Other Continuous Overpass Business
Last Updated September 28, 2022
■Major Overpass Projects
Railroad Name | Extension | Number of railroad crossings | Year of completion | Major intersections |
---|---|---|---|---|
Keikyu Shonan Line | Approx. 1.5km | 5 | Completed in FY1980 | Mizonokuchi, Tsurumi Line |
Tokyu Denentoshi Line | 312m | Three-dimensional road | Completed in FY1989 | Shinkoji Nagatsuta Line |
Tokyu Toyoko Line | Approx. 0.8km | 3 | Completed in fiscal 1994 | City street 209, Kikuna |
Keikyu Shonan Line | Approx. 1km | 3 | Completed in fiscal 1994 | Shiomidai Hirado Line |
Sotetsu Main Line | 260m | Three-dimensional road | Completed in fiscal 1998 | Tokiwadai, Hodogaya Line |
Keikyu Shonan Line | Approx. 0.9km | 2 | Completed in fiscal 1999 | City Road Sasashita 270 |
Tokyu Toyoko Line | Approx. 1.8km | 4 | Completed in FY 2002 | Hiyoshi Motoishikawa Line |
Sotetsu Main Line | 354m | Three-dimensional road | Completed in fiscal 2005 | Ring Route 4 |
Sotetsu Main Line | Approx. 1.9km | 9 | Completed in FY2021 | Iwama Riverside Line |
Sotetsu Main Line | Approx. 2.8km | 10 | In business | Sakamoto Tsurugamine Line |
Keikyu Shonan Line (around Kamiooka)
Toukyu Toyoko Line (Hiyoshi to Tsunashima)
Sotetsu Main Line (Hoshikawa-Tennocho)
Inquiries to this page
Construction Section of Construction Department, Road and Highway Bureau Construction Department
Telephone: 045-671-2792
Telephone: 045-671-2792
Fax: 045-663-8993
Email address: do-tetsudou@city.yokohama.lg.jp
Page ID: 521-280-184