Situation of construction site of new city hall
Last Updated June 26, 2020
The latest situation | |
---|---|
Appearance on the north side of the site 3rd floor citizen lounge | Photo taken on January 31, 2020 With this, it is the last time to deliver the situation at the site. Thank you very much for watching over the long time. |
Past situation | |
Exterior on the south side of the site | Photo taken on December 24, 2019 The Parliament building is proceeding with furniture construction in the parliament building. In addition, completion inspections are being carried out atrium and underground locations. |
Appearance photo on the south side of the site | Photo taken on November 22, 2019 In the administrative building, finishing work has been almost completed up to the upper floor, and completion inspections are underway. |
Photograph of exterior on the west side of the site | Photographed on October 29, 2019 We are working on finishing work such as carpets to the upper floor of the Gyosei Building.In the atrium, exterior walls and ceiling construction are progressing, and the scaffolding is being dismantled and floor equipment is being constructed. The Parliament Building is working on walls and ceilings in the parliament. Underground equipment construction on the second basement floor is progressing, and wall and floor finishing work is underway. The first basement floor is under construction of ceilings and equipment. |
Appearance photo on the south side of the site Internal view photos of the administrative building (elevator lobby) | Photo taken on September 6, 2019 In the Gyosei Building, interior work and equipment work have progressed to the upper floors, and unit work such as toilets is being promoted. |
Appearance photo on the north side of the site Internal view of the administrative building (office room) | Photographed on August 7, 2019 |
Photographed on June 21, 2019 | |
Photo taken on May 20, 2019 The government building is working on waterproofing work on the roof and installing solar panels. In addition, a new medium-sized tower crane was assembled to dismantle the large cranes that had been used so far. Inside, we are proceeding with interior and equipment construction. | |
Photographed on April 19, 2019 | |
Photographed on March 19, 2019 | |
Photographed on February 19, 2019 | |
Photographed on January 28, 2019 In the administrative building, exterior wall panels were installed from the 23rd floor to the 25th floor. In addition, we plan to construct the steel frame of the tower from February. The Congress Building is placing concrete on the roof surface and installing exterior wall panels. Underground, we are working on skeleton construction on the second basement floor and partitioning on the first basement floor. | |
| Photo taken on December 19, 2018 The administrative building has undergone steel frame construction on the 30th to 32nd floors, and has been completed to the top floor. The tower crane will also climb to the top floor, and the remaining tower will be constructed with steel frames. The exterior wall panels were installed from the 18th to the 22nd floor. In the assembly building, steel construction was completed to the roof, and a deck on the roof was laid. In the basement, we are continuing to focus on skeleton construction on the second basement floor and equipment plumbing on the first basement floor. |
| Photo taken on November 20, 2018 The administrative building has completed steel frame construction on the 27th to 29th floors, and is also proceeding with floor construction, fireproof coating work, and partition work. In addition, exterior wall panels were installed from the 14th floor to the 17th floor. In the parliament building, steel frames have been assembled up to the roof on the 8th floor. In the basement, excavation work has been almost completed, and we are focusing on skeleton work on the second basement floor and equipment plumbing work on the first basement floor. |
Photographed on October 28, 2018 The administrative building has almost completed the steel frame construction on the 24th to 26th floors, and is also proceeding with floor construction, fireproof coating work, and partition work. In addition, exterior wall panels were installed from the 9th to the 13th floors. The parliament building has constructed steel frames on the 4th to 6th floors. Underground, we continue to carry out excavation work on the second basement floor, skeleton work, fireproof coating work on the first basement floor, and equipment plumbing work. | |
Photo taken on September 23, 2018 The administrative building has completed steel frame construction on the 18th to 20th floors, and is also proceeding with floor construction and fire-resistant coating work. In addition, exterior panels have been installed on the 5th to 8th floors. The Parliament Building is under construction of steel frames on the 4th to 6th floors. In the basement, we continue to carry out excavation work on the second basement floor, fireproof coating work on the first basement floor, and equipment plumbing work. | |
Photographed on August 21, 2018 The administrative building has completed steel construction on the 12th to 14th floors, proceeded with floor construction, and started steel construction on the 15th to 17th floors. In addition, some exterior panels were installed on the 3rd to 4th floors. The Congress Building proceeded with floor construction on the seismic isolation floor and installed seismic isolation devices. Underground, we are proceeding with excavation work on the second basement floor, fireproof coating work on the first basement floor, and equipment plumbing work. | |
Photographed on July 23, 2018 The administrative building has completed steel construction on the 9th to 11th floors, proceeded with floor construction, and started steel construction on the 12th to 14th floors. The Assembly Building has completed steel frame construction on the first to second floors, and has been performing foundation work to install seismic isolation devices. Underground, we proceeded with excavation work on the second basement floor and floor work on the first basement floor, and started fire-resistant coating work. | |
Photographed on June 22, 2018 | |
Photo taken on May 22, 2018 On the ground, we have been working on steel and floor construction on the 3rd to 5th floors. In the basement, drilling work has been started up to the second basement floor. In addition, we continue to work on steel frames and floors on the first basement floor. | |
Photographed on April 23, 2018 | |
Photographed on March 24, 2018 | |
Photographed on February 21, 2018 | |
Photographed on January 28, 2018 | |
Photo taken on December 21, 2017 | |
Photo taken on November 22, 2017 | |
Photographed on October 27, 2017 | |
Photo taken on September 25, 2017 | |
Photographed on August 22, 2017 | |
Photographed on July 21, 2017 At the site, we were preparing for the start of construction in August. | |
※Photo: Provided by the Takenaka-Nishimatsu Construction Joint Venture |
Inquiries to this page
General Affairs Bureau General Affairs Department Administration Division
Telephone: 045-671-2082
Telephone: 045-671-2082
Fax: 045-662-7650
Email address: so-kanri@city.yokohama.lg.jp
Page ID: 335-832-019