Major Flows of Land Readjustment Projects

Last Updated December 22, 2023

In order to promote the land readjustment project by the city enforcement, we are proceeding with procedures based on the City Planning Act and the Land Readjustment Act.

[Main Flow of Land Readjustment Project]
 (1) Examination of town development plans (formerly Kamiseya Communication Facility Land Use Basic Plan) (~ March 31, 2020)
 (2) Former Kamiseya Communication Facility Area Land Readjustment Project Environmental Impact Assessment Procedure
 (3) City planning decision
    Effective district (April 15, 2022)City draft briefing session document about city planning decision (February 25, 2021)
    Roads (August 25, 2023)   ※City draft briefing session document about city planning decision (change) (from November 18, 2022 to December 19, 2022)
※As for the details such as city planning roads, please see i-MAPPY.
 (4) Business plan decision
 (5) Establishment of Land Readjustment Council
 (6) Temporary replacement land designation (November 30, 2023)
 (7) Relocation and Compensation
 (8) Development of infrastructure, etc.  ※Prior to this, we have been removing U.S. military facilities since January 2023.
 (9) Landfill disposal (scheduled for FY2033)
 (10) Clearing (project completed: scheduled for March 31, 2039)

※Procedures for other projects conducted in the enforcement area
 [Reference] Environmental Impact Assessment Procedure for International Horticultural Expo 2027
 [Reference] (Tentative name) Former Kamiseya Communication Facility Park Maintenance Project Environmental Impact Assessment Procedure

2022
DateContents
November 18-December 19 (video distribution period)

We carry out city planning city draft briefing session ※It's finished.
About city planning change of city planning road 3.4.3 ring road No. 4, 3.3, 3.3.9 National highway No. 16 (Hachioji Kaido) and 2 other routes pertaining to the former Kamiseya communication facility district land readjustment project

Date and time and venue
DateTimeVenueCapacity (first come, first served)Outline of the proceedings
Saturday, November 19

19:00
Scheduled for ~20:30
[Open at 18:30]

Asahi public hall
(1-4-12 Tsurugamine, Asahi-ku)

350 peopleSummary of Minutes (PDF: 345KB)
Sunday, November 20

19:00
Scheduled for ~20:30
[Open at 18:30]

Seya Ward Office
Large conference room on the 5th floor
(190 Futatsubashi-cho, Seya-ku)

60 peopleSummary of the Minutes (PDF: 102KB)
Tuesday, November 22

19:00

Scheduled for ~20:30
[Open at 18:30]

Asahi public hall
(1-4-12 Tsurugamine, Asahi-ku)

350 peopleSummary of Minutes (PDF: 235KB)
Friday, November 25

19:00

Scheduled for ~20:30
[Open at 18:30]

Hydrangea plaza
[Seya Kumin Cultural Center]
Multipurpose music room
(4-4-10 Seya, Seya-ku, Seya-ku)

100 peopleSummary of Minutes (PDF: 219KB)

Information on the briefing venue (map, etc.) (PDF: 392KB)
●Measures to prevent COVID-19 infection
・This briefing will be held after taking measures to prevent the spread of the new coronavirus based on the policies of the prefecture.
・Please cooperate in wearing a mask, hand washing and disinfecting, measuring body temperature, and ensuring social distance when visiting.
・The temperature will be measured before entering, and if there is a fever of 37.5 ° C or higher, admission will be refused.
・Please fill in your name and contact information at the reception to respond to contact etc. as necessary.
・In addition, please follow the instructions of the staff at the venue.
・Depending on the situation of the new coronavirus infection, the holding method etc. may be changed or canceled.
●Others
・No application is required. Please come to the venue on the day.
・If you would like a sign language interpreter, please contact us at the reception desk on the day.
・You can use the toll parking lot at each venue, but the number is limited, so please cooperate with the use of public transportation.
[About video distribution]
We release contents of city planning city draft briefing session by video distribution. ※The content will be the same for the video distribution and the venue.
Video distribution period: From Friday, November 18, Reiwa 4 to Monday, December 19
Video (YouTube) ※It's finished.
[Reception of questionnaires and public statements, public hearings, etc.]
The publication period has ended.

October 17-November 12

We carry out online briefing session to affect road plan in former Kamiseya communication facility district land readjustment project
In the former Kamiseya communication facility district, the enforcement area was decided on a city plan on April 15, 2022, a business plan was decided on October 5, and a land readjustment project was promoted by city enforcement.
We carry out briefing session for city planning procedure to affect road plan of this district this time. In addition, to prevent the spread of COVID-19 infection, video distribution will be performed on the Yokohama City website.
[Road to proceed with this procedure]
(Roads in the land readjustment project enforcement area)
Change of widening of Ring Route 4 No. 3, 4, and 3
New addition of Kamikawai Seya Line 1, No. 3, 3, 53
New addition of Kamikawai Seya Line 2, No. 3, 3, 54
(Hachioji Kaido)
Change of widening of National Route 16 No. 3, 3, 9
[Overview of online briefing sessions for city planning procedures related to road planning]
■Video distribution period
From 9:00 am on Monday, October 17, 2022 to 5:00 pm on Saturday, November 12
Online Explanation Video (YouTube) ※It's finished
Online briefing materials (PDF: 3,784KB)
■Questionnaire reception
We will accept a questionnaire regarding the content of the online briefing. Answers to the questionnaire will be published on the website.
■Questions and Answers
[Primary] From Monday, October 17, 2022 to Monday, October 24, 2022  ※It's finished.
≪Primary≫ Questions and Answers (PDF: 301KB)
[Second] From Tuesday, October 25, 2022 to Friday, November 4, 2022 ※It's finished.
≪Second ≫ Questions and Answers (PDF: 388KB)
■Submission method
You can submit a questionnaire by electronic application. required items (name, contact information, Address, project name and question content) must be submitted by mail or by mail (weekdays from 8:45 to 5:00 p.m. on weekdays).
■Questionnaire submission destination
[Submission of Questionnaire by Electronic Application]
・Electronic Application Service ※It's finished.
 ※It cannot be used during the maintenance period (irregular).
 ※There are restrictions such as the number of characters and model-dependent characters. Please be careful.
[Submission of written questionnaire]
Please fill in the questionnaire (the form is free) with required items described in the submission method and mail or bring it by mail (8:45 am to 5:00 pm on weekdays) by the last day of submission.

≪Submission: 29th floor of 6-50-10 Honmachi, Naka-ku, Yokohama 231-0005, Japan
 Urban Development Bureau Kamiseya Maintenance Promotion Section

October 5

Yokohama International Port Construction Project Former Kami Seya Communication Facility District Land Readjustment Project has been decided!
In the former Kami-Seya communication facility area, we will eliminate the mixture of state-owned land and private land, consolidate land for agricultural promotion and urban land use, and integrate the development of urban infrastructure such as agricultural infrastructure and roads necessary in the future. For the purpose of promoting the project, we have been coordinating with the former Kami-Seya Communication Facility Town Development Council, which is composed of landowners.
Since the outline of the design has been approved by the Ministry of Land, Infrastructure, Transport and Tourism, based on the provisions of Article 55, Item 9 of the Land Readjustment Act, a business plan was decided on October 5, 2022, and land readjustment project I will proceed.
[Press Release] Yokohama International Port Construction Project Former Kami Seya Communication Facility District Land Readjustment Project has been decided! (PDF:774KB)

June 4

About general inspection of business plan of former Kamiseya communication facility district land readjustment project ※It's finished.

 About former Kamiseya communication facility district land readjustment project, business plan was finished, so Article 55 of the Land Readjustment Act
Based on the provisions of paragraph 1, we will conduct a public inspection.
 In accordance with the provisions of Article 55, Paragraph 2 of the Act, interested parties shall submit a written opinion on the contents of the business plan.
You can do it.
  
[Press Release] About general inspection of business plan of former Kamiseya communication facility district land readjustment project (PDF: 200KB)
 
[Inspection]
1.Contents of inspection
  Business plan of the land readjustment project for the former Kamiseya communication facility area
2.Inspection period
  From Saturday, June 4, 2022 to Friday, June 17, 2022
  ※During the period, public inspection is also possible on Saturdays and Sundays.
3.Inspection time
  From 8:45 a.m. to 5:15 p.m.
4.Public inspection site
  [Weekdays] Urban Development Bureau Kamiseya Maintenance Promotion Section
      (South side of the 29th floor of 10 City Hall, 6-50 Honmachi, Naka-ku)
  [Saturday and Sunday] Citizen collaboration promotion center (collaboration lab)
      (10th floor of 10 City Hall, 6-50 Honmachi, Naka-ku)
・Those who wish to have a public inspection are directly connected to the 1C entrance to the Yokohama City Hall (Minato Mirai Line Bashamichi Station) and JR/Municipal Subway Sakura.
 Please come to the nearest bus stop, Yokohama City Hall-mae, a 3-minute walk from Kimachi Station.
・On weekdays, please go up to "3rd floor city hall reception desk", and at the reception counter, say "29th floor Kami Seya maintenance promotion section"
 Please come out.
・As Saturdays and Sundays are closed days, please come directly to "1st floor citizen collaboration promotion center (collaboration lab)"
・Outside the opening hours of the 1st floor Citizens' Collaboration Promotion Center (Collaborative Lab) on Saturdays and Sundays (from 8:45 am to 9:00 am, 5:00 pm
 From 5:15 pm to 5:15 pm), there is a person in charge in front of the entrance of the collaborative lab, so please call out.
・During the inspection process, the person in charge may be absent. In that case, please wait a while or contact the following address:
 Please contact us.
 [Contact] Urban Development Bureau Kamiseya Maintenance Promotion Division Telephone: 045-671-2061


