Yokohama City Government Building Construction Times
Last Updated June 26, 2020
We send about design, plan summary of new city hall and progress of construction, construction method to all of you once every three months as "Yokohama City Government Building Construction Times".
Last issue (PDF: 1,960KB)
(Apr. 2020)
~ At the end of January, the building was completed~
Oh Completed Report
Office (high-rise section)
Meeting room and committee room (middle layer)
Atrium (low-rise part)
Citizen use facilities (low-rise building)
Exhibit and Remains Exhibition
Connection between Bashamichi Station and Sakuramirai Bridge
No. 10 (PDF: 2,239KB)
(December 2019)
~ Appearance, close to completion! ~
Oh Points of the plan
Planning of exterior and parliamentary functions
Oh On-site report
Planting, exterior, low-rise part, and atrium
Oh About historical remains excavated at the new city hall site
No. 9 (PDF: 5,673KB)
(September 2019)
~ The atrium, which is a atrium space with a height of about 20m, has appeared~
Oh Plan for atrium
Oh I know a little bit of architecture
Method of construction of atrium
Oh On-site report
Construction status of administrative buildings, atrium, and parliamentary buildings
Oh I received a power in August
No. 8 (PDF: 2,154KB)
(June 2019)
-All installation of the outer wall of the administrative building has been completed~
Oh Points of the plan
Plan for the high-rise floor of the Administration Building
Oh I know a little bit of architecture
Elevators that support middle-rise seismic isolation
Oh On-site report
Atrium steel frame construction, interior work of the administrative building, floor of the parliamentary hall, etc.
Oh The upper building has been built
No. 7 (PDF: 2,006KB)
(February 2019)
-Exterior work has progressed and the overall picture of the building has begun to appear! ~
Oh Points of the plan
Use of BIM
Oh Demolition of large tower cranes
Oh On-site report
Steel frame construction, exterior wall work, equipment plumbing work, foundation work, etc.
Oh "Out Kannai OPEN!" Participation in
No. 6 (PDF: 5,511KB)
(December 2018)
~ The ground steel frame and exterior are steadily rising! ~
Oh Points of the plan
Environmental Technology (Fuel Cell)
Oh I know a little bit of architecture!
How do you build a steel frame straight?
Oh On-site report
Status of steel frame construction and fire-resistant coating
Oh Interview with a temporary enclosure art creator
Oh Implementation of Children's Adventure
No. 5 (PDF: 2,127KB)
(Aug. 2018)
~ The ground steel frame is steadily rising! ~
Oh Points of the plan
Environmental Technology
・Air-conditioning system in offices
・DHC (Regional Heating and Cooling)
・Geothermal Air Conditioning
Oh On-site report
How do you go up the tower crane?
Construction status at the site
Oh I know a little bit!
Symposium
Introduction of temporary enclosure art
No. 4 (PDF: 2,715KB)
(Apr. 2018)
We are proceeding with ground construction and underground construction at the same time! ~
Oh Points of the plan
BCP measures
・Highest Seismic Performance in Japan - Adoption of Hybrid Seismic Isolation
Oh On-site report
Ground steel frame construction and seismic isolation layer construction
Underground excavation work, steel frame construction, and floor construction
Oh I know a little bit!
Supervisor design of the new city hall
No. 3 (PDF: 1,634KB)
(February 2018)
-To a new government building that plays a central role in crisis management that can deal with various crises-
Oh Points of the plan
BCP measures
・Equipment-related measures
・Introduction of Earthquake and Structural Monitoring System
Oh On-site report
Flow of steel frame construction and first floor preceding floor construction
Oh I know a little bit of architecture!
What is the capacity of the tower crane?
No. 2 (PDF: 3,388KB)
(November 2017)
~ We are working on pile construction that will form the foundation of the building~
Oh Points of the plan
The concept of landscape formation
Exterior Exterior Planning
Oh On-site report
Flow of construction of punch piles and structures
Oh I know a little bit of architecture!
What is the difference?
No. 1 (PDF: 1,009KB)
(Aug. 2017)
Construction started with the aim of completion in 2020! ~
Oh Points of the plan
Where is the new city hall planned?
What kind of building is the new city hall?
Oh On-site report
A groundbreaking ceremony was held!
Oh I know a little bit of architecture!
The construction period is shortened by the reverse hitting (Sakauchi) method!
In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
To download Adobe Acrobat Reader DC
For inquiries to this page
General Affairs Bureau General Affairs Department Administration Division
Phone: 045-671-2082
Phone: 045-671-2082
Fax: 045-662-7650
Email address: so-kanri@city.yokohama.jp
Page ID: 376-044-605