Specific construction work implementation notification (window)
Last update date April 10, 2024
When you are going to carry out construction work with specific construction work in designated area, please report conduct of specific construction work based on the Noise Control Law and Vibration Control Law in the next point. For more information, please refer to the following link.
Guide to Specific Construction Work Implementation Report (PDF: 1,385KB)
Areas subject to notification
The entire area of Yokohama, excluding industrial areas according to Article 8, Paragraph 1, Item 1 of the City Planning Act
Person who is obliged to report
Primary contractor who intends to carry out construction work involving specific construction work
Notification deadline
Up to 7 days prior to the start of the specific construction work
[Example]
registration form's entry guidelines and number of copies to be submitted
Formulation procedures
Notifications by law and specific construction work type according to the Noise Control Law and the Vibration Control Law should be filled out in a lump in Form 9 in registration form.
Form, registration form, etc. | Download | Example of description |
---|---|---|
[Form 9] Implementation of specific construction work registration form | What is the form | Example of description (PDF: 237KB) |
Work schedule | Work schedule (Excel: 20KB) |
Number of copies submitted
registration form requires two copies of both primary and secondary.
Matters to be noted
About the period of implementation of specific construction work
The period should be set in advance, taking into account rainy weather, etc., and submit a report.
If it cannot be completed within the period originally notified, please submit a new notification of the implementation of the specific construction work, with the day following the end of the implementation period as the start date of the specific construction work.
In this case, notification period is up to seven days prior to the start of the specific construction work.
About specific construction work at night
Night work is prohibited in principle, but if you are forced to carry out specific construction work at night, please attach a copy of the police department permit to registration form.
About registration form
A copy of the notification form may be used.
Number of working days
There is no need to submit a notification for construction work that ends on the work start date (construction work that ends in one day).
However, in the case where work is performed one day at intervals of several days, a notification is required because it is considered a continuous work instead of construction work that ends on the work start date.
attached documents of registration form
Schematic drawing near the specific construction work site
[Example of description]
Precautions for entry: Write a sketch of about 80m around the site of the specific construction work site, and illustrate the location of schools, nursery schools, hospitals, clinics, libraries, and special elderly nursing homes.
[Example of description]
Reporting destination
Please bring the registration form directly to the counter. (Reservation required)
10 City Hall 27th floor, 6-50 Honcho, Naka-ku, Yokohama City (guide map (image: 335KB))
Atmosphere and Sound Environment Division Noise Section, Yokohama Green Environment Bureau
Phone: 045-671-2485
In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
To download Adobe Acrobat Reader DC
For inquiries to this page
Atmosphere and Sound Environment Division, Green Environment Bureau
Phone: 045-671-2485
Phone: 045-671-2485
Fax: 045-550-3923
Email address: mk-souon@city.yokohama.lg.jp
Page ID: 768-520-522