Kanazawa Wastewater Treatment Plant

Last update date April 4, 2024

Kanazawa Wastewater Treatment Plant supports moisture to the historic Kanazawa

Photo of Kanazawa Wastewater Treatment Plant

Overview

Treatment area in Kanazawa Wastewater Treatment Plant

Kanazawa Wastewater Treatment Plant was constructed as part of a sewerage improvement plan based on the Yokohama International Port City Construction Plan, and commenced operation in October 1979 as the eighth water reclamation center in Yokohama.
In April 2009, the adjacent Nambu Sludge Treatment Plant was integrated to unify management, and from April 1, 2010, the organization was renamed Nambu Sewerage Center.

Kanazawa Ward and part of Isogo Ward and Konan Ward are treated as treatment zones.

Sewage flows directly or flows into the water reclamation center via the Kanazawa pumping station, is treated high-grade treatment by the standard activated sludge method, and (partially advanced treatment by the A2O method is performed in some series), sterilization from Tomioka River to Tokyo Bay. Will be released.


  • Site area: 129,440㎡
  • Planned processing area: 4,913㏊
  • Processed population: 381,600 people
  • Plan processing capacity: 221,900㎥
  • Sludge treatment: Pumping to Nambu Sludge Treatment Plant

Kanazawa Wastewater Treatment Plant Brochure (PDF:980KB)

Characteristics

  1. In the first, second and third series of water treatment, advanced treatment is performed using anaerobic-aerobic method (A2O method) for the purpose of removing nitrogen and phosphorus.
  2. There are facilities for reuse of treated water, which is used as cooling water for machines, rinsing water in the premises, and as a heat source for air conditioners in the main building. It also supplies water to neighboring Nambu Sludge Treatment Plant and Resources and Waste Recycling Bureau Kanazawa plants as miscellaneous water.
  3. The jurisdiction facilities include Kanazawa pumping station (sewage relay / rainwater drainage pumping station) and Rokuura pumping station (rainwater drainage pumping station). In each case, a distant monitoring and control device is used to operate and monitor from the water reclamation center to save labor.
  4. In the Torihama and Fukuura districts, there are the Torihama Daiichi Plant wastewater treatment plant and the Fukuura Factory wastewater treatment plant as pretreatment facilities for the purpose of pollution control in the city. Co-processing.
    (The Torihama Daini Factory Wastewater Treatment Plant was abolished on March 31, 2013.)

Pumping stations under the jurisdiction of

Kanazawa pumping station

Photograph of Kanazawa Pumping Station

  • Site area: 14,710㎡
  • Planned drainage area: 390㏊
  • Planned drainage capacity: 65.1m3 per second
  • Start of operation: March, 1981

Rokuura Pumping Station

Photo of Rokuura Pumping Station

  • Site area: 3,000㎡
  • Planned drainage area: 102㏊
  • Planned drainage capacity: 11.4m3 per second
  • Start of operation: November, 1973

Pretreatment facilities for factory wastewater

Torihama Daiichi Plant Wastewater Treatment Plant

Photograph of the Torihama Daiichi Plant

  • Planned amount of cyanide wastewater treatment: 60 per day㎥
  • Chromium-acid alkaline wastewater Planned treatment volume: 340 per day㎥
  • Public sewage drainage: August, 1978
  • Start of operation: May, 1973

Fukuura Plant Wastewater Treatment Plant

Photographs of Fukuura Plant

  • Planned amount of cyanide wastewater treatment: 130 per day㎥
  • Planned amount of chromium wastewater treatment: 75 per day㎥
  • Acidal alkaline wastewater treatment volume: 1,320 per day㎥
  • Public sewage drainage: April, 1998
  • Start of operation: May, 1982

Access

If you are coming from Namikikita Station on the Kanazawa Seaside Line

Kanazawa Wastewater Treatment Plant is a 5-minute walk from Namikikita Station on the seaside line.

Photo of ticket gate at Namikikita Station

(1) Exit the ticket gate at Namikikita Station on the Seaside Line and proceed to the left.


Photograph on the 2nd floor exit of Namikikita Station

(2) Go down the stairs of "Exit 2".


Photo under the 2nd stairs exit from Namikikita Station

(3) If you go down the stairs, go straight to the intersection.


Photo of Koura 1-chome intersection

(4) Go right at the intersection of Koura 1-chome, please go right.


Photo of the main gate of Kanazawa Wastewater Treatment Plant

(5) After a while, you will arrive at the main gate of Kanazawa Wastewater Treatment Plant. Thank you very much for your help. The office is located on the second floor, up the stairs.


In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

For inquiries to this page

Sewerage River Bureau Sewerage Facilities Department Nambu Sewerage Center

Phone: 045-773-3096

Phone: 045-773-3096

Fax: 045-776-1689

Email address: gk-nambugesuido@city.yokohama.lg.jp

Return to the previous page

Page ID: 664-250-368

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews