Approval of energy-saving performance improvement plan (Article 35 of the Act)
Last update date April 1, 2024
Page information
- About procedure of certification application
- About application documents
- Certification Fees
- About change procedure
- Procedure for completion
- About other forms
Standard procedures are applied to Yokohama City after receiving a technical examination on the certification criteria in advance by the "examination body".
≪Reviewing body≫
・Registered energy-saving judging body: Registered building energy consumption performance assessment organization prescribed in the Building Energy Conservation Law
・Registered Housing Performance Evaluation Facility: Registered house performance evaluation organization prescribed in the Act on Promotion of Housing Quality Assurance
Where a certificate of conformity with the technical review has been obtained by the examination body | 30th |
---|---|
The Company has not received a certificate of conformity with the technical review by the examination body | 120 days |
- Other than the above. Housing and Architecture Bureau Standard Process Period PagePlease check it out.
※Precautions for applying for certification of energy-saving performance improvement plans
- Before starting construction, it is necessary to apply for certification to Yokohama City.
- The examination body should undergo a review of all certification criteria in Article 35, Paragraph 1 of the Act.
- If you do not receive a technical review in advance, or if you wish to apply for confirmation along with the certification, please contact us in advance.
Building Planning Division, City of Yokohama, Housing and Architecture Bureau Building Guidance Department | |
---|---|
Address | 10 City Hall 25th Floor, 6-50 Honcho, Naka-ku, Yokohama |
Telephone | 045-671-4526 |
About certification criteria
Please refer to laws and regulations for the certification criteria.
Please bind all copies and one copy to A4 size file and submit.
- Certification Application Form (Form 33) (outside site)
- Power of Attorney (when the applicant delegates the procedure to another person)
- Books specified in the table of Article 23 of the Enforcement Regulations of the Law (PDF: 199KB)
- Other books that the mayor determines as necessary
- A set of attached documents when the technical examination conformity certificate and conformity certificate issued by the examination body are issued
seal is no longer required for applications.
※The seal of Power of Attorney is not required. (Please determine the necessity of seal between delegates and delegates.)
After receiving the counter, please pay the prescribed fee amount using the fee payment machine.
Regarding the changes, the procedure differs depending on whether technical review is required again.
Please confirm the contents in advance with the examination body that has undergone a technical examination when applying for certification.
Change Certification Application Form (Rule Style 35) (External Site) |
---|
In principle, the change application fee is half the price of the certification application fee. (rounded down to less than 100 yen) ※However, if the evaluation method is different from the initial application, it may not be half the price. |
Notification of change of authorized builder (Summary No. 3 style) (outside site) |
---|
If you wish to re-issue the certification letter, please apply for the “Application for Re-grant of the Certification Notice” and “300 yen fee” at the same time. |
When construction work is completed, please submit two copies of the main and secondary copies of the "Report that construction based on the Building Energy Consumption Performance Improvement Plan was completed" with the "Construction Supervision Report" immediately.
Report (Summary No. 6 style) that construction based on building energy consumption performance improvement plan was completed (outside site) |
---|
Construction Supervision Report |
If minor changes are made, explanatory materials |
Photos, etc. that can confirm the explicit status of diversion prevention when receiving floor area ratio exception is received |
About procedure to affect certification application, please confirm summary of Yokohama-shi.
Minor change applicable certification application (for buildings that receive no conformity judgment) (Summary No. 2 style) (outside site) |
---|
Notification of withdrawal (when withdrawing before certification) (Summary No. 4 style) (outside site) |
Application form (Summary No. 5 style) to cancel the plan (outside site) |
Report (Summary No. 7 style) on new construction of buildings for improvement of energy consumption performance (outside site) (When a report is requested by Yokohama City) |
Re-grant application such as authorization letter of advice (summary eleventh style) (outside site) ≪fee 300 yen≫ ※If you are not lost, please attach the previous certification notice. |
In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
To download Adobe Acrobat Reader DC
For inquiries to this page
Building Planning Division, Housing and Architecture Bureau Building Guidance Department
Phone: 045-671-4526
Phone: 045-671-4526
Fax: 045-550-3513
Email address: kc-casbee@city.yokohama.jp
Page ID: 692-697-447