Q
Do you have any materials that summarize the standards?
A

There is a "Guide to Scenic Area". We can download from homepage "1, act, permission standard requiring permission in scenic area".

Q
Is it possible to use the angle of the building coverage rate?
A

Relaxation of the occupancy rate according to the Building Standards Law, such as corner lot mitigation, cannot be applied.

Q
Is there an application fee?
A

It doesn't work.

Q
How long is the screening period?
A

It will be 15 days as standard. About buildings such as buildings, please submit permission application before submitting confirmation application.

Q
In what case, do I need to do?
A

[Building of buildings, etc.]
Construction, extension, renovation or relocation of a building, with a total floor area of more than 10 m2

[Creation of residential land, etc.]
Changes in traits of land with an area of more than 60 m2, cuts that produce glue exceeding 1.5 m, and embankment

[New construction of structures, etc.]
New construction, renovation, extension or relocation of outdoor structures such as retaining walls, towers, elevated water tanks, billboards, and the like, whose height exceeds 1.5m.

[Logging of wood and bamboo]
Cutting wood and bamboo with a height of more than 5m on the site where the building is located, cutting wood and bamboo on land where there is no building (excluding normal management activities for childcare of wood and bamboo such as thinning, pruning, and tidying) )

※In addition to the above procedures, there are changes in colors such as buildings, landfill or reclamation of the water surface, collection of debris, and accumulation of debris, waste or recycled resources outdoors.

Q
Do I need to submit a notification?
A

I need it.
When construction is completed, please submit act completion notice (17th style) in scenic area promptly. Please refer to the following for required documents.

[Building of buildings, etc.]
Completion drawing (when there is a minor change), photo of planting, etc. (the number of trees planted, tree height, planting location), overall photo of buildings, etc. (Building Standards Law)

[Creation of residential land, etc.]
Completion drawing (if there is a minor change), photo of planting, etc. (Number of trees planted, tree height, planting location), overall photo of the land, copy of the inspection certificate (development act, residential land development, etc.) When subject to)

[New construction of structures, etc.]
Completion drawing (if there is a minor change), a photo of the work (those that understand the form and design), photos of planting, etc. (If necessary as a retaining wall design), copy of the inspection certificate (development act , When it is subject to the Residential Land Development Act and the Building Standards Law)

[Logging of wood and bamboo]
Completion drawing (if there are minor changes), photos after logging, and photos of planted trees (those whose number of trees planted, height, and location of planting)

Q
I would like to confirm whether the planned site corresponds to a scenic area.
A

To confirm whether it corresponds to a scenic area, please check with iMappie (outside site) (outside site) or
Please refer to City Planning Division (045-671-3510).

For inquiries to this page

Building Planning Division, Housing and Architecture Bureau Building Guidance Department

Phone: 045-671-4526

Phone: 045-671-4526

Fax: 045-550-3513

Email address: kc-fuchi@city.yokohama.jp

Return to the previous page

Page ID: 303-952-309

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews