Here's the text.
Notification of
About notification based on the Water Pollution Control Law
Last update date April 1, 2024
Example of email
When setting up specific facilities, it is necessary to submit a report based on the Water Pollution Control Law.
Please refer to the report style table for the requirements of each report.
For consultation on notification, please contact us by e-mail or telephone first.
In addition, we can respond to web conferences, so please feel free to contact us.
Please send about three desired dates and times to mk-mizu@city.yokohama.lg.jp as shown in the example.
We will reply with the date and time, meeting ID, passcode, etc. that can be handled by this section. (The WEB conference system prepared by this section is ZOOM (free version).)
There is a possibility that you will have to wait at the counter, so please contact us in advance when you come to the agency.
Precautions for Preparation
Please note that we have reviewed a part of the style of notification of installation, use, change notification and abolition of use abolition from January 2024.
①seal is not required. (After December 28, 2020)
②If the notifier is a corporation, it is, in principle, the name of the representative of the corporation. When submitting registration form on behalf of the factory manager, etc., a power of attorney must be submitted. However, the legal responsibility lies with the representative.
③About drainage destination, please confirm in "public sewer common start area figure" of "daichan map" of Yokohama-shi administration map reporting system (outside site). (Confirmation method (PDF: 1,821KB))
④Please refer to the description method in the table for the description of each report. In addition, about notification of installation, use, change notice, please see the description example.
[Additional items at the time of submission]
⑤Please submit two copies of the notification documents.
⑥It is not possible to fill in with pencil or disappearing ballpoint pen.
⑦Please standardize registration form to A4 size as much as possible. For large-sized documents such as drawings, fold A3 size into A4 size.
Submission method (in principle, please use electronic application)
Submission method: [Recommended] Electronic application (outside site), (mail), (with bringing)
Submission: Green Environment Bureau Environmental Conservation Department Water and Soil Environment Division
Postal code: 231-0005
Address: 6-50-10, Honmachi, Naka-ku, Yokohama City, City Hall 27F
Phone number: 045-671-2489
Email address: mk-mizu@city.yokohama.lg.jp
Submission deadline
In the case of installation notification / change notification, construction related to installation and change is not possible for 60 days from the date of receipt of the notification.
However, construction can be started with a notice of shortening the implementation restriction period.
This notice will be issued in writing or electronic data (with an electronic signature).
The electronic signature uses the certificate of responsibility of the Local Government Organization Certification Infrastructure (LGPKI). Please use the "Public Personal Authentication Service (external site)" of the Local Government Information System Organization or the "SkyPDF Verification Service" of Skycom. (At this time, the certificate of responsibility is not registered in Adobe's AATL (Adobe Approved Trust List), so Adobe Acrobat displays "¥ at least one signature is a problem." Is valid.)
If you have any questions, please contact us.
Report style
Articles | Details of notification | Notification requirements | Style | Description method Example of description |
---|---|---|---|---|
Article 5 | Notification of installation | Paragraph 1 |
Please take a look first. |
|
Section 3 |
||||
Article 6 | Notification of Use | When a specific facility (including a designated area specific facility) is added, if the facility is currently installed, it will be notified within 30 days after it has been added. | ||
Article 7 | Notification of change | Changes pertaining to Article 5, Paragraph 1 |
||
Changes pertaining to Article 5, Paragraph 3 Change the structure, equipment, usage methods, and the system of import / exporting / unloading of hazardous substances specified facilities (except when discharging water into public water bodies) or designated facilities for harmful substances storage (including changes in drainage volume) When we do, we report 60 days before construction conduct. |
||||
Article 10 | Notification of Changes in Names (Note 1) | If any of the following changes are made, we will notify you within 30 days after the change. 1.Name, name, name and Address of the notifier; 2.Location due to changes in the name of the factory, business site number, etc. |
||
Notification of abolition of use | When we abolished use of specific facility, we report within 30 days after the abolition. | |||
Article 11 | Succession Notification (Note 1) | When a specific facility is transferred or borrowed, or inherited or merged, a notification will be made within 30 days after the succession. | ||
Article 14, Paragraph 3 | Notification of Pollution Load Measurement Method (Note 2) | In the following cases, we will notify you in advance. 1.When a business site is subject to the total amount regulation 2.When changing the measurement method |
||
Article 6, Paragraph 3 | Notification of pollution status and amount of discharged water by drainage system | If the location becomes a new designated area, notify us within 60 days. | ||
― | Start of use, etc. | Report within 15 days after the start of use of specific facilities, etc. | ||
― | Power of Attorney | This is required if proxy/agent other than the representative submits a notification. | No form | Example of description (word: 13KB) |
Note 1) This style is common to the Air Pollution Control Law, the Noise Control Law, the Vibration Control Law, the Water Pollution Control Law, and the Law Concerning Special Measures Law. |
In order to open PDF files, you may need a separate PDF reader.
If you do not have it, you can download it free of charge from Adobe.
To download Adobe Acrobat Reader DC
For inquiries to this page
Green Environment Bureau Environmental Conservation Department Water and Soil Environment Division
Phone: 045-671-2489
Phone: 045-671-2489
Fax: 045-671-2809
Email address: mk-mizu@city.yokohama.lg.jp
Page ID: 580-153-779