
(3) Explanation to residents and explanation to public facilities managers
The developer will explain to the residents the contents of the development concept. At the same time, we will explain matters pertaining to public facilities to public facilities managers.
Scope of explanation and method of explanation
 Specific large-scale development projectsOther Development Business
Scope of explanationLocal residents (within 50m from the development project area)
Local town development plan management organization
Proximity residents (within 15m from the development project area)
Local town development plan management organization
Method of explanationHolding briefings (advance distribution of materials)Hold individual visit explanations or briefing sessions (advance distribution of materials)

Arrow

Procedures for the Development Project Coordination Ordinance (4) and (5)
(4) Submission of Statement of Opinion (word: 34KB), (5) Sending Statement of Opinion
Residents can submit a written opinion on the development concept to the developer within 5 days after the explanation of the residents.
The developer sends the written opinion individually to the residents who have submitted the written opinion.

Arrow

Procedures for the Development Project Coordination Ordinance (6) and (7)
(6) Submission of development business plan (word: 25KB), (7) inspection of development business plan

The developer submits the development project plan to the city.
The city will inspect the development project plan for 14 days.

Development Business Plan

Overview

Development Business Structure Thinking (land use plan, outline of planned building, etc.), explanation to residents, etc.
Opinion, statement of opinion of inhabitants and opinion of company for it.

Window for inspection and browsing
Yokohama Building Information Center (2nd floor of City Hall)Inspection and Inspection
The ward office that has jurisdiction over the wardBrowse

Arrow

Procedures for Development Project Coordination Ordinance (8) and (9)
(8) Submission of re-statement statement (word: 17KB), (9) Sending re-statement statement
Residents can submit a re-statement to the developer via the city for the opinion of the developer written in the development project plan during the inspection period for the development project except for the road location designation. .
The developer sends a re-opinion individually to the residents who have submitted the re-opinion.

Arrow

Procedure of the Development Project Coordination Ordinance (10)
(10) Discussion between the developer and the mayor
(In the case of a development project other than a specific large-scale development project or a development project for which a re-opinion has been submitted.)
  1. In the case of a development project other than a specified large-scale development project where a re-opinion has been submitted.

    The development company discusses with the mayor about matters determined by the mayor each time.

  2. In the case of a specific large-scale development project

    Development company discusses matter to establish in the following with the mayor so that it becomes plan in consideration of local situation.
    ※ Contents of discussion (items to make development plans that take into account the actual conditions of the region)

    • Thing about maintenance of public facilities in development business area and public interest facilities
    • Harmony with the surrounding environment
    • Thing about consistency with local town development plan (thing which established policy of town development such as city planning master plan district plan)
    • Thing about measures for maintenance of good living environment by designation of city planning, conclusion of building agreement
    • Measures related to anti-crime program in the development project area
    • Thing about securing of traffic safety in development business area and neighboring roads
    • Thing about offer to city of land for maintenance of public interest facilities which the mayor particularly recognized
      (Development project area: Development projects with an area of 3ha or more or apartments with 500 or more dwelling units)
    • Other matters deemed necessary by the mayor

Arrow

Procedure of the Development Project Coordination Ordinance (11)
(11) Submission of a development project plan consent application and examination of facility maintenance standards (consent criteria)
The developer submits an application for consent to the development project plan.
City examines "maintenance standard of facility (consent standard)" in development business.


Consent Criteria

Arrow

Procedure of the Development Project Coordination Ordinance (12)
(12) Issuance of a notice of consent / disagreement and subsequent procedures

After examination about procedure and maintenance standard of facility, city answers development company about result.
Penalties will be applied to developers who have started construction despite the disagreement of the city.
※ It is mandatory to submit development permission and building confirmation applications after consent.

Please contact the Housing and Architecture Bureau Information Consultation Section for specific details in specific locations.

Inquiries to this page

Residential Land Examination Division, Housing and Architecture Bureau Residential Land Examination Department

Telephone: 045-671-4515

Telephone: 045-671-4515

Fax: 045-681-2435

Email address: kc-takuchishinsa@city.yokohama.lg.jp

Return to the previous page

Page ID: 380-059-117

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews