Block development status Central District (50-67 block)
Last update date April 17, 2024
Block | Business Overview | Progress and Progress | |
---|---|---|---|
50 Blocks | Pacific Royal Court Minatomirai Ocean tower | Business entities: DH Development Minatomirai (Yes) Site area: Approx. 5,000㎡ Total floor area: Approx. 45,600㎡ Facility size: 29 floors above ground, 1 floor below ground, about 100m high | Completed in November 2007 |
Pacific Royal Court Minatomirai Urban Tower | Business entities: PD Minatomirai, a special purpose company Site area: Approx. 5,000㎡ Total floor area: Approx. 45,900㎡ Facility size: 29 floors above ground, 1 floor below ground, about 100m high | Completed in June 2008 | |
Brillia Grande Minatomirai | Business entities: Co-operative Tokyo Housing Supply Center and others Site area: About 8,000㎡ Total floor area: Approx. 73,700㎡ Facility size: 30 floors above ground, 1 basement floor, about 100m high 2 buildings | Completed in November 2007 | |
52 Blocks | Minato Mirai 21 Central District 52 Development Project Plan | Business entities: Koyu Co., Ltd., a special purpose company in the 52nd district of DK Minatomirai 52 district Site area: Approx. 11,800㎡ Total floor area: Approx. 115,000㎡ Facility size: 29 floors above ground and 2 floors below ground, about 180 meters high | February, 2024 |
53 Blocks | Yokohama symphostage | Business entities: Ohbayashi Corporation, Keihin Kyuko Electric Railway Co., Ltd., Nippon Steel Kowa Real Estate Co., Ltd., Yamaha Corporation, Minatomirai EAST LLC | March, 2024 |
54 Blocks | Yokohama Grand Gate | Business entities: Shimizu Construction Co., Ltd., Mitsubishi UFJ Trust and Banking Corporation | April, 2020 |
Block 55-1 | LG YOKOHAMA INNOVATION CENTER | Business entities: LG Holdings Japan, Inc. | March, 2022 |
55-2 Blocks | Minatomirai Gakuen Building | Business entities: (Study) Minato Mirai Gakuen Site area: Approx. 3,600㎡ Total floor area: Approx. 11,000㎡ Facility size: 8 floors above ground, about 33 meters high | August, 2016 |
Block 56-1 | Keikyu Group Head Office | Business entities: Keihin Electric Express Railway Co.,Ltd. Site area: Approx. 3,600㎡ Total floor area: Approx. 25,800㎡ Facility size: 18 floors above ground, 1 basement floor, approximately 86m high | September, 2019 |
56-2 block | Shiseido Global Innovation Center (S/PARK) | Business entities: Shiseido Co.,Ltd. Site area: About 6,500㎡ Total floor area: Approx. 56,000㎡ Facility size: 16 floors above ground, 1 basement floor, approximately 77 meters high | April, 2019 |
58 Blocks | Yokohama Gate Tower | Business entities: Kajima Corporation, Sumitomo Life Insurance Company, and Mitsui Sumitomo Insurance Co., Ltd. Site area: Approx. 9,300㎡ Total floor area: Approx. 84,000㎡ Facility size: 21 floors above ground, 1 basement floor, about 110m high | March, 2022 |
Block 59-A | OKAM Minatomirai Building | Business entities: OKA CORPORATION Site area: Approx. 6,900㎡ Total floor area: Approx. 49,000㎡ Facility size: 11 floors above ground, about 52m in height | September, 2016 |
Block 59-B Block | PRYME COAST Minatomirai | Business entities: Okada Building, Ltd., Mitsubishi UFJ Trust and Banking Co., Ltd. | June, 2017 |
Block 60/61 | Music Terrace (K Arena Yokohama, Hilton Yokohama, K Tower Yokohama) | Business entities: Ken Corporation, Inc. | September, 2023 |
Block 60/61 | (Tentative name) Linkage Terrace Project | Business entities: Ken Corporation, SMFL Mirai Partners Co., Ltd., Kajima Corporation, Iwasaki Gakuen Site area: Approx. 23,000㎡ Total floor area: Approximately 25,000 m2 (West Wing) approx. 130,000 m2 (East Wing) Facility size: 13 floors above ground (west wing) 27th floor (East Wing), 1 basement floor, about 64m in height (west wing), about 100m (East Wing) | March, 2026 |
61 Blocks | Yokohama Anpanman Kodomo Museum | Business entities: Nippon Television Music Co., Ltd. Operating entity: ACM Co., Ltd. Site area: Approx. 5,700㎡ Total floor area: Approx. 14,000㎡ Facility size: 4 floors above ground, about 18 meters high | July, 2019 |
62 blocks | (Tentative name) HARBOR EDGE PROJECT | Business entities: Bell Djajajaja Yokohama Hospitality Asset Special Purpose Company | July, 2025 |
65 blocks | FUJIFILM Business Innovation, Ltd. | Business entities: Fujifilm Business Innovation Co., Ltd. Site area: Approx. 15,000㎡ Total floor area: Approx. 135,300㎡ Facility size: 20 floors above ground, 1 floor below ground, about 100m high | April, 2010 |
66 blocks | NISSAN MOTOR Co., Ltd. | Business entities: Nissan Motor Site area: Approx. 10,000㎡ Total floor area: Approx. 92,300㎡ Facility size: 22 floors above ground and 2 floors below ground, about 100m high | August, 2009 |
67 Blocks | Yokohama Mitsui Building | Business entities: Mitsui Fudosan Co.,Ltd. Site area: Approx. 7,800㎡ Total floor area: Approx. 90,200㎡ Facility size: 30 floors above ground, 2 floors below ground, about 153 meters high | March, 2012 |
※“Business entities” refers to the situation at the time of development.
To the development of other blocks
●Shinko district (1-17 block) ●Central District (18-25 blocks) ●Central district (block 26-31) ●Central district (32-38 block)
●Central District (District 39-49) ●Central district (block 50-67) ●Yokohama Station East Exit District (68 blocks)
For inquiries to this page
Minatomirai, Toshin Nagawa Coastal Area Promotion Division, Urban Development Bureau
Phone: 045-671-2038
Phone: 045-671-2038
Fax: 045-651-3164
Email address: tb-mmhigashikanarin@city.yokohama.jp
Page ID: 498-112-160