It is Yokosuka power station construction work environmental assessment procedure the suburbs 2

Last update date February 25, 2019

List of procedure situation

Business name

Yokosuka power station construction work

Business position

5-2931-70, Uragocho, Yokosuka-shi others

Business type

Setting (targeted for law) of power station

Company

Tokyo Menka Kaisha, Ltd. power Yokosuka

Influence is

Yokosuka-shi, Yokohama-shi (Konan Ward, Isogo Ward, Kanazawa Ward, Sakae Ward), Kamakura-shi, Zushi-shi, Hayama-machi

Method book

Sending: January 11, 2001
Notification, general inspection: From January 12, 2001 to February 26

Opinion summary

Sending: March 14, 2001
The number of the authorities of statement of position: Eight (Yokohama citizen: 0)

Opinion statement

Report: 0 people

Examination committee

Question: January 26, 2001
Report: April 10, 2001

The mayor opinion

Making: April 25, 2001
Notification, general inspection: From May 2, 2001 to May 31

Brief, abstract of the disclosure

Sending: July 4, 2002
Notification, general inspection: From July 5, 2002 to August 19

Area concerned

Yokosuka-shi, Yokohama-shi (Kanazawa Ward), Zushi-shi, Hayama-machi

Briefing session

July 18, 2002 Kanazawa Ward (once), suburbs four times, five times in total

Opinion summary, opinion

Sending: September 26, 2002
The number of the authorities of statement of position: Five of them

Opinion statement

Report: One person
Cancellation of opinion statement: One person

Examination committee

Question: July 23, 2002
Report: October 10, 2002

The mayor opinion (PDF: 5KB)

Making: October 22, 2002
Notification, general inspection: It is November 25 from October 25, 2002

Evaluation book, abstract of the disclosure

Sending: July 10, 2003
Company general inspection: It is August 11 from July 11, 2003

Adobe Acrobat Reader DC (old Adobe Reader) is necessary to open file of Portable Document Format.
Person who does not have can download free of charge from Adobe company.
Get Adobe Acrobat Reader DCTo downloading of Adobe Acrobat Reader DC

Inquiry to this page

Environmental Planning Bureau policy coordination department environmental assessment section

Telephone: 045-671-2495

Telephone: 045-671-2495

Fax: 045-663-7831

E-Mail address [email protected]