[Submission of Statement of Opinion]

1. Acceptance Period
   From Saturday, June 4, 2022 to Friday, July 1, 2022

2.Submission method
  required items (Address, name, contact information, opinion on business plan) is filled out in the written opinion and urban development within the application period.
 Please bring or mail to the Bureau Seya Maintenance Promotion Section.
  In case of bringing: Excluding Saturdays and Sundays, from 8:45 am to 5:15 pm
        (During the inspection period from June 4 to June 17, on Saturdays and Sundays, the "1st floor Citizen Collaboration Promotion Center"
        (Collaborative Lab) ".
  In the case of mailing: Effective postmark on Friday, July 1, 2022

3.Style of Statement of Position
  Statement of Position ※It's finished.
 
4.Submission address
  〒231-0005
  6-50 Honcho, Naka-ku 10 City Hall 29th floor south side (green)
  Urban Development Bureau Kamiseya Maintenance Promotion Section

April 15

We made press release about "city planning decision of former Kamiseya communication facility district land readjustment project and environmental impact assessment book". .
Press release document (PDF: 562KB)

2020

From February 5 to 22
(Online)

An online briefing was held for the city planning decision of the land readjustment project area in the former Kamiseya communication facility area.

・Online briefing video (YouTube) (* Disclosed)

Online briefing materials (PDF: 3,842KB)
What is the land readjustment project (PDF: 181KB)


[Reception of Questionnaire] ※Acceptance of the questionnaire has been closed.

■Acceptance Period

 From Friday, February 5, 2021 to Monday, February 15, 2021

■Scheduled date of publication

 Monday, February 22, 2021

■How to submit


[Submission of Questionnaire by Electronic Application]

・Electronic application service (PC) (* Acceptance of questionnaires has been completed.)

・Electronic application service (smartphone) (* Acceptance of questionnaires has been closed.)

 ※It cannot be used during the maintenance period (irregular).

 ※There are restrictions such as the number of characters and model-dependent characters. Please be careful.


[Submission of written questionnaire]

Fill out the following questionnaire (any format is acceptable) with required items, and mail or bring it by the last day of submission.

(8:45 am to 5:00 pm on weekdays)
 ※At the Seya Ward Office and the Asahi Ward Office's Ward Administration Promotion Division Office, you can read materials and accept questionnaires.

≪4-43 Honmachi, Naka-ku, Yokohama 231-0005 A-PLACE Basyamichi, 4F, Japan
 Urban Development Bureau Kamiseya Maintenance Promotion Section

・Questionnaire (* Acceptance of questionnaire has been closed.)

・Questionnaire (* Acceptance of questionnaire has been closed.)


[Answer to Questionnaire]

Question summary and answer (PDF: 218KB)

August 1, 2, 4, 5 An environmental impact assessment method briefing session was held.
(Tentative name) It was held jointly with the briefing session on the method of the Urban Expressway Railway Seya Line Maintenance Project.
Announcement of public inspection and briefing on environmental impact assessment method book (PDF: 1,051KB)
Environmental Impact Assessment Method Explanation Video (External Site) ※The content of the video is the same as the Briefing Session.
Explanatory materials (PDF: 7,307KB)
Reference slide (PDF: 422KB)
Status of the briefing and Q & A session (PDF: 531KB)
From July 21 to September 3 (Tentative name) For the former Kami Seya Communication Facility Land Readjustment Project, we created an environmental impact assessment method book based on the Environmental Impact Assessment Law and conducted a general inspection. .
[Press Release] (Tentative name) We inspect environmental impact assessment method book of former Kami-Seya communication facility district land readjustment project and (tentative name) Urban Expressway Railway Kami-Seya Line maintenance project and hold briefing session!

2019

From January 15 to February 14

(Tentative name) We carried out general inspection of plan stage environmental consideration book and design stage evaluation book pertaining to former Kami Seya communication facility district land readjustment project.
[Press Release] "We will start full-scale procedures for commercialization of businesses related to the promotion of land use at the former Kamiseya Communication Facility!"

You may need a separate PDF reader to open a PDF file.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

Inquiries to this page

Decarbonization, GREEN x EXPO Promotion Bureau Kami Seya Maintenance Office Kami Seya Maintenance Promotion Section

Telephone: 045-900-0594

Telephone: 045-900-0594

Fax: 045-550-4098

Email address: da-kamisui@city.yokohama.lg.jp