Procedure for Development Business Coordination Ordinance

Last update date March 7, 2022

July 9, 2013

 Procedure flow

The general procedure for obtaining a development permit is as follows. Documents, drawings, detailed procedures, etc. required at each stage vary depending on the development project.
For details, please confirm in "guide of the regulations about adjustment of Yokohama-shi development business" and please talk with person in charge.

Procedures (1) and (2) of the Development Business Coordination Ordinance
(1) Installation of signs, (2) Submission of sign installation
In order to disseminate the outline of the development project to the residents, the developer will install signs in an easy-to-see place in the development project area and submit a sign installation notice to the city.

Arrow

Procedure of Development Business Coordination Ordinance (3)
(3) Explanation to residents, explanations to public facilities managers
The developer will explain the contents of the development plan to the residents. In addition, about matters pertaining to public facilities, we explain to public facilities manager.
Scope of explanation and method of explanation
 Specified large-scale development projectsOther development projects
Scope of explanationLocal residents (within 50 m from the development project area)
Local town development plan management group
Proximity residents (within 15m from the development project area)
Local town development plan management group
Explanation methodHolding briefing sessions (pre-distributed materials)Holding individual visits or briefing sessions (pre-distributed materials)

Arrow

Procedure for Development Business Coordination Ordinance (4), (5)
(4) Submission of sent statement of opinion (word: 34KB), (5) Sending of written opinion
Residents can submit a written opinion on the development concept to the developer within five days after the explanation of the residents.
The developer sends a written opinion individually to the residents who have submitted the written opinion.

Arrow

Procedures for Development Business Coordination Ordinance (6), (7)
(6) Submission of a development project plan (word: 25KB), (7) Inspection of the development project plan

Developers submit a development project plan to the city.
The city will inspect the development project plan for 14 days.

Development Business Plan

Overview

Development business Structure (Outline of land use plan, outline of planned buildings, etc.), status of explanation to residents,
List of opinions and opinions of residents and the opinion of the company for it.

Contact point for inspection and inspection
Yokohama Architecture Information Center (city hall 2nd floor)Inspection and inspection
The ward office in charge of the wardViewing

Arrow

Procedures for the Development Business Coordination Ordinance (8) and (9)
(8) Submission of re-review (word: 17KB), (9) Sending a re-view
Residents can submit a re-opinion to the developer via the city for the opinion of the developer written in the development project plan during the inspection period for the development project excluding the road location designation.
The developer sends a re-view individually to the residents who have submitted the re-opinion.

Arrow

Procedure for Development Business Coordination Ordinance (10)
(10) Discussion between the developer and the mayor
(In the case of a development project other than a specified large-scale development project or a development project other than a specific large-scale development project, in which a re-opinion has been submitted)
  1. In the case of a development project other than a specified large-scale development project for which a re-opinion has been submitted

    The developer discusses with the mayor about the matters that the mayor determines each time.

  2. In the case of specific large-scale development projects

    The developer will discuss with the mayor about the matters specified below so that the plan will be considered in consideration of the local situation.
    ※ Details of discussions (items to make development plans that take into account local circumstances)

    • Thing about maintenance of public facilities and public interest facilities in development project area
    • Harmony with the surrounding environment
    • Thing about consistency with local town development plan (thing which established policy of town development such as city planning master plan district plan)
    • Thing about measures for maintenance of good living environment by designation of city planning, conclusion of building agreement.
    • Measures to anti-crime program in the development business area
    • Thing about securing of traffic safety in development business area and the surrounding roads
    • Thing about offer to city of land for maintenance of public interest facility which the mayor recognized in particular
      (Development project covers development projects with an area of 3 ha or more or apartment houses with 500 or more dwelling units)
    • Other matters that the mayor deems necessary

Arrow

Procedure for Development Business Coordination Ordinance (11)
(11) Submission of a development project plan consent application and examination of facility maintenance standards (consent standards)
The developer submits an application for consent to the development project plan.
City examines "maintenance standard (consent standard) of facility" in development business


Consent criteria

Arrow

Procedure for Development Business Coordination Ordinance (12)
(12) Issuance of a letter of consent / disagreement and subsequent procedures

After examining procedures and maintenance standards for facilities, the city will respond to the developer about the results.
Penalties will be applied to developers who have started construction despite the disagreement with the city.
※ It is obligatory to submit a development permit and building confirmation application after consent.

For specific contents at a specific location, please contact the person in charge of the license or the Housing and Architecture Bureau Information Consultation Section.

For inquiries to this page

Housing and Architecture Bureau Residential Land Examination Division

Phone: 045-671-4515

Phone: 045-671-4515

Fax: 045-681-2435

Email address: kc-takuchishinsa@city.yokohama.jp

Return to the previous page

Page ID: 380-059-117

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews