Menu

Close

Here's the text.

landfill, Shinanomachi, Totsuka-ku

Last update date April 1, 2023

About business such as removal of specific trouble pertaining to landfill, Shinanomachi, Totsuka-ku

Location map

Bird's eye view


In accordance with the Special Measures Law Concerning the Removal of Failure Caused by Specified Industrial Waste, Sanko Co., Ltd. established in Shinanocho, Totsuka-ku, landfill, Totsuka-ku, Totsuka-ku, Tokyo, Sanko Co., Ltd. established on February 15, 2008, with the consent of the Minister of the Environment on the conservation in the living environment oflandfill.
Since the plan targets have not been achieved in some parts, we will continue our business until FY2022 with the consent of the Minister of the Environment on March 26, 2018, and will continue the business until FY2022.

[Press Release on March 26, 2018]
pdf About extension of business such as specific obstacle removal to affect landfill Shinanomachi, Totsuka-ku (PDF: 358KB)
pdf Project implementation plan for removal of specific obstacles pertaining to landfill, Shinano-cho, Totsuka-ku (PDF: 8,180KB) (consent to change on March 26, 2018)

pdf Project implementation plan for removal of specific obstacles pertaining to landfill, Shinano-cho, Totsuka-ku (PDF: 7,504KB) (consent to change on March 26, 2013)

[February 15, 2008 Press Release]
pdf Acquisition of consent from the Minister of the Environment for a project implementation plan for removing specific problems related to landfill, Shinanomachi, Totsuka-ku (PDF: 247KB)
pdf Project implementation plan (PDF: 3,321KB) such as removal of specific problems pertaining to landfill, Shinanomachi, Totsuka-ku

1 Background

In preparing the implementation plan for the project to remove specific obstacles, etc., a verification committee and a technical review committee were set up by experts such as academic experts, and based on the opinions of both committees, measures to prevent recurrence and countermeasure construction plans. Etc. were considered.

(1) About Verification Committee
(2) About Technical Review Committee

2 Outline of countermeasure construction

(1) Outline of construction plan

1) Measures to prevent the diffusion of groundwater pollution

By eliminating sewage in the disposal site, we will remove pollution sources and control the leakage of sewage. In addition, wells are installed at groundwater pollution points to prevent the spread of contamination by pumping up and eliminating contaminated groundwater.

2) Measures to prevent the collapse of accumulated waste

After installing earth retaining (walls to a deep foundation), the steep slope is shaped into a stable slope to prevent waste from collapsing outside the site. In addition, soil is covered with soil after shaping to prevent waste from scattering and outflow of waste.
pdf Waste collapse prevention measures (PDF: 1,107KB)

3) Schedule

In 2008, we started installation work for pumping wells for sewage, etc., installation of earth retaining walls in 2009, and shaping work on piled waste in 2010.
pdf Construction schedule (PDF: 93KB)

(2) Announcement of Shinano Town Improvement Project

Leaflets distributed to nearby residents are posted.
pdf News of Shinano-cho improvement work Vol.1 (PDF: 445KB) (December 2008)
pdf News of Shinano-cho improvement work Vol.2 (PDF: 496KB) (July 2009)
pdf News of Shinano-cho improvement work Vol.3 (PDF: 771KB) (December 2010)
pdf News of Shinano-cho improvement work Vol.4 (PDF: 434KB) (December 2011)
pdf News of Shinano-cho improvement work Vol.5 (PDF: 392KB) (September 2012)
pdf News of Shinano-cho improvement work Vol.6 (PDF: 419KB) (October 2013)

3 Monitoring of environmental impacts

1) Prevention of the diffusion of groundwater pollution
2) Prevention of collapse of piled up waste

(2) Response in case of abnormality

The Business Waste Management Section will strengthen the monitoring system in the event of abnormal weather or an earthquake, and confirm local safety.

Monitoring items in case of abnormality
Monitoring itemsCriteria
RainfallWhen the rainfall intensity is 50 mm / hour or the continuous rainfall exceeds 150 mm at the Higashitotsuka Fire Branch
When an earthquake occursSeismic intensity 4 or higher

4 Pursuing Responsibility to Executive Officers

We will continue to pursue responsibilities, including collecting administrative expenses, for those who have left inappropriate conditions for many years, including the collection of administrative expenses. In addition, we will continue to investigate whether there is any violation of laws and regulations, and if there is any violation, we will pursue responsibility.

(1) About collection of expenses from executors

A payment order and reminder were issued to the executer, using the expenses required for the construction that had already been finalized, but the delinquency was delinquent. For this reason, heavy equipment such as construction equipment left in the disposal site and property (deposits, real estate, etc.) owned by former officers were seized and exchanged by public auctions, etc., and about 7 million yen has been collected so far.

(2) About proposal of voluntary removal of waste pertaining to landfill, Shinanomachi, Totsuka-ku

We conducted a survey of waste disposal companies and received proposals from 25 companies for voluntary removal of waste.

pdf Regarding the implementation status of voluntary removal (PDF: 120KB)

In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

For inquiries to this page

Waste Management Section, Resources and Waste Recycling Bureau Business Waste Management Department

Phone: 045-671-3811

Phone: 045-671-3811

Fax: 045-663-0125

Email address: sj-shinano@city.yokohama.jp

Return to the previous page

Page ID: 563-855-228

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews