Fire Bureau Standard Processing Period

 ※These standard processing periods do not include the number of days required for correction, etc.

Last Updated October 1, 2024

List of standard processing periods for Fire Bureau (*as of October 1, 2024)
Jurisdiction section, etc.Laws, ordinances, etc.Basis clause
[Article-(No.)]
Office work related to licensing, etc.Standard processing period
Total number of daysPassover
Organizations, etc.
Passover
Number of days
fire brigade DivisionOrdinance for Enforcement of compensation for public affairs accidents such as fire brigade, Yokohama City4Certification of compensation for public affairs accidents14Each fire department7
5-1Approval of nursing, etc.14Each fire department7
Each fire departmentYokohama City Fire Prevention Ordinance28-1Approval of smoking, etc. in places where smoking is prohibited5
76-2-1Confirmation of water filling and water pressure inspection of small quantities of hazardous materials tanksFrom the date of completion of the inspection 5
Fire Services Act8-2-3-1Special certification for inspection of fire prevention objects and reporting30
10-1Approval of temporary storage and temporary handling of hazardous materials5
14-2-1Establishment and change approval of prevention regulations10
36-1Special certification for disaster prevention management inspections and reporting30
Decree on the Regulation of Dangerous Goods8-4Reissuance of completion inspection certificate2
Yokohama City Dangerous Goods Regulations20-2Approval of reissuance of installation permit, inspection certificate, etc.2
Law Concerning the Security of Liquefied Petroleum Gas and Proper Transactions36-2Issuance of written opinion pertaining to permission to install liquefied petroleum gas storage facilities, etc.From the date of completion of the survey or from the date of arrival of the survey sheet 5
Regulations for Enforcement of the Act on Ensuring Security of Liquefied Petroleum Gas and Proper Transactions56-2Issuance of written opinion pertaining to permission to change the installation of liquefied petroleum gas storage facilities, etc.From the date of completion of the survey or from the date of arrival of the survey sheet 5
Security Section, each fire departmentFire Services Act11-1Permission to install hazardous materials factories, etc.19Each fire department4
15
(in the case of fire chief's decision)
Permission to change hazardous material factories, etc.14Each fire department4
10
(in the case of fire chief's decision)
11-5Confirmation of completion inspection of hazardous materials factories, etc.From the date of completion of the inspection 9Each fire department4
From the date of completion of the inspection 5
(in the case of fire chief's decision)
11-5
Proviso
Approval of temporary use of hazardous materials factories, etc.14Each fire department4
10
(in the case of fire chief's decision)
11-2-1Confirmation of inspections before completion inspection of hazardous materials factories, etc.From the date of completion of the inspection 9Each fire department4
From the date of completion of the inspection 5
(in the case of fire chief's decision)
Security SectionFire Services Act14-3-1Confirmation of security for outdoor tank storageFrom the date of completion of the inspection 19Each fire department4
14-3-2Confirmation of temporary security check for outdoor tank storageFrom the date of completion of the inspection 19Each fire department4
Decree on the Regulation of Dangerous Goods8-4-2
Proviso
Approval of change of security inspection time14Each fire department4
Enforcement Order of the Disaster Prevention Law for Petroleum Complex16-1Certification of alternative measures for facilities or equipment that are effective for disaster prevention10
Ministerial ordinances concerning specific disaster prevention facilities and disaster prevention organizations in oil complexes, etc.6Certification of alternative measures to prevent spilled oil spills10
12Certification of alternative measures such as fire hydrants10
Explosives Control Law3Permits related to the manufacture and sales of explosives16
5Permit for sales and sales of explosives15
10-1Permission to change explosive manufacturing facilities, etc.14
11-1 provisoInstructions for storage outside the gunpowder storage area10
12-1Permission for installation, relocation or change of gunpowder storage14
Proviso of 13Permission for exemption from possession or possession of gunpowder storage10
15-1、15-2Completion inspection of explosives manufacturing facilitiesFrom the date of completion of the inspection 5
17-1Permit to transfer or transfer of explosives7 (Excluding the period required for inquiries to Public Safety Commission, Kanagawa Prefecture.)
17-7Rewriting of explosives transfer permit or transfer permit5
17-8Reissuance of explosives transfer permit or transfer permit5
24-1Permit to import explosives7
25-1Permit to consumption of explosives14 (excluding the period required for inquiries to Public Safety Commission, Kanagawa Prefecture)
27-1Permission to dispose of explosives7
28-1Authorization for establishment or change of harm prevention regulations10
29-1、29-5Approval for the establishment or change of security education plans10
35-1Security inspections of explosives manufacturing facilitiesFrom the date of completion of the inspection 5
Enforcement Regulations of the Explosives Control Law7-4 of 67Cancellation of designation of a person who should provide security education5
High Pressure Gas Safety Act5-1Permission to manufacture high-pressure gas15
14-1Permission to change facilities for the production of high-pressure gas13
16-1Permission for the establishment of first-class storage10
19-1Permission to change the location of first-class storage10
20-1Completion inspection of installation of facilities for production of high-pressure gas or first-class storageFrom the date of completion of the inspection 10
20-3Completion inspection of specific change work of facilities for production of high-pressure gas or first-class storageFrom the date of completion of the inspection 10
22-1Import inspection of high-pressure gasFrom the date of completion of the inspection 10
35-1Security inspection of specified facilitiesFrom the date of completion of the inspection 10
44-1, 48-1 (3), 48-1 (5), 49-1, 49-2, 49-49-4Inspection or reinspection of containers and accessoriesFrom the date of completion of the inspection 10
48-5Permission for special filling7
49-1、50-1、50-3Registration or renewal of container inspection stations11
54-1Notification of conformity with container standards pertaining to application for change of type or pressure of high-pressure gas to be filled in containers10
Law Concerning the Security of Liquefied Petroleum Gas and Proper Transactions3-1Registration of liquefied petroleum gas sales business13
29-1、32-1Certification or renewal of the Security Agency13
33-1Authorization of increase in the number of general consumers10
35-1Approval of the establishment or change of security business rules10
35 6-1Certification of liquefied petroleum gas distributors14
36-1Permission to install storage facilities, etc.13
37 2-1Permission to change storage facilities, etc.13
3-1 of 37Completion inspection of storage facilitiesFrom the date of completion of the inspection 10
37-4-1Permitted equipment13
37 4-3Permission to change equipment13
37 4-4Completion inspection of filling equipmentFrom the date of completion of the inspection 10
37 6-1Security inspection of allocating equipmentFrom the date of completion of the inspection 10

Inquiries to this page

General Affairs Bureau General Affairs Department Legal Division

Telephone: 045-671-2093

Telephone: 045-671-2093

Fax: 045-664-5484

Email address: so-hosei@city.yokohama.lg.jp

Return to the previous page

Page ID: 335-764-463

Menu

  • LINE
  • Twitter
  • Facebook
  • Instagram
  • YouTube
  • SmartNews