Introduction to Hokubu No.1 Wastewater Treatment Plant

Hokubu No.1 Wastewater Treatment Plant Main Gate

View of Hokubu No.1 Wastewater Treatment Plant


Returning to Introduction of Water Reclamation Centers


Hokubu No.1 Wastewater Treatment Plant is a combined sewage treatment facility that covers the northwestern part of Tsurumi Ward and part of Kohoku Ward. Sewage is cleaned by the activated sludge method and discharged into the Tsurumi River. In addition, along the Tsurumi River, a first-class river, three sewage relay and rainwater drainage pumping stations, five rainwater drainage pumping stations, and three underground pumping facilities are managed along the coast to drain rainwater quickly to the Tsurumi River. We are making efforts to prevent flooding in the town. In addition, a rainwater reservoir is operating as an initial pollution countermeasure during rainfall.

Overview of Hokubu No.1 Wastewater Treatment Plant
Site area100,320m2
Planned processing area2,150ha
Processed population297,100 people
Planned processing capacity139,100m33/day (currently 149,600m3/day)
Sludge treatmentPumping to Hokubu Sludge Treatment Plant

You can download the outline brochure of our Center.
"Introduction of Water Reclamation Center" ~ Hokubu No.1 Wastewater Treatment Plant (PDF: 480KB)



Hokubu No.1 Wastewater Treatment Plant manages many pumping stations and prevents flooding in the town as a measure against rainwater drainage. In addition, Motomiya pumping station and rainwater reservoir are installed as a measure to prevent pollution during rainfall, and the upper part is open as a park.

Kamisueyoshi Pumping Station

Panoramic view of Kamisueyoshi pumping station

Overview of Kamisueyoshi Pump Station
Site area2,650m2
Planned drainage area131.9ha
Planned drainage capacity792.0m3/min
Start of operationMarch, 1987

Sueyoshi Pumping Station

View of the Sueyoshi Pumping Station

Overview of Sueyoshi Pumping Station
Site area2,220m2
Planned drainage area428.0ha
Planned drainage capacity625.8m3/min
Start of operationMarch, 1964

Takada Pumping Station

Panoramic view of Takada Pumping Station

Outline of Takada Pumping Station
Site area5,300m2
Planned drainage area305.0ha
Planned drainage capacity2025.0m3/min
Start of operationMarch, 1985

Tarumachi Pumping Station

Panoramic view of Tarumachi pumping station

Outline of Tarumachi Pumping Station
Site area14,700m2
Planned drainage area604ha
Planned drainage capacity2,774.2m3/min
Start of operationApril, 1967

Kita-Tsunashima Pumping Station

Panoramic view of Kita-Tsunashima Pump Station

Outline of Kita-Tsunashima Pumping Station
Site area6300m2
Planned drainage area913ha
Planned drainage capacity1,989.0m3/min
Start of operationMay, 1972

Egasaki Pumping Station

Panoramic view of Egasaki pumping station

Outline of Egasaki Pumping Station
Site area2,630m2
Planned drainage area147.0ha
Planned drainage capacity960.0m3/min
Start of operationNovember, 1991

Tsunashima No.2 Pump Station

Outline of Tsunashima No.2 Pump Station
Site area496.0m2
Planned drainage area47.8ha
Planned drainage capacity67.2m3/min
Start of operationJuly, 1961

Minami-Tsunashima Pump Station

Outline of Minami Tsunashima Pumping Station
Site area1,200m2
Planned drainage area257.9ha
Planned drainage capacity64.2m3/min
Start of operationFebruary, 1958


We participate in facility tour events and local festivals.


Access map (PDF: 71KB)

When coming from JR Tsurumi Station

Tsurumi Station Yokohama East Exit Bus Terminal

Take a bus from Tsurumi Station Yokohama East Exit Bus Terminal No. 1 and 2 at Tsurumi Station, get off at the fourth bus stop, Morinaga Factory.

(As of November 2015, you can use 13 municipal buses from Platform No. 1 and 29 and 155 municipal buses from Platform 2.)


In front of Morinaga Plant bus stop

When you get off the bus stop, the front is Mornaga & Co. Tsurumi Plant, head to the left, cross the next traffic light, and head toward Tsurumi Sports Center. Hokubu No.1 Wastewater Treatment Plant is about a 10-minute walk.


Morinaga Bridge

Beyond Morinaga Bridge is Tsurumi Sports Center and Hokubu No.1 Wastewater Treatment Plant on your right.


Hokubu No.1 Wastewater Treatment Plant exterior

Go ahead while looking at Hokubu No.1 Wastewater Treatment Plant on your right. The main gate is located in the back of the left.


Hokubu No.1 Wastewater Treatment Plant Main Gate

Click here for the main gate of Hokubu No.1 Wastewater Treatment Plant.


When you come by car

Intersection in front of Morinaga Factory

From Tsurumi Station, turn right at the intersection in front of Morinaga Factory, cross the Morinaga Bridge, turn right after crossing Morinaga BridgeHokubu No.1 Wastewater Treatment Plant.


In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
Get Adobe Acrobat Reader DCTo download Adobe Acrobat Reader DC

For inquiries to this page

Sewerage River Bureau Sewerage Facilities Department Hokubu No.1 Wastewater Treatment Plant

Phone: 045-572-2281

Phone: 045-572-2281

Fax: 045-572-1109

Email address: gk-hokubu1wtp@city.yokohama.lg.jp

Return to the previous page

Page ID: 954-827-652

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews